Loading...
DR8801-CS 890207 COPPELL PUBLIC WORKS -- lvI]~lvIORAN-DIJI~ TO: Steve Goram, Director of Public Work ~o.~~~ FROM: Steven M. Morton, Chief Public WorkskI~spec RE: Reopening of Freeport Pkwy. Steve, due to the wet and frigid weather conditions, it will be impossible to complete~ the construction of Freeport Pkwy. and reopen it to traffic by 2/15/89 for the following reasons in accordance with COG specifications. 1) Subbase cannot be frozen 2) Subbase mositure cannot be over 6% optimum, it is 12+ 3) Subgrades will have to dry out to make final grade & compaction 4) Concrete cannot be poured when temperature is 40° and falling 5) Air temperature must be 35° and raising 6) Air surrounding concrete must retain 50° for 5 days 7) Curing time shall be a minimum of 7 days from last pour prior to traffic being allowed on it 8) Traffic buttons and paint striping cannot be applied on until temperature is 40° plus and dry I am monitoring the weather and site conditions very closely. It looks like we will get a weather break in temperature this weekend (10th, llth), but it is predicted to rain or snow (9th - llth). If we do indeed get the weather break, they should be able to dry, compact, and make grade on the week of the 13th, form & pour on the week of the 20th, cover & cure on the week of the 27th and reopen Freeport Pkwy. sometime in the week of March 6th. Please bear-in-mind that any rain the occurs after the 13th affects this schedule, two days to every one rain day and any precipitation that freezes affects the schedule 3 days to 1, due to penetration of moisture as it thaws. I will have Buckelew change the signs t~ng 3/10~ will also Co. and the Papers upon your ~ to proceed. noti~ the Cable SMM/bb ~/~-m~ ~/0 ' ~'-~ /_____The City With A Beautiful Future P.O. Box 478 Coppell, Texas 75019 214 - 462 - 0022 NEWS RELEASE Date: 2/7/89 Date of Release: Immediate Release Due to the continued inclement weather conditions, the reopening of Freeport Pkwy. scheduled for 2/15/89 will be delayed until 3/10/89. We are sympathetic to the inconvience this places ont he motorist and are endeavoring to complete this construction as quickly as weather conditions will allow. Thank you for your patience and cooperation. Steven M. Morton Chief Public Works Inspector cc: City Manager City Secretary's Office