Loading...
DR8801-CS 890207 (2)February 7, 1989 Mr. David Sorrell Buckelew Construction Co. P. O. Box 6318911 Richardson, Texas 75083 Re: Bethel Road Drainage Improvement Quantity Adjustment, Item 31 88157.04 Dear Mr. Sorrell: Steve Morton has confirmed that the existing 16" water line was concrete encased at Station 0+35, thus requiring the connection being moved to station 0+29. As a result of this extra work, we agree to increase item 31 by 6 L.F. The 16" water line as bid was profiled complete with beginning and ending stations. On this basis, a quantity increase for item 31 for pipe slope will not be allowed. Please do not hesitate to call if we can answer any questions. Sincerely, . ~ ~y~fe~ L. Sit~for~i,l/P' E. Director, Civil Ehgineering CLS/np attachment cc: Steve Morton