Loading...
TR0301-CN070420 CITY OF COPPELL CHANGE OR EXTRA WORK ORDER PROJECT: Traffic Signal Installation Project # TR 03-01 (A) Belt Line Road @ MacArthur Blvd. & (B) MacArthur Blvd. @ Bethel School Rd. CONTRACTOR: Roadway Solutions, Inc. OWNER: City of CoppeU CHANGE ORDER NO.: Three (3) DATE: April 18, 2007 Item Description Quantity Unit Unit Price Total 2 EA 750.00 $1,500.00 Revised Contract time of completion 275 Calendar Days The contractor hereby accepts this Contract adjustment as a final and complete adjustment in full accord and satisfaction of all past and future liability originating under any clause in the Contract by reason of this revision to the Contract. 1~ '0t- Recommended" 'ty ~ineer /'.~ ADD: Naztec TS2 Ethernet Upgrades for NEW unused controllers Additional Arrow Additional Word 4 Inch Thermo 1 1 80 EA EA LF 135.00 165.00 4.00 Total Revision to Contract Amount Previous contract amount Net increase in contract amount Change Order #1 Net increase in contract amount Change Order #2 Net increase in contract amount Change Order #3 Revised contract amount Net increase in contract time of completion 4',cJ.'" Date kl't> ? Date Page I of I $135.00 $165.00 $320.00 $2,120.00 $298,042.00 8,006.80 4,800.00 2,120.00 $312,968.80 o Day 'hZIJ,tJ7 Date