ST9902-CN070420 CITY OF COPPELL CHANGE OR EXTRA WORK ORDER PROJECT: West Sandy Lake Road Project # ST 99-02A CONTRACTOR: Tiseo Paving Company OWNER: City of Coppell CHANGE ORDER NO.: Six (6) DATE: April 18, 2007 Item Description Extend Confirmation lights @ Royal Ln., Freeport, and N. Coppell Rd. Total Revision to Contract Amount Change Ord. #6 Quantity Unit Unit Price Total ADD: 1 LS 1,755.00 $1,755.00 Original contract amount Net increase in contract amount Change Order # 1 5/9/06 Net increase in contract amount Change Order # 25/17/06 Net increase in contract amount Change Order # 3 ] 1/2/06 Net increase in contract amount Change Order # 4 1/8/07 Net increase in contract amount Change Order # 5 2/15/07 Net increase in contract amount Change Order # 6 4/18/07 Revised contract amount Net increase in contract time of completion Revised Contract time of completion $1,755.00 $3,961,787.00 15,635.00 2,900.00 6,737.00 2,250.00 2,090.00 1,755.00 $3,993,154.00 2 Day 312 Calendar Days The contractor hereby accepts this Contract adjustment as a final and complete adjustment in full accord and satisfaction of all past and future liability originating under any clause in the Contract by reason of this revision to the Contract. ~ ~ - ""-- Recomme oed by Ken G m, P.E., City Engmeer .r-- .- .,. AccePte~ Jim Witt, City Manager ~~~ Agreed to by Tiseo Paving Company 4-. ,g., Date Y/~' (7 Date i.f-c20-o 7 Date Page 1 of 1