WA0001-CS000225 (2) SHIMEK, JACOBS & FINKI,EA, L.L.P.
CONSULTING ENGINEERS
8333 Douglas Avenue, #820 Dallas, Texas 75225-5816 Fax (214) 361-0204 Phone (214) 361-7900
ROSS L. JACOBS, P.E.
RONALD V. CONWAY, P.E.
JOHN W. BIRKHOFF, P.E.
JOE R. CARTER, P.E.
GARY C. HENDRICKS, P.E. February 25, 2000
1. c. FINKLEA, P.E.
PAUL A. CARLINE, P.E.
MATT HICKEY, P.E.
Advantage Contract Services, Inc.
7150 Almeda Genoa Rd.
Houston, Texas 77075
Re: City of Coppell
Repainting of the 1.5 Million Gallon Elevated Storage Tank
Gentlemen:
We are handing you two fully executed copies of your contract with the City of Coppell, for the repainting of
the interior of the 1.5 million gallon elevated storage tank. These sets are for your files.
In addition we are handing you five sets of plans and specifications for your use during the construction phase
of the project. Please be sure to have at least one set on the project site at all times.
Finally, the contract documents state the completion date for this project is April 25,2000 assuming a February
25th Notice to proceed by the City of Coppell. Due to another ongoing water system project, the notice to
proceed for this project must be postponed at least one week. As provided in the contract documents, the
contract completion date will be adjusted accordingly. Therefore, a notice to proceed will not be issued today.
We will keep you informed of the progress on the other water system project and provide you with the City 's
anticipated schedule for starting this project as soon as it is known.
If you have any questions or need additional information, please do not hesitate to contact this office.
SIn H '
._Sincerel~_x~~
Enclosures . te~
cc: Mr. Kenneth M. Griffin, P.E.
/Mr. Glenn Hollowell, P.E.
\xsjfisjLvo12~projectsklerical\coppell\1999-176\letters\const\kXnotice to proceed delayed.doc