REPORT OF REINFORCING
STEEL PLACEMENT OBSERVATION
MacArthur Vista Center
670 N. MacArthur Boulevard
Coppell, Texas
REPORTED TO: MacArthur Vista, LP
12201 Merit Drive, Suite 170
Dallas, Texas 75251
ATTN: Mr. Alen Hinckley
REPORT NO. 32
REPORT DATE: 04-23-07
REG PROJECT NO. 14082
DATE OBSERVED: 03-30-07
TECHNICIAN: D. Rico
PAGE: 1 of 1
CONTRACTOR: Royal General Contractors, Inc.
Items Observed: Retaining wall: 30-55'S, 30-55'W from N.W. building
corner
Light pole bases: 70'S, 70'E and 45'S, 60'W from S.W.
building corner.
Reference Plans or Notes Used: Sheets A101 and RFI 613
Comments: All the deviations noted on 3-29-07, Report No. 31 were
corrected.
OThere were no deviations noted.
The reinforcing steel placed at the above referenced locations was observed with
respect to the referenced portions of the contract documents.
Mail
Distribution: (1) MacArthur Vista, LP/
Mr. Alen Hinckley
(1) City of Coppell/Mr. Lee Stone
(1) City of Coppell/Mr. Rick O'Dell
(1) Daniels & Associates/
Mr. Brent Lovelady
(1) Royal General Contractors/
Mr. Bob Fowles
(1) Royat General Contractors/
Mr. Micah Corn
(1) UBSE/Mr. Gary Ten Eyck
Submitted by:
REED ENGINEERING GROUP, LTD.
Original Signed By
Ronald F. Reed, P.E.
BW/rs
2424 STUTZ DR. SUITE 400 DALLAS, TX 75235 rep [214] 350 5600 Fax. [214] 350 0019
REEL7 I Er"lGlr'IEER11-"1G
GEOTECHNICAL AND i G R O U P
ENVIRONMENTAL CONSULTANTS
REPORT OF REINFORCING
STEEL PLACEMENT OBSERVATION
MacArthur Vista Center
670 N. MacArthur Boulevard
Coppell, Texas
REPORTED TO: MacArthur Vista, LP
12201 Merit Drive, Suite 170
Dallas, Texas 75251
ATTN: Mr. Alen Hinckley
REPORT NO. 31
REPORT DATE: 04-23-07
REG PROJECT NO. 14082
DATE OBSERVED: 03-29-07
TECHNICIAN: D. Rico
PAGE: 1 of 1
CONTRACTOR: Royal General Contractors, Inc.
Items Observed: Retaining wall: 30-55'S, 30-55'W from N.W. building
corner.
Light pole base: 70'S, 70'E and 45'S, 60'W from S.W.
building corner.
Reference Plans or Notes Used: Sheets A101 and RFI G13
List Deviations Noted: 1) #3 at 12" O.C. vertical and horizontal rebar missing at
exterior face of retaining wall.
2) Six #6 vertical bars were placed in light pole bases
instead of eight #6 vertical bars.
The noted deviations were reported to: Superintendent
xOThe noted deviations were not corrected.
The reinforcing steel placed at the above referenced locations was observed with
respect to the referenced portions of the contract documents.
Mail
Distribution: (1) MacArthurVista, LP/
Mr. Alen Hinckley
(1) City of Coppell/Mr. Lee Stone
(1) City of Coppell/Mr. Rick O'Dell
(1) Daniels & Associates/
Mr. Brent Lovelady
{1) Royal General Contractors/
Mr. Bob Fowles
(1) Royal General Contractors/
Mr. Micah Corn
(1) UBSE/Mr. Gary Ten Eyck
Submitted by:
REED ENGINEERING GROUP, LTD.
Original Signed By
Ronald F. Reed, P.E.
BW/rs