Loading...
DR8801-CS 881111November 11, 1988 TO: FROM: RE: COPPELL PUBLIC WORKS MEMORANDUM Steve Goram, Director of Public Works Steven M. Morton, Chief Developmental Ins Bethel Rd~ Drainage Improvements / Status ~'~ Steve, Buckelew wili be delivering detour signage on Saturday. Signs will be bagged. On Monday, the Contractor and myself will verify the placement of the si§nage as shown on the detour plans. After any adjustment or corrections (if any) have been completed, the bags will be removed, barricades will be put~.in place, and.I Freeport will be closed. If f~r any. reason the.~Signage~ can not' be brought into conformancy with 'the detour plans, it will not be closed until it can be brought up to specifications. I have notified Paul Lipscomb of this schedule and ask him to have. a representative there. I also spoke to Paul in reference to some loose ends, primarly Trench Safety Plan, Contract Quantity, and CPM charts. Paul said he will have the above items delivered today. Russell will be forwarded a set of Trench Safety Plans for his review prior to excavation. The major loose end is the testing of materials (concrete), density, and proctors. These tests (by contract) will be.our responsibility and expense. We have not selected a lab. George Holland has been our Geotech representative for over 1½ years. I will be getting George a set of plans Monday (after detour) and he will give us a quote to provide services. In April, Clyde Sifford contacted McClelland Laboratory on a ball park price, they gave an estimate of $12,000.00. This was phoned in quantities, they have not seen the plans. I will see about gettin them a set of plans for a comparative quote on Monday. We can also include Hooper Engineering, if necessary. SMM/bb