Loading...
DR8802-CS 920327 RHODE CONSTRUCTION CO. ALL TYPES PIPELINE CON~'FRUCTION ° °' 2031 JOHN WEST ROAD SUITE 121 PH 214-327-79M, DALLAS, TEXAS 75228 FAX 214-327-_ _~5_ _ March 27, 1992 Mr. Kenneth M. Griffin, P.E. City Engineer City of Coppell P.O. Box 472 Coppell, TX 75019 Re: Dear Mr. Griffin: Please accept this letter as our second request for an extension of time on the above referenced project in response to our phone conversation of March 20, 1992. The following information is per your request to receive additional information concerning our first request of a time extension dated March 11, 1992. Our request for an extension of time is based on the contract between Rhode Construction Co. and the City of Coppell, specifically Page 6.9, Paragraph 4.02 of the General Conditions. This paragraph states in fact that the Contractor will be entitled to an extension of time due to unavoidable causes or casuses beyond the Contractor's control, certainly weather is beyond the Contractor's control. Further, there is no statement in the Contract that excludes weather as a cause. Therefore, we believe that the abnormal amount of rainfall is grounds for the extension of time as requested. Also, as you are aware, the Kaye Street Drainage Project has been constructed under extreme adverse conditions as relating %o property owners and right-of-ways. These conditions were not created by Rhode Construction Co., we as the Contractor inherited these problems which we have handled in a sedulous and professional manner, which can be witnessed by the Land Owner's and also, by Mr. Larry Davis, Inspector for the City of Coppell. The time allotted for the above referenced project was 60 calendar days. During these 60 calendar days, there were possibly 43 working days total. We have worked 36 full days and 2 half days. In this same period of time, it has rained 21 days out of the 60 days and as you know, after a rain it will take one or two days afterward for the ground to dry enough for work to resume to normal production. On this project, we worked in the rain in order to try to complete the project within the alotted time frame. In order to do the job, 10 days were used excavating the entire right-of-way down 1½" to 2" deep in order to find ground that was hard enough to operate the equipment on. All this mud had to be hauled out and stockpiled and will be hauled back in to fill %he right-of-way which takes additional time. Our production was slowed to 20% to 25% of normal production for many of the 60 days alotted due to the above. Again we would ask you to consider extending our completion date to April 7, 1992. If additional information is needed, please contact me. Sincerely, Bradley W. Lands cc: Mr. Alan D. Ratliff, City Manager