Amberpoint 1A-CS070711
iii HaIff Associates
8616 Northwest Plaza Drive
Dallas, Texas 75225-4292
(214) 346-6200
Fax (214) 214-361-5573
LETTER OF TRANSMITTAL
TO:
Mr. Ken Griffin, P.E.
City of Coppell Engineering Dept.
255 Parkway Blvd, P.O. Box 478
Coppell, TX 75019
DATE:
07/11/07
AVO:
25027
PROJECT: Staples Expansion, Lot 1 AR, Block A
Amberpoint Bus. Park at Coppell
Coppell, TX
FROM: Cody Graham, E.I.T.
cgraham @halff.com
VIA:
Courier
WE ARE SENDING YOU [gI Attached:
D Shop Drawings [gI Prints
D Copy of letter D Change order
D Under separate cover:
D Plans D Drawings
D Submittal D Other:
D Specifications
THESE ARE TRANSMITTED as checked below:
[gI For approval
D For your use
D As requested
D For review/comment
D Approval as submitted
D Approved as noted
D Returned for corrections
D Other:
D Resubmit _ copies for approval
D Submit _ copies for distribution
D Return _ corrected prints
ITEMS SENT:
7 - Copies of signed and sealed Engineering Construction Plans tor Staples Fulfillment Center Expansion.
7 - Copies of signed and sealed Early Grading Package for Staples Fulfillment Center Expansion.
1 - Comment response letter.
1 - Letter requesting variance of pavement standards.
1 - Copy of Terracon Geotechnical Eng. Report #94075192 for subject project.
COMMENTS:
Ken, attached is our signed and sealed engineering submittal for the above project. Please call 214.346.6315 if
you have any questions or problems, as we are trying to have approved plans this week. Thanks!
SIGNED: Cody Graham, E.I.T.
PREPARED BY: Halff Associates
COPIES:
[gI File
[gI Owner
D Contractor
D Other:
1:\25000s\25027\admin\lot\lOT 07-11-07 KG.doc
III HaIff Associates
ENGINEERS. ARCHITECTS. SCIENTISTS. PLANNERS. SURVEYORS
8616 NORTHWEST PLAZA DRIVE
DALLAS, TEXAS 75225
(214) 346-6200
FAX (214) 739-0095
July 11,2007
AVO 25027
Kenneth M. Griffin, P.E.
Director of Engineering/Public Works
City of Coppell Engineering Department
255 Parkway Blvd.
Coppell,Texas 75019
Re: Staples Fulfillment Center Expansion, Lot lAR, Block A, Amberpoint Bus. Park at Coppell
Request Variance for Site Pavement to Waive Lime Stabilized Subgrade
Dear Mr. Griffin:
On behalf of Staples, Inc. we are requesting a variance from the standard City of Coppell pavement
specification for the Staples Fulfillment Center Expansion project at Amberpoint Business Park Lot
lAR, Block A.
We request a variance for the proposed car parking areas to use 5-inches of 4,000 psi concrete
placed over unstablized subgrade; in lieu of the Coppell standard of 5-inches of Class "C" concrete
(3,600 psi) over lime stabilized subgrade.
We request a variance for the proposed truck traffic areas to use 7-inches of 4,000 psi concrete
placed over unstablized subgrade; in lieu of the Coppell standard of 6-inches of Class "C" concrete
(3,600 psi) over lime stabilized subgrade.
If you have any questions or require additional information, please call me at (214) 346-6244.
Sincerely,
HALFF ASSOCIATES, INC.
JJt/!L//ffi~
Mark W. McGraw, P.E.
Project Manager
cc: John Whitney, Staples, Inc., w/enc.
enc: Terracon Geotechnical Engineering Report No. 94075192, dated June 5,2007
DALLAS . FORT WORTH . HOUSTON . McALLEN . AUSTIN . FRISCO . SAN ANTONIO . FLOWER MOUND
TRANSPORTATION . WATER RESOURCES . LAND DEVELOPMENT . MUNICIPAL . ENVIRONMENTAL . STRUCTURAL
MECHANICAL . ELECTRICAL . SURVEYING . GEOGRAPHIC INFORMATION SYSTEMS
ARCHITECTURE . LANDSCAPE ARCHITECTURE . PLANNING
III HaIff Associates
ENGINEERS. ARCHITECTS. SCIENTISTS. PLANNERS. SURVEYORS
8616 NORTHWEST PLAZA DRIVE
DALLAS, TEXAS 75225
(214) 346-6200
FAX (214) 739-0095
July 11,2007
Ava 25027
Michael Garza, EJ.T.
Graduate Engineer
City of Coppell Engineering Department
255 Parkway Blvd.
Coppell,Texas 75019
Re: Staples Fulfillment Center Expansion, Lot 1AR, Block A, Amberpoint Bus. Park at
Coppell Construction Plan Review Comments dated June 21, 2007
Dear Mr. Garza:
We offer the following responses to your June 21, 2007 comments regarding the subject
project:
1. Location map has been revised.
2. Legal has been revised.
Sheet Clo01
3. More clarification for fire hydrant and water service protection was added to sheet.
Sheet C2.01
4. Subgrade material has been specified. A copy of the geotechnical report and letter
requesting a variance for pavement subgrade is included in this submittal.
Sheet C3.01
5. Existing elevations, specifically along Sandy Lake Road, were tied in a 3/29/07
topographic survey of the site. Survey was field-checked. Existing curb and gutter
elevations along Sandy Lake Road were added to this sheet for clarity.
Sheet C5.01
6. Water line plugs locations have been clarified. Fire hydrant to remain is shown more
clearly.
DALLAS . FORT WORTH . HOUSTON . McALLEN . AUSTIN . FRISCO . SAN ANTONIO . FLOWER MOUND
TRANSPORTATION . WATER RESOURCES . LAND DEVELOPMENT . MUNICIPAL . ENVIRONMENTAL . STRUCTURAL
MECHANICAL . ELECTRICAL . SURVEYING . GEOGRAPHIC INFORMATION SYSTEMS
ARCHITECTURE . LANDSCAPE ARCHITECTURE . PLANNING
iii HaIff Associates
ENGINEERS. ARCHITECTS. SCIENTISTS. PLANNERS. SURVEYORS
Michael Garza, E.I.T.
City of Coppell
July 11,2007
Page 2
Sheet C6.01
7. Detail of grate inlet protection is shown on sheet C6.02. We do not foresee any
conflict. Construction vehicles will drive beside or over grate inlet.
If you have any questions or require additional information, please call me at (214) 346-6244.
Sincerely,
HALFF ASSOCIATES, INC.
jIJ./ i// //pL
Mark W. McGraw, P.E.
Project Manager
cc: John Whitney, Staples, Inc., w/enc.
enc: Letter requesting variance to pavement subgrade.
Terracon Geotechnical Engineering Report No. 94075192, dated June 5,2007
GEOTECHNICAL ENGINEERING REPORT
STAPLES EXPANSION
SWQ OF SANDY LAKE ROAD AND NORTH POINT DRIVE
COPPELL, TEXAS
REPORT NO. 94075192
June 5, 2007
Prepared for:
STAPLES, INC.
Framingham, Massachusetts
Prepared by:
lrerracon
Dallas,Texas
lrerracon
June 5, 2007
Consulting Engineers & Scientists
Staples, Inc.
500 Staple Drive
Framingham, Massachusetts 01702
8901 Carpenter Freeway, Suite 100
Dallas. Texas 75247
Phone 214.630.1010
Fax 214.630.7070
www.terracon.com
Attn: Mr. John F. Whitney
Re: Geotechnical Engineering Report
Staples Expansion
SWQ of Sandy lake Road and Northpoint Drive
Coppell, Texas
Terracon Report No. 94075192
Dear Mr. Whitney:
In accordance with your authorization, Terracon has completed its geotechnical engineering
report at the above referenced site. The work was accomplished in accordance with the
general scope outlined in Terracon's Proposal No. P07940733 dated May 2, 2007. The
results are presented in the attached report.
Please do not hesitate to contact us if there are any questions. We stand ready to assist
during the design or construction phase of the project.
We appreciate the opportunity to provide these services.
Sincerely,
lrerracon
-"',...."",
_--:;~ OF .,. \\,
:...~ ....... S'J...'I.
'" -, .' *. -r..., t
,:' CO ..' .... '($1 ,
t: '.*~
f . ............... ..* ~
I!. ..~~~!?~~MED.... ~
~ -<l '. ( 9492;'" r{1~S!- 2t> 07
" ~ . /. <:). Q;;-,
'40....- ".9E'NS~." ,~~
. ~J' . .. .... ,,':\,...,:-
,,\\SlmJAl f.~~--
,,""........--
CC: Richard Nordyke/O'Brien Associates
Keith LesliefTechniStructures
Delivering Success for Clients and Employees Since 1965
More Than 80 Offices Nationwide
llerracon
TABLE OF CONTENTS
Page
Letter of Transmittal.... .................. ................. ................... .................. ............ ....................... i
INTRODUCTION ....................... .... ....... ............. ............... ........... ......... ..... .......... .................1
PROJ ECT DESCRI PTION ......... .......... ........... ............. ................ ....................... ......... .........1
SITE EXPLORATION PROCEDU RES .......... .............. ....... ............ .................... ......... .........1
Field Exploration.. ............. ..... ......... ...................... ........... ......... ........ .............. ...........1
Laboratory Testing.............................. ......... ......................................... ..................... 2
SUBSURFACE CONDITIONS.. .... .......... ..... ....................... ...... ... ..... ......... .......... ................. 3
Soil Conditions ................................. .............. ...........................................................3
Groundwater Conditions............................................................... .............................3
ANALYSIS AN D RECOM MENDA TIONS .. ................................. ................ ....... ...................4
Geotechnical Considerations................ ........ ........................................ .....................4
Drilled Shaft Foundation System................ ......................................... ........... ...........4
Underreamed Shafts..................... ........ ...............................................................4
Soil Induced Uplift Loads ................ ....... ................................. ........ ........ ........... ..5
Drilled Shaft Construction Considerations..................................... .......................5
Grade Beams/Pier Caps ..................... ............................................ ........ .......... ...6
Seismicity ............ ............................... ........................................... ......................6
Floor System.............................. ........ ....... .......................................... ................... ...6
Structural Floor Slabs ......................... ............... ............................ ......................7
Floor Slabs on Modified Subgrade .... ..................................... ....... ................. ...... 7
Excavation and Replacement............ ...... ........................................... .................... ...8
Select Fill.. .............................................. ............................................................... ....8
Site Grading...................................................................................... ........................ 9
Utilities...... .......................................... .... ..................................... ...... ........... ......... .... 9
Surface Drainage................................. ................................................................. ...1 0
Surface Pavement Recommendations............................................. ..................... ...1 0
Pavement Subgrades ...................... ............................................................... ...1 0
Pavement Sections.................... ................. .......................................................11
Preventative Maintenance........... ...................................................................... 12
GENERAL COM MENTS.. .... ...... .... ........ ....... ................ ....... .... ... ........ .... ................ ............12
APPENDIX
Figure
Boring Location Diagram........................... ................ ....... ..................................................... 1
Log of Boring.. ....................... ............ ....... ............... ................ .... ......... ...... ......... ........ 2 and 5
General Notes....................................................................................................................... 6
Unified Soil Classification System.... ............. ........... ....... ....................... .... .......... ........ .........7
lrerracon
GEOTECHNICAL ENGINEERING REPORT
STAPLES EXPANSION
SWQ OF SANDY LAKE ROAD AND NORTH POINT DRIVE
COPPEll, TEXAS
REPORT NO. 94075192
June 5, 2007
INTRODUCTION
A new expansion of Staple warehouse with associated surface parking is planned at the site
located in the southwest quadrant of Sandy Lake Road and Northpont Drive in Coppell,
Texas. This report describes the subsurface conditions encountered and provides
recommendations regarding the geotechnical design and construction of foundations and
floor slabs for the proposed building and associated surface parking areas. In addition,
general earthwork recommendations are provided. Our scope of services included drilling
and sampling 4 borings, laboratory testing, and engineering analyses.
PROJECT DESCRIPTION
The proposed expansion consists of a tiltwall warehouse building of about 148,000 SF
footprints. Surface parking is planned surrounding the warehouse. The expansion will be
on the north side of the existing Staple warehouse building. The column loads of the
building are anticipated to be about 150 kips, or less.
Currently, the site is vacant land with weeds, native grass and some small to large sized
trees. Based on NCTCOG topographic map, the existing surface elevations of the site vary
from about 518 to 520 feet. The planned finished floor (FF) elevation of the building will be
521.5 feet. Therefore, about 1 Y2 to 3Y2 feet of fill will be required to prepare proposed
building pad.
SITE EXPLORATION PROCEDURES
Field Exploration
Four borings were drilled on May 17, 2007 at the approximate locations shown on the
Boring Location Diagram, Figure 1, in the Appendix. The borings were located in the field
by a representative of Terracon using a site plan provided by the client. The boring
locations are considered to be approximate.
The results of the field exploration program are presented on the Logs of Borings, Figures 2
through 5, in the Appendix. General Notes for terms and abbreviations used in the boring
logs are presented on Figure 6. Field logs of the borings were prepared by the drill crew.
These logs included visual classifications of the materials encountered as well as
interpretation of the subsurface conditions between samples. The boring logs included with
Geotechnical Engineering Report
Staples Expansion
Coppell, Texas
Terracon Report No. 94075192
June 5, 2007
llerracon
this report represent the engineer's interpretation of the field logs and include modifications
based on laboratory evaluation of the samples.
A truck-mounted auger-drilling rig was used to advance the boring. Samples of the soils
encountered in the boring were obtained using thin-walled tube sampling procedures. The
samples were tagged for identification, sealed to reduce moisture loss, and taken to the
laboratory for further examination, testing, and classification.
Disturbed samples of soil were obtained with a split-spoon sampler in conjunction with the
Standard Penetration Test (SPT). The test employs a 140-pound hammer that is dropped a
distance of 30 inches, driving the split spoon sampler into the subject material. The number
of blows required for 18 inches of penetration is recorded and value for the last 12 inches, or
the penetration obtained from 50 blows, is reported as the Standard Penetration resistance
(UN value") on the boring log.
Laboratory Testing
The Logs of Boring and samples were reviewed by a geotechnical engineer who selected
soil samples for testing. Tests were performed by technicians working under the direction of
the engineer. A brief description of the tests performed follows.
Plastic and liquid limit tests (Atterberg limits) were performed on selected samples from the
borings. These tests were used in conjunction with moisture content measurements to aid
in classifying the soils in accordance with the Unified Soil Classification System (USCS).
The USCS is summarized on Figure 7 in the Appendix. Absorption swell tests were
performed on selected samples of the cohesive materials. These tests were used to
quantitatively evaluate volume change potential at in-situ moisture levels. Shear strengths
of cohesive soils were estimated by field pocket penetrometer and laboratory unconfined
compressive strength tests performed on selected samples.
The results of the laboratory tests are presented on the Logs of Borings. Results of the
swell tests are presented in Table 1.
Boring Depth Liquid Plasticity Initial Final Surcharge Swell
Limit Index Moisture Moisture
No. (feet) % % (%) (0/0) (pst) (0/0)
B-1 2-4 58 38 20 23 300 0.2
B-2 19-20 - - 17 22 1,500 2.3
B-4 8-10 34 19 12 19 900 0.8
TABLE 1 . SUMMARY OF SWELL TESTS
2
Geotechnical Engineering Report
Staples Expansion
Coppell, Texas
Terracon Report No. 94075192
June 5, 2007
llerracon
SUBSURFACE CONDITIONS
Soil Conditions
The conditions encountered at the boring locations are depicted on the Logs of Boring.
Descriptions of each stratum with its approximate depth and thickness are provided. The
stratum depths pre referenced from the ground surface present at the time of drilling.
Stratification boundaries on the boring logs represent the approximate location of changes in
soil types; in-situ, the transition between materials may be gradual. A brief discussion of the
stratigraphy indicated by the exploration program is presented below.
Fill materials consisting of brown and dark brown sandy clays with trace amounts of sand
and gravel were encountered in Borings B-1 and B-3 to a depth of 2 feet below grade.
Visually, the fill is classified as CL by the USCS. The clay fills were stiff to hard in
consistency.
Below the fill and existing grade, dark brown, brown and tan clays with trace amounts of
calcareous nodules were encountered in the borings to depths of 4 to 13 feet. These clays
had Liquid Limits (LL's) ranging from 53 to 58 percent and Plasticity Indices (PI's) ranging
from 33 to 38. These soils are classified as CH by the USCS. The clay soils were stiff to
hard in consistency.
Tan and gray silty clays with trace amounts of sand, calcareous nodules and deposits were
next encountered at depths of 4 to 13 feet and they extended to depths of 14 to 22 feet.
These clays had LL's ranging from 28 to 40 percent and PI's ranging from 10 to 22. These
soils are classified as CL by the USCS. The clay soils were very stiff to hard in consistency.
Below tan and gray silty clay, tan sandy clay with trace amounts of silt was encountered at a
depth of 14 feet in Boring B-4 and it extended to a depth of 22 feet. Visually, this soil is
classified as CL by the USCS. The sandy clay was very stiff in consistency.
Tan sand was next encountered at depths of 17 to 22 feet below grade. This sand had
some gravel, and became cemented and slightly cemented below 22 feet. The cemented
sand extended to boring termination depths of 25 feet below grade.
The surficial clay soils encountered at this site are considered highly to moderately active
with respect to moisture induced volume changes. Active soils can experience significant
volume changes (expansion or contraction) with fluctuations in their moisture content.
Groundwater Conditions
The borings were advanced in the dry using auger drilling techniques, which allows short-
term groundwater observations to be made while drilling. Groundwater seepage was not
observed in the borings during and upon completion of drilling.
3
Geotechnical Engineering Report
Staples Expansion
Coppell, Texas
Terracon Report No. 94075192
June 5, 2007
lrerracon
Groundwater conditions may be different at the time of construction. Groundwater
conditions may change because of seasonal variations in rainfall, landscape irrigation, and
runoff.
ANALYSIS AND RECOMMENDATIONS
Geotechnical Considerations
Highly to moderately active soils were encountered in the borings. The results of the swell
tests performed on selected soil samples of the clay soils indicate that at their present
moisture levels the soils are considered relatively stable with regard to post construction
moisture induced volume changes. This could change if the soils are allowed to desiccate
prior to construction. We estimate the potential magnitude of post-construction heave at this
site to be on the order 3 to 4 inches for dry subgrade conditions.
Shallow or near surface footings are subject to differential movements due to moisture
induced volume changes in the site soils. A positive means to reduce the potential for
foundation movement would be to support the structure on a foundation system bearing
below the zone of seasonal moisture variation. The use of drilled and underreamed
reinforced concrete shafts situated in the overlying tan silty clay and clay at a depth of about
12 feet below existing grade, should perform satisfactorily.
If floor slab movements must be limited to less than one inch, a floor system structurally
suspended above the subgrade is recommended. If movement of one inch is acceptable.
floor slab on subgrade soils at their current moisture levels can be used. If the soils become
dry, subgrade soils should be modified as discussed in this report. It should be noted that
there is a risk that 1-inch of movement can result in unsatisfactory performance. Some of
the risks that can affect performance include uneven floors, floor and wall cracking, and
sticking doors.
Asphaltic concrete pavement or Portland cement concrete pavement can be used at this site.
If asphaltic concrete is used, the subgrade should be stabilized with lime.
Geotechnical recommendations for the building foundation, floor slab subgrade preparation,
earthwork and pavement are presented in the following report sections. These should be
reviewed when the grading plan is available.
Drilled Shaft Foundation System
Underreamed Shafts
Drilled and underreamed shafts should be situated in the tan silty clay and clay strata at a
depth of about 12 feet below existing grade. An allowable bearing pressure of 5,000 psf
(pounds per square feet) is recommended.
4
Geotechnical Engineering Report
Staples Expansion
Coppell, Texas
Terracon Report No. 94075192
June 5, 2007
1rerracon
Underreamed shafts should have a minimum base to shaft diameter ratio of 2 to 1 to resist
the uplift loads described below. In addition, the bell diameter should be a minimum of 36
inches larger than the straight shaft portion. A minimum shaft diameter of 18 inches is
recommended.
We recommend that underreamed shafts be maintained a minimum edge to edge spacing of
one underream diameter, based on the larger of the two. Closer drilled shaft spacing should
be evaluated to determine if reductions in the allowable bearing pressures should be made
to control settlement.
About 70 to 80 percent of the foundation settlement of properly constructed underreamed
shafts is expected to occur as the shafts are loaded. The total settlement is estimated to
range from % to 1 percent of the underream diameter. Differential settlements of equally
loaded drilled shafts are expected to range from % to % of the total settlements.
Soil Induced Uplift Loads
The shafts will be subject to uplift because of heave in the overlying clay soils. The
magnitude of these loads varies with the shaft diameter, soil parameters, and particularly the
in-situ moisture levels at the time of construction. The shafts must contain sufficient
continuous vertical reinforcing to resist the net soil induced uplift load.
The uplift load can be approximated by assuming a uniform uplift of 1,200 psf over the shaft
perimeter for a depth of 8 feet in the soils at their current moisture conditions.
Drilled Shaft Construction Considerations
The drilled shafts should be installed in accordance with ACI 336. Excavation for the shafts
should be maintained in the dry. Concreting should closely follow excavation to reduce
potential caving and/or seepage problems. Close coordination of excavation and concreting
could be required due to groundwater seepage or caving soils. Care should be taken not to
undermine the existing foundations during construction of the building expansion.
The top of the drilled shafts should be cast without any top enlargement that can result in
increasing the soil uplift forces acting on the drilled shafts. The enlarged top or
umushroomed shaped" top drilled shafts should be cut away to the nominal shaft diameter
before grade beams or panels are placed.
The concrete should have a slump of 6 inches plus or minus 1 inch and be placed in a
manner to avoid striking the reinforcing steel during placement. Close coordination of
excavation and concreting will serve to reduce potential caving of the underreams.
The drilled shaft design recommendations provided in this report are based on proper
construction procedures. including maintaining a dry shaft excavation and proper cleaning of
5
Geotechnical Engineering Report
Staples Expansion
Coppell, Texas
Terracon Report No. 94075192
June 5, 2007
lrerracon
bearing surfaces prior to placing reinforcing steel and concrete. All drilled shaft installations
should be inspected by qualified geotechnical personnel to help verify the bearing stratum,
the design penetration, and perform related duties.
Grade Beams/Pier Caps
The drilled shafts should support all grade beams. A minimum void space of 6 inches is
recommended between the bottom of grade beams and pier cap extensions, and the
subgrade. This void will serve to reduce distress resulting from swell pressures generated
by the clays. Structural cardboard forms are one acceptable means of providing this void
beneath cast-in-place elements. Soil retainers should be used to help prevent the filling of
the void with soil.
The grade beams should be formed rather than cast against earth trenches. Backfill against
the exterior face of grade beams should be properly compacted onsite clays. Compaction
should be a minimum of 93 percent of ASTM D 698 maximum dry density. The fill soil
should be placed at 2 or more percentage points above the optimum moisture content
determined by that test.
Seismicity
Based on the 2003 International Building Code, Table 1615.1.1 Site Class Definitions, the
site soils can be characterized as Site Class C. Site Class C is described as very dense soil
and soft rock for the top 100 feet of the site soil and rock profile.
Floor System
Floor slabs placed on grade may be subject to movement as a result of moisture induced
volume changes in the active soils. The soils expand (heave) with increases in moisture
and contract (shrink) with decreases in moisture. The movement typically occurs as post
construction heave.
The potential magnitude of the moisture induced movements is rather indeterminate. It is
influenced by the soil properties, overburden pressures, and to a great extent by soil
moisture at the time of construction. Potential Vertical Movement calculations were
performed using the Texas Department of Transportation (TxDOT) Method 124-E. The
TxDOT method is empirical and is based on the liquid and plastic limits and moisture
content of the subsurface soils. Potential soil movements at this site are estimated to be on
the order of 3 to 4 inches if the soils become dry at the time of construction. Based on the
results of the laboratory tests, the soils are currently at favorable moisture levels. At these
levels potential movements are estimated to be about one inch.
A structural floor slab is recommended if floor slab movements are to be limited to less than
one inch. If floor slab movements of about one inch are acceptable, the floor slabs can be
6
Geotechnical Engineering Report
Staples Expansion
Coppell, Texas
Terracon Report No. 94075192
June 5, 2007
llerracon
supported on a subgrade at the present moisture level. It should be noted that even Y2 inch
of movement in slabs can result in uneven floors, sticking doors, and cracking of floor slabs
and wall partitions. If the risk of these movements is unacceptable, the floor slab should be
structurally suspended.
Structural Floor Slabs
A floor system structurally suspended above the subgrade is recommended if movements
are to be limited to less than 1 inch. A minimum void space of 10 inches is recommended
beneath the slabs.
The minimum void space can be provided by the use of cardboard carton forms, or a deeper
crawl space. The bottom of the void should preferably be higher than adjacent exterior
grades. If it is lower, it should be shaped and drained to prevent the ponding of water. A
ventilated and drained crawl space is preferred for several reasons, including the following:
. Ground movements will affect the project utilities, which can cause breaks in the lines
and distress to interior fixtures.
. A crawl space permits utilities to be hung from the superstructure, which greatly reduces
the possibility of distress due to ground movements. It also can provide ready access in
the event repairs are necessary.
. Ground movements are uneven. A crawl space can be positively drained preventing the
ponding of water and reducing the possibility of distress due to unexpected ground
movements.
Floor Slabs on Modified Subgrade
At the time of our field operations on May 17, 2007, in-situ moisture contents in the existing
soils were in a favorable condition. Potential movements from the present moisture levels
are estimated to be on the order of 1 inch. This level of movement can be maintained by
moisture conditioning the upper 2 feet of clay soil in conjunction with a 1 foot cap of select fill
in the building pad and other areas sensitive to movement. It is also recommended that the
floor slab be placed within 30 to 40 days after installation of the select fill cap. However, it is
emphasized that the clays can dry rapidly when the soils are exposed to warm, dry weather.
As the soils dry, the magnitude of potential movements will approach the levels previously
discussed in the "Floor Systems" section above.
If the subgrade soils are allowed to desiccate, then it will be necessary to moisture condition
the desiccated soils to reduce the expected post-construction vertical movement to a level of
one inch. A suitable method to modify subgrade soils at this site is "Excavation and
Replacement", as described below. The area to be treated should be extended beyond to
7
Geotechnical Engineering Report
Staples Expansion
Coppell, Texas
Terracon Report No. 94075192
June 5, 2007
llerracon
building line to include entrances and adjacent flatwork sensitive to movement. The treated
area should be capped with one foot of select fill.
Excavation and Replacement
The area to be treated should be undercut to a minimum depth of 2 feet or as required to
remove desiccated soils. The exposed subgrade soil should be scarified to a depth of 8
inches and re-compacted to between 92 to 98 percent of Standard Proctor (ASTM 0 698) at
a minimum of +4 percentage points above the soil's optimum moisture content. The depth
of desiccated soils should be evaluated by additional soil borings or test pits prior to slab
construction.
The excavated soils, free of vegetation, any debris, rocks greater than 4 inches in maximum
dimension and any deleterious material, should be thoroughly mixed with water as needed
to raise the soil moisture content to 4 or more percentage points above optimum moisture
content. The moisture conditioned fill can then be replaced in loose lifts, less than 9 inches
thick, and uniformly compacted. Each lift should be compacted to between 92 and 98
percent of the Standard Proctor (ASTM 0698) maximum dry density.
Care should be taken that a lift is not allowed to desiccate prior to placing a subsequent lift.
The select fill cap should then be placed above the reworked subgrade within 48 hours of
completing the installation of the moisture conditioned soils. The select fill serves to prevent
desiccation of the moisture conditioned clays. Steps should be taken to prevent desiccation
of the clays around the perimeter of the structures where the select fill cap feathers out, or
they are exposed by cuts.
It should be realized that slab movements of even 1/2 inch can result in distress to floor
coverings, interior partitions, and finishes. Special provisions should be made to
accommodate movement, if slab-on-grade construction is utilized.
A properly engineered and constructed vapor barrier should be provided beneath slabs-on-
grade which will be carpeted or receive moisture sensitive coverings or adhesives
Select Fill
Select fill material should be a very sandy clay to clayey sand with a Liquid Limit (LL) of less
than 35 percent and a Plasticity Index (PI) preferably between 6 and 15. As an alternate to
select fill, the pad can be capped with flexible base. The base should meet the
requirements of TxOOT Item 247, Grade A, Type 1 or 2. Recycled concrete meeting these
requirements is acceptable.
8
Geotechnical Engineering Report
Staples Expansion
Coppell, Texas
Terracon Report No. 94075192
June 5, 2007
, Ierracon
The select fill or base should be spread in loose lifts, less than 9 inches thick, and uniformly
compacted to a minimum of 95 percent of ASTM 0698 within :t2 percentage points of the
soil's optimum moisture content. The first lift of select fill should be placed wet of optimum
to prevent drying the underlying subgrade. Positive drainage must be provided away from
the structure to prevent the ponding of water in the select fill.
Site Grading
Preparation of the site for construction operations should include the removal and proper
disposal of all obstructions and materials, which would hinder preparation of the site for
construction.
To the extent practical, it is recommended that trees scheduled for removal in the vicinity of
proposed slab-on-grade foundations be removed as far in advance of slab construction as
possible. This will tend to restore a more favorable soil moisture equilibrium which will, in
turn, tend to minimize the potential for greater than anticipated post-construction ground
movements. Root balls should be removed, and the soil that is placed in these areas should
be placed and compacted as described above in the section "Excavation and Replacement",
under the supervision of a geotechnical engineer or his representative.
The on-site soils, free of vegetation, rocks greater than 4 inches in maximum dimension,
and any other deleterious matter, are generally suitable for site grading. If imported fill
materials are used, they should be clean soil with a Liquid Limit preferably less than 50
percent and no rock greater than 4 inches in maximum dimension.
The subgrade in areas to be filled should be scarified to a minimum depth of 6 inches and
uniformly compacted to a minimum of 95 percent of ASTM D 698 at or above the optimum
moisture content as determined by that test. The fill materials should then be spread in
loose lifts, less than 9 inches thick, and uniformly compacted to the same criteria. If filling is
suspended and the subgrade becomes desiccated or rutted, it should be reworked prior to
placement of a subsequent lift.
When placing fill on existing slopes that are steeper than 6H to 1V, the fill should be
benched into the slope. This permits placement of relatively horizontal lifts and breaks of
potential slide planes. Permanent slopes should generally be 4H to 1 V or flatter. Site
improvements should be held back from the crest of slopes to reduce the affects of creep or
shallow slides.
Utilities
Care should be taken that utility trenches are not left open for extended periods, and they
are properly backfilled. Backfilling should be accomplished with properly compacted on-site
soils as recommended in this report, rather than granular materials. A positive cut-off at the
9
Geotechnical Engineering Report
Staples Expansion
Coppell, Texas
Terracon Report No. 94075192
June 5, 2007
, Ierf'ilaX1
building line is recommended to help prevent water from migrating in the utility trench
backfill.
Surface Drainage
All grades must be adjusted to provide positive drainage away from the structures. Water
permitted to pond near or adjacent to the perimeter of the structures can result in soil
movements that exceed those discussed in this report. Open ground should preferably be
sloped at a minimum of 5 percent grade for at least 10 feet beyond the perimeter of the
building.
Flatwork and pavement could be subject to post construction movement. Maximum grades
practical should be used for paving and flatwork to prevent areas where water can pond. In
addition, allowances in final grades should take into consideration post-construction
movement of f1atwork, particularly if such movement would be critical. Consideration should
be given to preswelling techniques as discussed in the previous section of this report in
sensitive areas. Where paving or flatwork abuts the structures, care should be taken that
joints are properly sealed and maintained to prevent the infiltration of surface water.
Planters located adjacent to the structures should preferably be self-contained or at least
designed to drain. Sprinkler mains should be located a minimum of 5 feet away from the
building lines. If heads must be located adjacent to the structures, then service lines off the
main should be provided.
Roof drainage should be collected by a system of gutters and downspouts and transmitted
by pipe to a storm drainage system or to a paved surface where the water can drain away
without entering the building subgrade. Ideally, roof drains should discharge to storm
sewers by closed pipe.
Surface Pavement Recommendations
Pavement Subgrades
Subgrade materials at this site are anticipated to consist of clay soils. These are subject to
loss in support value with the moisture increases, which occur beneath pavement sections.
They react with hydrated lime, which serves to improve and maintain their support value.
Lime stabilization is recommended beneath flexible (asphalt) pavement sections. Rigid
(concrete) pavements may be placed on an unstabilized properly compacted subgrade as
discussed in the "Pavement Section" below.
A minimum of 8 percent hydrated lime (TxDOT Item 264), by dry weight, should be used.
The lime should be thoroughly mixed and blended with the top 6 inches of the subgrade
(TxDOT, Item 260). Stabilization should extend a minimum of one foot beyond the edge of
the pavement.
10
Geotechnical Engineering Report
Staples Expansion
Coppell, Texas
Terracon Report No. 94075192
June 5. 2007
lrerracon
The subgrade. stabilized or unstabilized, should be uniformly compacted to a minimum of 95
percent of ASTM D698 maximum dry density between -1 to +3 percentage points of the
optimum moisture content. The subgrade should be protected and maintained in a moist
condition until the pavement is placed. Pavement subgrades should be graded to prevent
ponding and infiltration of excessive moisture on or adjacent to the pavement subgrade
surface.
Pavement Sections
Both asphalt and concrete pavement sections are presented below. They are not
considered equal. Over the life of the pavement, concrete sections would be expected to
require less maintenance.
Five inches of asphaltic concrete should be adequate in parking lots servicing only
automobile traffic. The section should consist of a two-inch surface course similar to TxDOT
Type D and a base course similar to Type A or B. The coarse aggregate in the surface
course should be crushed limestone rather than gravel.
Portland cement concrete is recommended in areas subject to truck traffic and should
provide good service for other pavement areas. In employee parking lots and other areas
not subject to trucks, a minimum of 5 inches of 3,OOO-psi concrete on an unstabilized
subgrade is recommended. In areas subject to truck traffic, the following table (Table 2)
summarizes the estimated number of allowable daily repetitions of a fully loaded tractor-
trailer rig. The sections are based on the use of a minimum 28-day compressive strength of
3,500 psi and a 20-year design life.
TABLE 2 - PAVEMENT SECTIONS
PAVEMENT ALLOWABLE DAILY
SECTION REPETITIONS
7" Concrete without lime 40
7" Concrete with lime 60
8" Concrete without lime 90
8" Concrete with lime 130
The pavements should contain a minimum of 5 :t 1 percent entrained air for a one-inch
maximum aggregate size. As a minimum they should be reinforced with No.3 bars on 18
inch centers in both directions.
The pavement will be subject to significant movement due to volume changes in the site
soils. Flat grades should be avoided with positive drainage provided away from the
pavement edges. Backfilling of curbs should be accomplished as soon as practical to
prevent ponding of water.
11
Geotechnical Engineering Report
Staples Expansion
Coppell. Texas
Terracon Report No. 94075192
June 5. 2007
lrerracon
The pavements presented in Table 2 represent a minimum design thickness. Periodic
maintenance must be anticipated and planned. Higher daily traffic volumes may require
thicker pavement sections. Additional recommendations can be provided if actual traffic
volumes are provided.
Preventative Maintenance
Preventative maintenance should be planned because of the highly active nature of the
clays at this site. Differential soil movements can occur that can cause pavement cracking
and opening of joints. Water entering joints can reduce the service life of the pavement.
Preventative maintenance should be provided for through an on-going pavement
management program to enhance future pavement performance. Preventative maintenance
activities are intended to slow the rate of pavement deterioration and to preserve the
pavement investment.
Preventative maintenance consists of both localized maintenance (e.g. crack and joint
sealing and patching) and global maintenance (e.g. surface sealing). Preventative
maintenance is usually the first priority when implementing a planned pavement
maintenance program and provides the highest return on investment for pavements. Also,
thicker pavement sections could be used to reduce the required maintenance and extend
the service life of the pavement. Signs should be placed at the entrances of the parking
area to limit heavy trucks being on the automobile pavements.
GENERAL COMMENTS
Terracon should be retained to review the final design plans and specifications so
comments can be made regarding interpretation and implementation of our geotechnical
recommendations in the design and specifications. Terracon also should be retained to
provide testing and observation during excavation, grading, foundation and construction
phases of the project.
The analysis and recommendations presented in this report are based upon the data
obtained from the borings performed at the indicated locations and from other information
discussed in this report. This report does not reflect variations that may occur between
borings, across the site, or due to the modifying effects of weather. The nature and extent
of such variations may not become evident until during or after construction. If variations
appear, we should be immediately notified so that further evaluation and supplemental
recommendations can be provided.
The scope of services for this project does not include either specifically or by implication
any environmental assessment of the site or identification of contaminated or hazardous
materials or conditions. If the owner is concerned about the potential for such
contamination. other studies should be undertaken.
12
Geotechnical Engineering Report
Staples Expansion
Coppell, Texas
Terracon Report No. 94075192
June 5, 2007
1rerracon
This report has been prepared for the exclusive use of our client for specific application to
the project discussed and has been prepared in accordance with generally accepted
geotechnical engineering practices. No warranties, either express or implied, are intended
or made. Site safety, excavation support, and dewatering requirements are the
responsibility of others. In the event that changes in the nature, design. or location of the
project as outlined in this report are planned. the conclusions and recommendations
contained in this report ,shall not be considered valid unless Terracon reviews the changes
and either verifies or modifies the conclusions of this report in writing.
13
APPENDIX
lrerracon
SANOY LAKE ROAD
r----------------------------------,
I 8 A ~I
I ~ .... 8-1 I
I I
: PROPOSED :
I EXPANSION 8-3 I
I ~-- I
- - - -r - - --- - - - i _\&- - - - - r - --I
I i l~~_"~_L_____.
I I
L____ ___________~u _______~-----m--- -i----J
(-
(~
II
I r
W
EXISTING
OFfICE/WAREHOUSE
OJ
"
o
::.
.,
o
>-
o
.1
U'
~
o
N
'"
."
r-
o
"
'"
I !
~ '
~ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ _ D
r-
o
o
N
o
"
o
LEGEND: _
~ APPROXIMATE LOCATION or BORING
U
<SO
o
N
f
L..J
:>
-
et
a
I-
2:
o
Q
J:
I-
et
o
2:
.,
"
)
NOTE: BORING LOCATIONS ARE APPROXIMATE
o 40 80; [I 1
~-~--nl
APPROXIMATE SCALE
BORING LOCATION DIAGRAM
11errcx:on
ST APLES EXPANSION
swa OF SANDY LAKE ROAD AND NORTHPOINT DRIVE
COPPELL, TEXAS
FIGURE 1
Project No.' 94075192
CLIENT Staple Inc.
Farmingham, Massachusetts
BORING See Figure 1
LOCATION
Cl DESCRIPTION
0
-'
u
E
0-
'"
Ci Approx. Surface Elevation: N/A ft
\J~ FILL. SANDY LEAN CLAY,
-l 0
\J~ Dark brown
-l 0 2.0
~ FAT CLAY,
Dark brown
4.0
!/ 1/ SILTY LEAN CLAY,
v/I/
1/ 1/ Tan and gray
//v
//
//
V
// 8.0
/
/ SIL TY LEAN CLAY,
1/[/
1/ Tan
1/1/
1/1/
1/1/
1/
vI/
1/1/
1/
1/1//
vl//
vl//
vl/
1/
1//
1//
v/
/v/
/v 17.0
..... SAND,
00.
o 0 Tan
o 0 0
o 0
o 0 0
o 0
o 0 0
o 0
o 0 0
o .
o 0 .
o 0
o 0 0
o .
o 0 0
. .
o 0 .
o 0
. 0 . 22.0
o .
. 0 . SAND.
o .
o 0 .
. 0 Tan, with gravel, cemented
o 0 .
. 0 0
. 0
. . 0
o 0
. . 0
. 0 25.0
. 0 0
B.H. at 25.0'
STRATIFICATION LINES REPRESENT APPROXIMATE
BOUNDARIES BETWEEN SOIL AND ROCK TYPES. IN
SITU. THE TRANSITION BETWEEN STRATA MAY BE
~ MORE GRADUAL
'"
Oil
,
Q.
C)
('oj
'"
;;;
~
WATER LEVEL OBSERVATIONS. FEET
'Sl- ~
'it ~
g No seepage observed.
LOG OF BORING NO. B-1
PROJECT: STAPLES EXPANSION
SITE SWQ of Sandy Lake Road & Northpoint Dr.
Coppell, Texas
SAMPLES TESTS
f- 0 LL 'if!.
0.. X
U Zu.. U W Z
~~ ~ 0.. 'if!. 0 u..
-' f- WUl &
f- 0 OJ: o '. ~ ~ .-: ~ >~
W al Ou w::!E>- woo ~ o (ii' f-
w ::!E Xz U5 ~ o (I) J: (I)
u.. >- f-_ f-O 0::: o:::f- Z :J U ~~ wt;
:i (/) o:::Cii ~ 0::: !J!'if!. :Jz W w
O~ eDti:iOcit;;~ 0 0 ~ en - 0::: Z 0:::
f- en W 5 (/) :Jw o..w :J
0.. U 0.. f-O ;tf51rlO o~ >- :5 z> ::!Eo::: -'
w en >- 0..-' 0::: 0 -!!:! Of- <(
0 :J f- eneD uo.. o:::!: ::!Eu 0 :J Q. ::!Een uen LL
- CL ST 4.5+
- CH ST 2.75 20 113 58 38
---
5- CL ST 4.5
- CL ST 4.5+
- CL ST 4.5+
10
-
- CF
-
CL ST 4.5+ 13 107 158 2.5
15
-
- CF
-
- SP SS 30/12
20
-
- CF
-
- SP SS 4.5/50
25
REMARKS
lrerracon
DATE DRILLED
5/1712007
Page 1 of 1
PROJECT NUMBER
94075192
FIGURE
2
~
<D
LOG OF BORING NO. B-2
CLIENT Staple Inc. PROJECT: STAPLES EXPANSION
Farmingham. Massachusetts
._n__._
BORING See Figure 1 SITE: SWQ of Sandy Lake Road & Northpoint Dr.
LOCATION Coppell, Texas
SAMPLES TESTS
I- 0 u.. ;Ii
a.. x
U Zu.. U w
<l:(I? a.. ;Ii 0 Ll- Z
-' I- II- ;Ii ~ ~ WOl ~
I- 0 OI 0: -.e. >~ cr
en DESCRIPTION w 10 aU ~ l- I- ~I
0 w:::; >- a I-
-' W :::; Xz 1-0 0: w" iii ~ l- e Ol
u u.. >- 1-- ~o: ~~ 0:1- Z ::; U ~~ wI-
E :r: (I? 0: in ::)7 w 0:" W
c. 03:: !!ltu oei I-W 0 0 f= Ol" a..Z a:
'" I- Ol W Oll- 5 Ol ::)w ::;;w ::)
t9 a.. U a.. 1-0 -'z UO -z >- :5 ~a; -'
Approx. Surface Elevation: N/Aft w Ol ~ a..-, <l:w Wo: 00 0: 0 og: ~
0 ::) OlIO ua.. 0:_ :::;u 0 ::; a.. ::;;iii UOl u..
0: FAT CLAY,
~ Dark brown - CH ST 1.5
- CH ST 2.0
0: 4.0 --
/ V SIL TV LEAN CLAY,
/v Tan and gray, with trace silt. and 5- CL ST 4.5+
/v calcareous deposits and nodules
//v
//v
//v - CL ST 4.5+
/ /v
/ V
//v
//V - CL ST 4.5+ 12 40
//V 22
//v
/ V 10
//v
// -
//
// - CF
/
// 13.0
-
// SIL TV LEAN CLAY,
// Tan, with sand -- f-
/ CL ST 4.5+ 9 28 10
// 15 --
//
// -
//
// - CF
/
//
// -
~ SP ST 45 17 111 22.6 47
Vl/ 20
Vl/
Vl/
V
Vl/ 22.0 CF
. 0 0 SAND.
o.
. . .
o 0 Tan, slightly cemented
. 0 0
. .
. . 0
. .
. 0 .
o . SP SS 30/12
. 0 .
. . 25.0
. . . 25 ..-
BH at 250'
STRATIFICATION LINES REPRESENT APPROXIMATE REMARKS
BOUNDARIES BETWEEN SOIL AND ROCK TYPES IN
SITU. THE TRANSITION BETWEEN STRATA MAY BE
MORE GRADUAL
WATER LEVEL OBSERVATIONS. FEET DATE DRILLED Page 1 of 1
51- ~ llerracon 5/17/2007 FIGURE
'!l- l? PROJECT NUMBER
No seepage observed. 94075192 3
,
Q.
<.:l
'"
en
on
....
o
...
en
'"
g
LOG OF BORING NO. B- 3
CLIENT Staple Inc.
Farmingham, Massachusetts
- _" . - __. n____ _ __._____
BORING See Figure 1
LOCATION
"-.J'-
"-.J'-
~
~
~
~
~
~
~ J~
/ /1/
1/
1/
1/
1/
/ 1/
1/
1/
/1/
/1/
. . .
. . .
. . .
...~
. . .
. .
. . .
. .
. . .
. .
. .
. . .
. . -.- -.. ~_.. - ---- --- -------.-... - -.-
SITE swa of Sandy Lake Road & Northpoint Dr.
Coppell,Texas
SAMPLES TESTS
- _.---- . - _.- -- .- I I I I
I- 0
0.. u. X
U Zu. U W
<(w 0.. ~ 0 u.
--' I- I~ ;;!!. WV>
I- 0 OI o ,D. ::P. ~ ~ ~ >~
W ID Ou I- 0 ~I
w:2; >- WOo en ~ >-
W ::!: Xz 1-00:: l- I- 0
u. >- 1-- ~o:: l1J~ ~Z Z :J 0 ~~ wI-
I VJ 0::- w 0::C>
o~ I->'I-w 0 0 f= en' o..Z
I- en W IDW 00 wI- 5 VJ ::Jw ::!:w
0.. U Q. 1-0 ~iD ~o o~ >- ~ z>
W VJ >- 0..-' 0:: 0 _w og:
0 ::J I- WID uo.. o::!: ::!:u 0 :J 0.. ::!:u; UV>
;
!
Ol
o
--'
Ll
:.c
c.
to
o
DESCRIPTION
Approx. Surface Elevation: N/A ft
FILL. FAT CLAY,
Brown and dark brown, with trace sand
g.Q.~d gravel ~_
FAT CLAY,
Brown
4.0
FAT CLAY,
Tan and brown, with trace calcareous
nodules
130
---+-.-- -- - -----,._._--~..__.
SILTY LEAN CLAY,
Tan, with trace sand
.18.0
SAND.
Tan
22.0
SAND.
Tan, with gravel, cemented
~50"
B.H at 25.0'
REMARKS
STRATIFICATION LINES REPRESENT APPROXIMATE
BOUNDARIES BETWEEN SOil AND ROCK TYPES. IN
o SITU. THE TRANSITION BETWEEN STRATA MAY BE
:g MORE GRADUAL
~
WATER LEVEL OBSERVATIONS. FEET
~ t-.--- - -- - --. . -----
N SL !'
'"
o
o
..
'"
CD
o
--'
PROJECT STAPLES EXPANSION
;fl
Z
~
l-
V>
W
a::
::J
-'
<(
u.
CH ST 1.5
-. -1--
___ u_ _j
CH ST
2.0
. ____d..._ I---~~ --
-.- -.---
i
I
I
...- ---. ... ---l
10_:~~_:35~-r-l-j ..11
I !!,' i
I '
I I I
I I I i
I
5- CH ST
18
53 33
2.75
----
CF
---. -...
CL ST
,
I
t
119.0 29
I
4.5
13 110
15
-
- CF
-
- SP SS 31/12
20
-
- CF
__ __H ." ... _.
-
-- -- --- --- ..-- -..-
,.
i
I
I
I
-- SP SS
25. --.
4/50
.--. --- -- ..
I
I
i
DATE DRILLED
5/17/2007
Page 1 of 1
..,
J'
lrerracon
PROJECT NUMBER
94075192
FIGURE
4
No seepage observed.
~
o
;;
<Ii
LOG OF BORING NO. B-4
CLIENT Staple Inc. PROJECT: STAPLES EXPANSION
Farmingham, Massachusetts
BORING See Figure 1 SITE: SWQ of Sandy Lake Road & Northpoint Dr.
LOCATION Coppell, Texas
SAMPLES TESTS
I- --- --
[1- 0 u. X ;i!-
U Zu. U w Z
<((I) [1- 0 u.
-' I- It- ;i!- wV) <C
t- o OI 0' ;i!- >- ~ >~ a::
01 DESCRIPTION W al AU > ;i!- l- t: >- a Vi. I-
0 w::a;: Vi
-' W ::a;: ~~ 1-0 a:: w. ::a;: I- a V)I V)
u. >- a:: I- Z ::J U ~ ;;;-~ III I-
u a::ii) iicr: ~o~ :Jz a::C> W
E :i (I) I-w W 0 i= a::
c.. l- V) 03: all- 00 V) I- 0 ~u.i [1-Z :J
'" W _W :5 V) ::a;:w
2i Approx. Surface Elevation: N/Aft [1- u [1- 1-0 ...JZ uo -z >- :5 z> og: -'
W V) >- [1--, <(w Wa:: 00 a:: 0 _w <C
0 :J I- V)al U[1- a::_ ::a;:u 0 ::J [1- :2 Vi uv) IJ..
~ FAT CLAY,
~ Dark brown - CH ST 1.0
- CH ST 4.5+
~ 4.0
/ v SIL TV LEAN CLAY,
//V
/ V Tan and gray, with trace sand 5- CL ST 4.5+
//V
/V
//V
//V - CL ST 4.5+
/ V
/V .-.
//V
//V - CL ST 4.5+ 12 114 34 19
//V
/ V
/ V 10 --
/ V
/V -
//V
//V - CF
//v
//V
/ V -
/V 14.0
i!~. . SANDY LEAN CLAY, CL ST 3.75 9 124 34 36
~ Tan, with trace silt 15
~ -
~ CF
~
%
% CL ST 3.75 10 118 32 45
% 20
% 22.0 CF
. . . SAND,
. .
. . .
. . . Tan, coarse, with gravel, cemented
. .
. . .
. .
. . . SP SS 26/12
. .
. . .
. . 25.0
. . . 25
B.H. at 25.0'
STRATIFICATION LINES REPRESENT APPROXIMATE REMARKS
BOUNDARIES BETWEEN SOIL AND ROCK TYPES. IN
SITU THE TRANSITION BETWEEN STRATA MAY BE
MORE GRADUAL
WATER LEVEL OBSERVATIONS. FEET DATE DRILLED Page 1 of 1
'Sl. ~ llerracon 5/17/2007 FIGURE
'l- ~ PROJECT NUMBER
5
No seepage observed. 94075192
Q.
"
,~
'"
:c
<>
"
'"
lD
g
GENERAL NOTES
DRILLING & SAMPLING SYMBOLS:
SS: Split Spoon _1_3/8"1.0., 2" D.o., unless otherwise noted
ST: Thin-Walled Tube - 2" D.O., unless otherwise noted
TC: TxDOT Cone Penetrometer Test
CF: Continuous Flight Auger
BS: Bulk Sample or Auger Sample
HS:
PA:
HA:
RC:
WB:
Hollow Stem Auger
Power Auger
Hand Auger
Rock Core
Wash Boring or Mud Rotary
The number of blows required to advance a standard 2-inch 0.0. split-spoon sampler (SS) the last 12 inches of the total 18-inch
penetration with a 140-pound hammer falling 30 inches is considered the "Standard Penetration" or "N-value". For TxDOT cone
penetrometer (TC) the penetration value is reported as the number of blows required to advance the sampler 12 inches or penetration
in inches after 100 blows using a 170-pound hammer falling 24 inches, reported as "blows perfoot: or inches per 100 blows and is not
considered equivalent to the .Standard Penetration" or "N-value".
WATER lEVEL MEASUREMENT SYMBOLS:
WL: Water Level WS:
WCI: Wet Cave in WD:
DCI: Dry Cave in SCR:
AS: After Boring ACR:
While Sampling
While Drilling
Before Casing Removal
After Casing Removal
NlE:
Not Encountered
Water levels indicated on the boring logs are the levels measured in the borings at the times indicated. Groundwater levels at other
times and other locations across the site could vary. In pervious soils, the indicated levels may reflect the location of groundwater. In
low permeability soils, the accurate determination of groundwater levels may not be possible with only short-term observations.
DESCRIPTIVE SOil CLASSIFICATION: Soil classification is based on the Unified Classification System. Coarse Grained Soils have
more than 50% of their dry weight retained on a #200 sieve; their principal descriptors are: boulders, cobbles, gravel or sand. Fine
Grained Soils have less than 50% of their dry weight retained on a #200 sieve; they are principally described as clays if they are
plastic, and silts if they are slightly plastic or non-plastic. Major constituents may be added as modifiers and minor constituents may be
added according to the relative proportions based on grain size. In addition to gradation, coars8i;jrained soils are defined on the basis
of their in-place relative density and fin8i;jrained soils on the basis of their consistency.
Unconfined
ComDressive
Strenath, Qu. Dsf
< 500
500 - 1,000
1,001 - 2,000
2,001 - 4,000
4,001 - 8,000
8,000+
Standard
Penetration or
N-value (SS)
Blows/Ft.
<2
2-3
4-6
7-12
13-26
26+
RELATIVE DENSITY OF COARSE-GRAINED SOilS
Standard
Penetration or
N-value (SS)
Blows/Ft.
0-3
4-9
10 - 29
30 - 49
50+
CONSISTENCY OF FINE-GRAINED SOilS
Consistency
Very Soft
Soft
Medium Stiff
Stiff
Very Stiff
Hard
TxDOT Cone
Penetrometer (TC)
Blows/Ft
Q-8
8-20
20-80
80 to 5"/100
5"/100 to 0"/100
Relative Densitv
Very loose
Loose
Medium Dense
Dense
Very Dense
RELATIVE PROPORTIONS OF SAND AND GRAVEL
Descriptive Term(s} of other Percent of
constituents Dry WelQht
GRAIN SIZE TERMINOLOGY
Maior Component
of Sample Particle Size
Trace
With
Modifier
< 15
15 -29
>30
Boulders
Cobbles
Gravel
Sand
Silt or Clay
RELATIVE PROPORTIONS OF FINES
Descriptive Term(s) of other
constituents
Percent of
Dry Weiaht
Term Plasticitv Index
Trace
With
Modifiers
<5
5 -12
> 12
Non-plastic
Low
Medium
High
Over 12 in. (300mm)
12 in. to 3 in. (300mm to 75 mm)
3 in. to #4 sieve (75mm to 4.75 mm)
#4 to #200 sieve (4.75mm to 0.075mm)
Passing #200 Sieve (0.075mm)
PLASTICITY DESCRIPTION
o
1-10
11-30
30+
lrerracan
FIGURE 6
UNIFIED SOIL CLASSIFICATION SYSTEM
Criteria for Assigning Group Symbols and Group Names Using Laboratory Tests.
5011 Classification
Group
Symbol Group Name"
GW Well-graded gravel'
GP Poorly graded gravel'
GM Silty gravel'G H
GC Clayey gravel,.GH
SW Well-graded sand'
SP Poorly graded sand'
SM Silty sandG.H1
SC Clayey sandG.H1
CL Lean clay"Ul
ML SiltK.L.M
OL Organic clay"Ul.N
Organic siltK'M.o
CH Fat clay"..M
MH Elastic SiltK....M
OH Organic clay"""'"
Organic silr..Mo
PT Peat
Coarse-Grained Soils Gravels Clean Gravels Cu ~ 4 and 1 $ Cc $ 3'
More than 50% retained More than 50% of coarse Less than 5% finesc Cu < 4 and/or 1 > Cc > 3'
on the No. 200 sieve fraction retained on
NO.4 sieve Gravels with Fines Fines classify as ML or MH
More than 12% finesc Fines classify as CL or CH
Sands Clean Sands Cu~6and1$Cc$3'
50% or more of coarse Less than 5% fineso Cu < 6 and/or 1 > Cc > 3'
fraction passes
No. 4 sieve Sands with Fines Fines classify as ML or MH
More than 12% fineso Fines Classify as CL or CH
Fine-Grained Soils Silts and Clays inorganic PI> 7 and plots on or above "A" line'
50% or more passes the Liquid limit less than 50 PI < 4 or plots below "A" line'
No. 200 sieve
organic Liquid limit - oven dried < 0.75
Liquid limit - not dried
Silts and Clays inorganic PI plots on or above "A" line
Liquid limit 50 or more Pilots below "A" line
organic Liquid limit - oven dried < 0.75
Liquid limit - not dried
Highly organic soils Primarily organic matter, dark in color, and organic odor
Hlf fines are organic, add "with organic fines" to group name.
I If soil contains ~ 15% gravel. add "with gravel" to group name.
J If Allerberg limits plot in shaded area. soil is a CL-ML. silty clay.
Kif soil contains 15 to 29% plus No. 200. add "with sand" or "with
gravel," whichever is predominant.
llf soil contains ~ 30% plus No. 200 predominantly sand, add
"sandy" to group name.
M If soil contains ~ 30% plus No. 200. predominantly gravel,
add "gravelly" to group name.
Npl ~ 4 and plots on or above "A" line.
o PI < 4 or plots below "A" line.
PPI plots on or above "A" line.
a PI plots below "A" line.
ABased on the material passing the 3-in. (75-mm) sieve
BIf field sample contained cobbles or boulders. or both. add "with cobbles
or boulders. or both" to group name.
cGravels with 5 to 12% fines require dual symbols: GW-GM well-graded
gravel with sill. GW-GC well-graded gravel with clay, GP-GM poorly
graded gravel with silt. GP-GC poorly graded gravel with day.
oSands with 5 to 12% fines require dual symbols: SW-SM well-graded
sand with sill. SW-SC well-graded sand with clay. SP-SM poorly graded
sand with silt, SP-SC poorly graded sand with clay
(030 )2
ECU = 0601010 Cc =
0,0 x De<)
F If soil contains ~ 15% sand, add "with sand" to group name.
Glf fines classify as CL-ML. use dual symbol GC-GM. or SC-SM.
--1
j
i
I
-1
I
I
60 I
For classification of fine-grained
solis and fine-grained fraction
50 '- of coarse-grained soils - -------
Equation of "A" -line
Horizontal at PI=4 to LL=25.5.
40'- then PI=0.73 (LL-20)
Equation ot "U" - line
Ver1ical at LL=16 to PI=7.
30 then PI=O.9 (LL-B)
~
X
W
o
Z
~
(3
i=
en
::5
a..
20
MH or OH
10
7 ---
4 -
o
o 10 16 20
100 110
90
60 70 80
50
30
40
lrerracon
LIQUID LIMIT (LL)
FIGURE 7
Form 1 "~I9B