RE: Northlake College, Lot 1 Block I
Dear Mr. Bradley:
A pre-construction conference on the referenced project has been scheduled for Tuesday,
August 28, 2007 at 9:00 a.m. in the 2d floor conference room in Town Center at 255
Parkway Blvd.
Please notify the franchised utility companies, contractors, sub-contractors, testing lab
and any other interested parties so that they may have a representative present. If you
have any questions concerning this project prior to the scheduled meeting, feel free to
contact me at (972) 304-3684.
Sincerely,
~~/~
Larry Davis, Construction Inspector
Office Phone: 972-304-3684
Fax: 972-304-3570
cc: Ken Griffin, P.E., Dir. of Engineering & Public Works
Glenn Hollowell, P.E., Asst. Dir. of Public Works
Lee Stone, Commercial Building Inspector
Tim Oates, Fire Marshal
Mike Garcia, E.I.T.
Eric Stanaland, Starling Richardson Construction
255 PARKWAY * P.O.BOX 9478 * COPPELL TX 75019 * TEL 972/4620022 * FAX 972/304 3673
2
RESPONSIBILITY FOR PRE-CONSTRUCTION
MEETING NOTIFICATION
The owner / owner's representative will be notified of the date, time and place of
the pre-construction meeting once it is scheduled by the Construction Inspector
assigned to the project.
It is the owner / owner representative's responsibility to notify the following
parties:
. Franchise Utilities (including but not limited to electric, gas, cable, &
telephone providers)
. Geotechnical firm
. Project Engineer
. Contractors or subcontractors for excavation, utility, & paving operations
. SWPPP representative