ST0502B-CS070730
Page 1 of 1
Rhonda Adloo - cost estimates Freeport Parkway (STOS-02 A &. B)
From: Ken Griffin
To: jperez@nctcog.org
Date: 7/30/2007 2:51 PM
Subject: cost estimates Freeport Parkway (ST05-02 A & B)
CC: Keith Marvin; Rhonda Adloo
Jose
Because we have not started the actual design, we do not have exact quantities and cost information.
However, we have spoken to Freese and Nichols about designing the project and they provided a cost estimate
in November 2005. Their estimate only covered construction, so I modified it today to include design, right of
way acquisition and geotechnical.
Freeport (SH 121 to Sandy Lake)
Construction $5,271,171
Right of Way $2,150,000
Design $805,000
Geotechnical $143,750
Total $8,370421
Freeport (Sandy Lake to Ruby)
Construction $4,133,660
Right of Way $258,750
Design $632,500
Geotechnical $115,000
Total $5,150,000
I hope this information is what you needed. If not please feel free to contact me at your convenience.
Ken Griffin, P. E.
Director of Engineering/Public Works
972-304-3686
kgriffin@ci.coppell.tx.us