Bethel BP-CS070924 THE.CITY.OF COPPELL September 24, 2007 Daniel M. Goodwin, P.E. Goodwin & Marshall, Inc. 2405 Mustang Drive Grapevine, TX 76051 RE: Bethel Business Park, Lot 1 Block 1 PRE-CONSTRUCTION MEETING Dear Mr. Goodwin: A pre-construction conference on the referenced project has been scheduled for Thursday, September 27,2007 at 1 :30 p.m. in the lobby conference room in Town Center at 255 Parkway Blvd. Please notify the franchised utility companies, contractors, sub-contractors, testing lab and any other interested parties so that they may have a representative present. If you have any questions concerning this project prior to the scheduled meeting, feel free to contact me at (972) 304-7090. Sincerely, ~ ot~1 Cdf- Rick O'Dell, Construction Inspector Office Phone: 972-304-7090 Fax: 972-304-3570 cc: Ken Griffin, P.E., Dir. of Engineering & Public Works Glenn Hollowell, P.E., Asst. Dir. of Public Works Lee Stone, Commercial Building Inspector Tim Oates, Fire Marshal 255 PARKWAY * P.O.BOX 9478 * COPPELL TX 75019 * TEL 972/462 0022 * FAX 972/304 3673 RESPONSIBILITY FOR PRE-CONSTRUCTION MEETING NOTIFICATION The owner / owner's representative will be notified of the date, time and place of the pre-construction meeting once it is scheduled by the Construction Inspector assigned to the project. It is the owner / owner representative's responsibility to notify the following parties: . Franchise Utilities (including but not limited to electric, gas, cable, & telephone providers) . Geotechnical firm . Project Engineer . Contractors or subcontractors for excavation, utility, & paving operations . SWPPP representative