Duke Lesley 2A-LR070908
Rone Engineering
.
8908 Ambassador Row, Dallas, TX 75247
7701 W Little York, Ste 600, Houston, TX 77040
4421 Freidrich, Ste 195, Austin, TX 78744
Corporate Phone: (214) 630-9745
Client:
Duke Construction, LP
14241 Dallas Pkwy, Ste 1000
Dallas, TX 75254-2936
Report of Drilled Pier Inspection
Report No.: 297227
Project No.: 0712932
Date of Service: 08/29/2007
Report Date: 09/08/2007
Project: Hemisphere's at Point West
Coppell, Texas
Services: Straight Shaft Pier Inspection
Report of Inspection
D ri lie r: A UQ e r
Pier Identification 1/14 J /1 4 H /14 G /14 F /14
PierDiameter(in) 24 24 24 24 24
Depth of Pier From Surface (ft) 45.80 43.00 44.50 38.30 43.00
Depth ofBearinQ Stratum Fro m Surface (ft) 38.00 37.60 37.50 32.00 37.00
Required Penetration (ft) 5.00 5.00 5.00 5.00 5.00
Actual Penetration (ft)' 7.80 5.40 7.00 6.30 6.00
Condition of Bottom (wet/dry) Dry Dry Dry Dry Dry
Plumb Within Tolerance (ves / no) Yes Yes Yes Yes Yes
CasinQ Diameter(in)/CasinQ LenQth (ft) 26/38 26/36.8 2 6 13 6 .7 26/3 1 .8 26/36.8
NumberofBars IReinforcinQ BarSize 6 / #6 6 1 #6 6 1 #6 6 / #6 6 / #6
Length of Reinforcing Steel (ft) 44.70 41.80 43.30 37.20 41.90
Time Drillina was Completed (am Ipm) 7 :4 3 AM 8:10 AM 8 :38 AM 8 :55 A M 9 :32 AM
Time Concrete was Placed (am /pm) 8 :50 AM 9:20 AM 9 :55 AM 10:37 AM 11:05AM
D e p th 0 f Pie r Fro m Top 0 f Con c re te (ft) 45.30 42.50 44.00 37.80 42.50
E Ie va ti 0 n: S u rfa c e (ft)" 9 8.50 98.50 98.50 98.50 98.50
Elevation: Top of Pier (ft).. 98.00 98.00 98.00 98.00 98.00
Elevation: Bottom of Pier (ft)" 5 2.70 55.50 54.00 60.20 55.50
Elevation: Top of Bearina Stratum (ft.)' , 60.50 60.90 61.00 66.50 61 .50
BearinQ Stratum (description) B lu e s h a Ie
Note: See re port # N A fo r Com pre s s i ve S tre n g th T est S p e c i men s.
'Additional Penetration not requested unless noted. "Elevation by others
LIMITATIONS: The test results presented herein were prepared based upon the specific samples provided for testing. We assume no responsibility for variation in quality
(composition, appearance, etc.) or any other feature of similar subject matter provided by persons or conditions over which we have no control. Our letters and reports are
for the exclusive use of the clients to whom they are addressed and shall not be reproduced except in full without the written approval of Rone Engineering Services, Ltd.
(TM/LB) Page 1 of 4
Rone Engineering
.
8908 Ambassador Row, Dallas, TX 75247
7701 W Little York, Ste 600, Houston, TX 77040
4421 Freidrich, Ste 195, Austin, TX 78744
Corporate Phone: (214)630-9745
Client:
Duke Construction, LP
14241 Dallas Pkwy, Ste 1000
Dallas, TX 75254-2936
Report of Drilled Pier Inspection
Report No.: 297227
Project No.: 0712932
Date of Service: 08/29/2007
Report Date: 09/08/2007
Project: Hemisphere's at Point West
Coppell, Texas
Services: Straight Shaft Pier Inspection
I
Driller: A ug e r
Pier Identification E 114 D 114 C 114 B 114 B 115
Pier Diameter (in) 24 24 24 24 24
Depth of Pier From Surface (ft) 42.90 45.00 44.60 42.00 42.70
Depth of Bearinq Stratum From Surface (ft) 37.00 38.00 37.00 37.00 37.50
Required Penetration (ft) 5.00 5.00 5.00 5.00 5.00
Actual Penetration (ft)* 5.90 7.00 7.60 5.00 5.20
Condition of Bottom (wet/dry) Dry Dry D rv D rv Dry
Plumb Within Tolerance (ves 1 no) Yes Yes Yes Yes Yes
Casinq Diameter (in) ICasina Lenath 7ft) 26/36.5 26 2 613 7 26/36 .5 26/3 7
NumberofBars IReinforcinq BarSize 6 1 #6 6/#6 6/#6 6/#6 6/#6
Lenqth of Reinforcinq Steel (ft) 41.70 43.70 43.40 40.70 41.40
Time Drilling was Completed (am 1 pm) 10:11 AM 10:33 AM 10:53AM 11:12AM 1 1 :45 A M
Time Concrete was Placed (am Ipm)- 11:20AM 12:00 PM 1:11 PM 1 :40 PM 2:20 PM
Depth of Pier From Top of Concrete (ft) 42.40 44.50 44.10 41.50 42.20
Elevation: Surface (ft)** 98.50 98.50 98.50 98.50 98.50
Elevation:Top ofPier(ft)** 98.00 98.00 98.00 98.00 98.00
Elevation: Bottom of Pier (ft)** 55.60 53.50 53.90 56.50 55.80
Elevation: Top ofBearinq Stratum (ft.)** 61.50 60.50 61.50 61.50 61.00
Bearing Stratum (description) Blue shale
Note: See re port # NA fo r Com pre s s ive S tre ng th T est S p e c im ens.
* Additional Penetration not requested un Ie s s note d . **E levation by others
LIMITATIONS: The test results presented herein were prepared based upon the specific samples provided for testing. We assume no responsibility for variation in quality
(composition, appearance, etc.) or any other feature of similar subject matter provided by persons or conditions over which we have no control. Our letters and reports are
for the exclusive use of the clients to whom they are addressed and shall not be reproduced except in full without the written approval of Rone Engineering Services, Ltd.
(TM/LB) Page 2 of 4
Rone Engineering
.
8908 Ambassador Row, Dallas, TX 75247
7701 W Little York, Ste 600, Houston, TX 77040
4421 Freidrich, Ste 195, Austin, TX 78744
Corporate Phone: (214) 630-9745
Client:
Duke Construction, LP
14241 Dallas Pkwy, Ste 1000
Dallas, TX 75254-2936
Report of Drilled Pier Inspection
Report No.: 297227
Project No.: 0712932
Date of Service: 08/29/2007
Report Date: 09/08/2007
Project: Hemisphere's at Point West
Coppell, Texas
Services: Straight Shaft Pier Inspection
D rille r: A UQ e r
Pie r Id e n ti fi c a ti 0 n C 115 D 11 5 E 11 5 F 11 5 G 115
PierDiameter(in) 24 24 24 24 24
D e p th 0 f Pie r F ro m S urfa ce (ft) 43.50 44.00 44.10 42.00 42.00
Depth of Bearing Stratum Fro m Surface(ft) 37.50 38.50 37.50 36.40 36.20
Required Penetration (ft) 5.00 5.00 5.00 5.00 5.00
Actual Penetration (ft)* 6.00 5.50 6.60 5.60 5.80
Condition of Bottom (wet 1 dry) Dry Dry Dry Dry Dry
Plumb Within Tolerance (yes Ino) Yes Yes Yes Yes Yes
C asinQ 0 iameter (in) 1 C asina Lenath (ft) 26/36.7 26/38 26/37.5 26/36 .4 2 6 13 6
N u m be r 0 f Bars 1 Rei n fo rc in a Bar S i z e 6 1 #6 6 1 #6 6 1 #6 6 1 #6 6 1 #6
Length of Reinforcina Steel (ft) 42.30 42.70 42.80 40.80 40.70
Time Drillina was Completed (am Ipm) 12 :03 PM 1 :00 PM 1 :40 P M 2 :05 PM 2 :2 8 PM
Time Concrete was Placed (am Ipm) 3:05 PM 3 :3 0 PM 4:10 PM
De p th 0 f Pie r Fro m Top 0 f Con c re te (ft) 43.00 43.50 43.60
Elevation: Surface (fO" 9 8.50 98.50 98.50 Site shut down due to
lightning - holes not
Elevation:Top of Pier (ft)** 98.00 98.00 98.00 P la c e d
Elevation: Bottom of Pier (ft).. 55.00 54.50 54.40
E Ie va Ii 0 n: Top of Bear in a Stratum (ft.)" 61 .00 60.00 61 .00
BearinQ Stratum (description) Blue shale
Not e. See re port # NA for Compressive Strength Test Specimens.
. Additional Penetration not requested unless noted HE levation by others
L1MfTA TIONS: The test results presented herein were prepared based upon the specific samples provided for testing. We assume no responsibility for variation in quality
(composition, appearance. etc.) or any other feature of similar subject matter provided by persons or conditions over which we have no control. Our letters and reports are
for the exclusive use of the clients to whom they are addressed and shall not be reproduced except in full without the written approval of Rone Engineering Services, Ltd.
(TM/LB) Page 3 of 4
Rone Engineering
.
8908 Ambassador Row, Dallas, TX 75247
7101 W Little York, Ste 600, Houston, TX 71040
4421 Freidrich, Ste 195, Austin, TX 78744
Corporate Phone: (214) 630-9745
Client:
Duke Construction, LP
14241 Dallas Pkwy, Ste 1000
Dallas, TX 75254-2936
Report of Drilled Pier Inspection
Report No.: 297227
Project No.: 0712932
Date of Service: 08/29/2007
Report Date: 09/08/2007
Project: Hemisphere's at Point West
Coppell, Texas
Services: Straight Shaft Pier Inspection
D rille r: Auger
Pie r Id e n ti fi c a ti 0 n H 115 1/1 5 J 11 5
PierDiameter(in) 24 24 24
D e p th 0 f Pie r Fro m S u rfa c e (ftl 43.20 45.00 43.60
Depth of Bearing Stratum Fro m S u rfa c e (ft) 37.00 38.00 38.00
Required Penetration (ft) 5.00 5.00 5.00
Actual Penetration (ft)* 6.20 7.00 5.60
Condition of Bottom (wet 1 dry) Dry Dry Dry
Plum b Within Tolerance (ves 1 no) Yes Yes Yes
Casing Diameter(in)/Casina Lenath (ft) 26/36.5 26/37 26
NumberofBars IReinforcing BarSize 6 1 #6 6 1#6 6 1 #6
Length of Reinforcing Steel (ft)
Time Drillina was Completed (am Ipm) 3 :09 PM 3:42PM 4 :09 PM
Time Concrete was Placed (am Ipm)
D e p th 0 f Pie r Fro m Top 0 f Con c re te (ft)
E Ie va tio n: S urfa ce (fO** Site shut down due to lightning - hole s
Elevation:Top of Pier (ft)** not p la c e d
Elevation: Bottom of Pier (ft)**
Elevation: Top of Bear in a Stratum (ft.) **
Bearing Stratum (description) Blue sha Ie
Nole: See report # NA to reo m pre s s ive Sire n 9 t h Tesl S pecim ens.
* Add it io n a I Pen e t ra I io n no I re que s t e d unless noled "E levalion by others
Technician: Chris Harbour Started: 06:00am
Report Distribution:
Orig: Duke Construction, LP (Dallas, TX) AUn: Mr. Paul Byrne
(1-ec copy)
1-cc City of Coppell AUn: Mr. Lee Stone
1-cc City of Coppell AUn: Mr. Larry Davis
Finished: 05:15pm Rone Engineering
p~
~
K. Scott Watson, AET
Project Manager
LIMITATIONS: The test results presented herein were prepared based upon the specific samples provided for testing. We assume no responsibility for variation in quality
(composition, appearance, etc.) or any other feature of similar subject matter provided by persons or conditions over which we have no control. Our letters and reports are
for the exclusive use of the clients to whom they are addressed and shall not be reproduced except in full without the written approval of Rone Engineering Services, Ltd.
(TM/LB) Page 4 of 4
Rone Engineering
.
Client:
Duke Construction, LP
14241 Dallas Pkwy, Ste 1000
Dallas, TX 75254-2936
8908 Ambassador Row, Dallas, TX 75247
7701 W Little York, Ste 600, Houston, TX 77040
4421 Freidrich, Ste 195, Austin, TX 78744
Corporate Phone: (214) 630-9745
Report of Concrete Compressive Strength Test
Report No.: 297521
Project No.: 0712932
Date of Service: 08/31/2007
Report Date: 09/08/2007
Project: Hemisphere's at Point West
Coppell, Texas
Services: Obtain samples of fresh concrete at the placement locations, perform required testing, cast compressive strength samples and bring
samples back to the laboratory for curing and testing in accordance with applicable standards.
Contractor: Duke Construction, LP
Concrete Supplier: Potter Concrete
Plant: 01
Specification Requirements
Strength: 3,000 psi @ 28 days
Slump (in.): NA
Air (%): NA
Test Method: ASTM C-172
ASTM C-31 (except 10.1.2)
ASTM C-143
:\ST~.:l C211
ASTM C-1064
ASTM C-138
ASTM C-39
PROJECT DATA
Mix Design 1.0.: 7751 PW
Placement Date: 08/31/2007
Weather Conditions: Overcast
Time Sampled: 02:40pm
Temperature - Air: 930F
Truck No: 133
Air Content: NA
Overall Placement Location:
Piers (see report #297520)
Batch time: 02:01 pm
Concrete: 950F
Ticket No: 13280
Unit Weight (pcf): NA
Measured
Slump
(inches)
7.0
Sample Location:
Pier L.1/3
REPORT OF TESTS
Concrete Compressive Cylinder 6" x 12"
Cylinder Maximum Compressive
Marked Date Age Diameter Area Load Strength Fracture
Set No. Tested (days) (in) (in2) (Ibs) (psi) Type
1 1 09/07/2007 7 6.00 28.27 90,380 3,200 Cone/Split
1 2 09/07/2007 7 6,00 28.27 93,670 3,310 Cone/Split
Average 3,250
3 09/28/2007 28
4 09/28/2007 28
5 10/26/2007 56
Technician: Chris Harbour Rone Engineering
See Report 297520 for technician time~~
Report Distribution:
Orig: ~~~~ ~oop~~truction, LP (Dallas, TX) Attn: Mr. Paul Byrne .'. . . . ..... .' . .
1-cc Potter Concrete Attn: Mr. Ryan Skelly K, Scott Watson, AET
1-cc City of Coppell Attn: Mr. Lee Stone. Pro'eet Manager
1-cc City of Coppell Attn: Mr. Larry DaVIS j
~
LIMITATIONS: The test results presented herein were prepared based upon the specific samples provided for testing. We assume no responsibility for variation in quality
(composition, appearance, etc.) or any other feature of similar subject matter provided by persons or conditions over which we have no control. Our letters and reports are
for the exclusive use of the clients to whom they are addressed and shall not be reproduced except in full without the written approval of Rone Engineering Services, Ltd.
(LB/LB) Page 1 of 1
Rone Engineering
.
8908 Ambassador Row, Dallas, TX 75247
7701 W Little York, Ste 600, Houston, TX 77040
4421 Freidrich, Ste 195, Austin, TX 78744
Corporate Phone: (214) 630-9745
Client:
Duke Construction, LP
14241 Dallas Pkwy, Ste 1000
Dallas, TX 75254-2936
Report of Drilled Pier Inspection
Report No.: 297520
Project No.: 0712932
Date of Service: 08/31/2007
Report Date: 09/08/2007
Project: Hemisphere's at Point West
Coppell, Texas
Services: Straight Shaft Pier Inspection
Report of Inspection
D rille r: Auger
Pie rid e ntifica tio n J.3/1.1 L.1/1.9 K.9/2 L .113 I L/16
PierDiameter(in) 30 30 30 30 24
D e p th 0 f Pie r Fro m S u rfa c e (ft) 44.00 43.20 43.00 42.80 42.20
Depth of Bearing Stratum Fro m Surface(ft) 36.60 36.50 36.70 37.00 36.50
R e quire d P e ne tra tion (ft) 5.00 5.00 5.00 5.00 5.00
Actual Penetration (ft)" 7.40 6.70 6.30 5.80 5.70
Condition of Bottom (wet 1 dry) Dry Dry Dry Dry Dry
Plum b Within Tolerance (yes 1 no) Yes Yes Yes Yes Yes
Casing D iam eter (in) 1 Casing Lenath (ft) 32/34 3 2 13 3 .5 32/35 32 26
r..,mu"'I 0fl:"dl:::,' Rell,'olLlng 8al Size 8 i #6 8 1 #6 ;, i #6 8 1 'If. 6 - - - ti i #6
Length of Reinforcing Steel (ft) 42.60 41.80 41.80 41.50 41.00
Time Drillina was Completed (am Ipm) 8 :16 AM 9:45 AM 1 0:57 AM 2:02 PM 2 :25 P M
Time Concrete was Placed (am Ipm) 8 :50 AM 1 0 :2 0 A M 1 1 :30 AM 2 :4 5 P M 3 :30 P M
De p th 0 f Pie r Fro m Top of Concrete (ft) 41.50 40.70 40.50 40.30 41.70
Elevation: Surface (ft)** 98.50 98.50 98.50 98.50 98.50
E Ie va ti 0 n: Top 0 f Pie r (ft) ** 96.00 96.00 96.00 96.00 98.00
Elevation: Bottom of Pier (ft)"" 54.50 55.30 55.50 55.70 56.30
Elevation: Top of Bearina Stratum (ft.) .. 61 .90 62.00 61.80 61.50 62.00
Bearing Stratum (description) Blue sha Ie
Note: See report # 297521 for Com pressive Strength Test Specimens.
"Additional Penetration not requested unless noted. ""E levation by others
LIMITATIONS: The test results presented herein were prepared based upon the specific samples provided for testing. We assume no responsibility for variation in quality
(composition, appearance, etc.) or any other feature of similar subject matter provided by persons or conditions over which we have no controL Our letters and reports are
for the exclusive use of the clients to whom they are addressed and shall not be reproduced except in full without the written approval of Rone Engineering Services, Ltd.
(CH/LB) Page 1 of 2
Rone Engineering
.
8908 Ambassador Row, Dallas, TX 75247
7701 W Little York, Ste 600, Houston, TX 77040
4421 Freidrich, Ste 195, Austin, TX 78744
Corporate Phone: (214) 630-9745
Client:
Duke Construction, LP
14241 Dallas Pkwy, Ste 1000
Dallas, TX 75254-2936
Report of Drilled Pier Inspection
Report No.: 297520
Project No.: 0712932
Date of Service: 08/31/2007
Report Date: 09/08/2007
Project: Hemisphere's at Point West
Coppell, Texas
Services: Straight Shaft Pier Inspection
D rille r: A ug e r
Pier Identification K.9/1.3 D 11 6
PierDiameter(in) 30 24
Depth of Pier From S u rfa c e (ft) 41.40 43.00
Depth of Bearing Stratum Fro m Surface (ft) 35.10 37.50
R e qui re d P e ne tra tio n (ft) 5.00 5.00
Actual Penetration (ft)" 6.30 5.50
Condition ofBotlom (wet I dry) Dry Dry
Plum b Within Tolerance (yes 1 no) Yes Yes
Casing Diameter(in)/Casina Lenoth (ft) 3 2 13 4 2 6 13 7
N u m be r 0 f Bars 1 Rei n fo rc i n 9 BarSize 8 1 # 6 6 1 # 6
Length of Reinforcing Steel (ft) 40.00 41.70
~c D i;;!ing W35 C c.f!iLle~~.<!{am. {2.I~l______- _ 3~QY~__ 4:10 PM I-.~ ~_n_::C. c..-;;c _ .---:-::...--.::....::....
.~._-- ~.~~- ---
Tim e Concrete was Placed (a m 1 pm) 4:55 PM 5:25 PM
D e p th 0 f Pie r Fro m Top of Concrete (ft) 38.90 42.50
Elevation: Surface (ft).. 98.50 98.50
Elevation: Top of Pier (ft)** 96.00 98.00
E Ie va tio n: B 0 tlo m ofPier(ft)** 57.10 55.50
Elevation: Top of Bear in a Stratum (ft.)" 63.40 61.00
Bearing Stratum (description) Blue s ha Ie
Note: See report # 297521 for Com pressive Strength Test Specim ens.
. Additional Penetration not requested unless noted. HE levation by others
Technician: Chris Harbour Started: 05:45am
Report Distribution:
Orig: Duke Construction, LP (Dallas, TX) Attn: Mr. Paul Byrne
(1-ec copy)
1-cc City of Coppell Attn: Mr. Lee Stone
1-cc City of Coppell Attn: Mr. Larry Davis
Finished: 05:45pm Rone Engineering
p~
~
K. Scott Watson, AET
Project Manager
LIMITATIONS: The test results presented herein were prepared based upon the specific samples provided for testing. We assume no responsibility for variation in quality
(composition, appearance, etc.) or any other feature of similar subject matter provided by persons or conditions over which we have no control. Our letters and reports are
for the exclusive use of the clients to whom they are addressed and shall not be reproduced except in full without the written approval of Rone Engineering Services, Ltd
(CH/LB) Page 2 of 2
Rone Engineering
.
8908 Ambassador Row, Dallas, TX 75247
7701 W Little York, Ste 600, Houston, TX 77040
4421 Freidrich, Ste 195, Austin, TX 78744
Corporate Phone: (214) 630-9745
Client:
Duke Construction, LP
14241 Dallas Pkwy, Ste 1000
Dallas, TX 75254-2936
Report of Drilled Pier Inspection
Report No.: 297759
Project No.: 0712932
Date of Service: 09/04/2007
Report Date: 09/08/2007
Project: Hemisphere's at Point West
Coppell, Texas
Services: Straight Shaft Pier Inspection
Report of Inspection
D rille r: AUQer
Pier Identification B /17 B /16 B /18 B /19 C /1 7
Pier Diameter (in) 24 24 24 24 24
Depth of Pier From Surface (ft) 43.60 43.30 43.20 44.10 46.70
Depth ofBearinQ Stratum Fro m Surface(ft) 37.00 37.50 37.00 37.50 38.00
Required Penetration (ft) 5.00 5.00 5.00 5.00 5.00
A ctua I P e netra tio n (ft)* 6.60 5.80 6.20 6.60 8.70
Condition of Bottom (wet / dry) D rv Dry Dry Dry Dry
Plumb Within Tolerance (ves /no) Yes Yes Yes Yes Yes
Cas i n g 0 i a mete r (i n) / Cas in Q Len Q th (ft) 26/36.5 26/37.5 2 6 /3 6 .7 26/37.5 26/38
-
'i~u:ill)~r \jj-SCif:tt 11\\Jliii'vl...;inQ Bul" 01ze 6 / #6 6 / #6 6 / #6 G ; # 6 -0 1#6
Length of Reinforcing Steel (ft) 42.40 42.00 42.00 42.90 45.40
Time Drillina was Completed (am /pm) 8:17 AM 8:31 AM 8:53 AM 9:15 AM 9 :44 A M
Time Concrete was Placed (am / pm) 9:55 AM 9:30 AM 10:19 AM 1 1 :40 AM 12:20 PM
Depth of Pier From Top of Concrete (ft) 43.10 42.80 42.70 43.60 46.20
Elevation: Surface (ft)** 98.50 98.50 98.50 98.50 98.50
Elevation: Top of Pier (ft)** 98.00 98.00 98.00 98.00 98.00
Elevation: Bottom of Pier (ft)" 5 4 .90 5 5.20 55.30 54.40 51.80
Elevation: Top of Bearina Stratum (ft.) .. 61.50 61.00 61.50 61.00 60.50
BearinQ Stratum (description) Blue shale
Note: See re port # N A fo r Com pre s s ive S tre ng th T est S p e c i men s.
* Additional Penetration not requested unless noted. "Elevation by others
LIMITATIONS The test results presented herein were prepared based upon the specific samples provided for testing. We assume no responsibility for variation in quality
(composition, appearance, etc.) or any other feature of similar subject matter provided by persons or conditions over which we have no control. Our letters and reports are
for the exclusive use of the clients to whom they are addressed and shall not be reproduced except in full without the written approval of Rone Engineering Services, Ltd.
(CHILB) Page 1 of 4
Rone Engineering
.
8908 Ambassador Row, Dallas, TX 75247
7701 W Little York, Ste 600, Houston, TX 77040
4421 Freidrich, Ste 195, Austin, TX 78744
Corporate Phone: (214) 630-9745
Client:
Duke Construction, LP
14241 Dallas Pkwy, Ste 1000
Dallas, TX 75254-2936
Report of Drilled Pier Inspection
Report No.: 297759
Project No.: 0712932
Date of Service: 09/04/2007
Report Date: 09/08/2007
Project: Hemisphere's at Point West
Coppell, Texas
Services: Straight Shaft Pier Inspection
D rille r: Auger
Pier Identification C 118 C /1 9 C /20 C /2 1 B 12 0
Pier Diameter (in) 24 24 24 24 24
De 0 th 0 f Pie r Fro m Surface(ft) 42.70 44.20 41.80 41.70 44.00
Deoth of Bear in a Stratum Fro m Surface(ft) 37.00 38.00 36.1 0 36.10 37.50
Reauired Penetration (ft) 5.00 5.00 5.00 5.00 5.00
A ctua I P e ne tra tio n (ft)' 5.70 6.20 5.70 5.60 6.50
Condition of Bottom (wet/dry) D rv D rv D rv D rv Dry
Plumb Within Tolerance (ves 1 no\ Yes Yes Yes Yes Yes
Casinq Diameter(in)/Casina Lenath (ft) 2 6 /3 7 26/37.3 2 6 /3 6 .1 2 6/36 26/37.5
NumberofBars /Reinforcina BarSize 6 / # 6 6 1 #6 6 1 #6 6 1 # 6 6 / #6
Lenath of Reinforcina Steel (ft) 41 .50 42.90 40.50 40.40 42.60
.! i m." J?_rdl~lJ:Lw '"' 3~'2'" II i~: tc d (e m / pm ) 1 0: 1 1 A!V',- ..1.0:42 AM 1 J :2 9~..h::M 12H}PM-- - +4 5-P M
Time Concrete was Placed (am / pm) 1 :00 PM 1 :29 PM 1:40PM 2 :00 PM 2 :35 P M
Deoth of Pier From Too of Concrete (ft) 42.20 43.70 41.30 41 .20 43.50
Elevation: S u rfa ce (ft).. 98.50 98.50 98.50 98.50 98.50
Elevation: Top of Pier (ft)" 9 8.00 98.00 98.00 98.00 98.00
Elevation: Botto m of Pie r (ft)" 5 5.80 54.30 56.70 56.80 54.50
E Ie va ti 0 n: Top of Bearina Stratum (ft.\" 61.50 60.50 62.40 62.40 61.00
Bearina Stratum (description) Blue shale
Not e' See re port # NA for Com pressive Strength Test S pecim ens.
.. Additional Penetration not requested unless noted. HE levation by others
LIMITATIONS: The test results presented herein were prepared based upon the specific samples provided for testing. We assume no responsibility for variation in quality
(composition, appearance. etc.) or any other feature of similar subject matter provided by persons or conditions over which we have no control. Our letters and reports are
for the exclusive use of the clients to whom they are addressed and shall not be reproduced except in full without the written approval of Rone Engineering Services, Ltd.
(CH/LB) Page 2 of 4
Rone Engineering
.
8908 Ambassador Row, Dallas, TX 75247
7701 W Little York, Ste 600, Houston, TX 77040
4421 Freidrich, Ste 195, Austin, TX 78744
Corporate Phone: (214) 630-9745
Client:
Duke Construction, LP
14241 Dallas Pkwy, Ste 1000
Dallas, TX 75254-2936
Report of Drilled Pier Inspection
Report No.: 297759
Project No.: 0712932
Date of Service: 09/04/2007
Report Date: 09/08/2007
Project: Hemisphere's at Point West
Coppell, Texas
Services: Straight Shaft Pier Inspection
D ri lie r: A uo e r
Pier Identification B /21 1/17 J /17 J /1 8 1/1 8
Pie r D i a mete r (i n) 24 24 24 24 24
De p th 0 f Pie r Fro m Surface(ft) 43.60 43.30 44.40 42.60 43.00
Depth of Bearino Stratum Fro m Surface(ft) 38.30 38.00 37.20 37.00 36.80
Required Penetration (ft) 5.00 5.00 5.00 5.00 5.00
A ctua I P e ne tra tio n (ft)" 5.30 5.30 7.20 5.60 6.20
Condition of Bottom (wet / dry) Dry Dry Dry Dry Dry
Plumb Within Tolerance (ves / no) Yes Yes Yes Yes Yes
Casino Diameter(in)/Casina Lenath (ft) 26/37.8 2 6 /3 7 2 6 /3 7 2 6/3 6 .7 26/36.8
N u m be r 0 f Bars / Rei n fo rc i n g Bar Size 6 / #6 6 / # 6 6 / # 6 6 / #6 6 / # 6
Length of Reinforcing S te e I (ft) 42.40 41 .70 43.10 41.40 41.60
" T im.e-Dti!lLJ:!.B~~~cC em p Ie l~'!!..j.~!!'.:.-.L pm) 1 :3 Q P M 2 : 2lL.E.M 2:5-~~L- - 3.,:1.~ M__.__~ ~1:.1JL_.P_M -'-'= -
Tim e Con c re te was Pia c e d (a m / pm) 2:56 PM 3:35 PM 4:02 PM 4:30 PM 5 :00 PM
D e p th 0 f Pie r Fro m Top of Concrete 1ft) 43.1 0 42.80 43.90 42.10 42.50
Elevation: Surface (ft).. 98.50 98.50 98.50 98.50 98.50
Elevation: Top of Pier (ft).. 98.00 98.00 98.00 98.00 98.00
Elevation: Bottom ofPier(ft)" 54.90 55.20 54.1 0 55.90 55.50
Elevation: Top of Bear in a Stratum (ft.)" 60.20 60.50 61 .30 61 .50 61.70
Bearino Stratum (d e scriptio n) Blue shale
Note. See report # NA for Compressive Strength Test Specimens.
. Additional Penetration not requested unless noted. HE levation by others
LIMITATIONS: The test results presented herein were prepared based upon the specific samples provided for testing. We assume no responsibility for variation in quality
(composition, appearance, etc.) or any other feature of similar subject matter provided by persons or conditions over which we have no control. Our letters and reports are
for the exclusive use of the clients to whom they are addressed and shall not be reproduced except in full without the written approval of Rone Engineering Services, Ltd.
(CH/LB) Page 3 of 4
Rone Engineering
.
8908 Ambassador Row, Dallas, TX 75247
7701 W Little York, Ste 600, Houston, TX 77040
4421 Freidrich, Ste 195, Austin, TX 78744
Corporate Phone: (214)630-9745
Client:
Duke Construction, LP
14241 Dallas Pkwy, Ste 1000
Dallas, TX 75254-2936
Report of Drilled Pier Inspection
Report No.: 297759
Project No.: 0712932
Date of Service: 09/04/2007
Report Date: 09/08/2007
Project: Hemisphere's at Point West
Coppell, Texas
Services: Straight Shaft Pier Inspection
D rille r: Auger
Pie r Id e n ti fi c a ti 0 n J /1 9
PierDiameter(in) 24
D e p th 0 f Pie r Fro m Surface (ft) 43.00
Depth of Bearing Stratum Fro m Surface (ft) 37.00
Required Penetration (ft) 5.00
Actual Penetration (ft) . 6.00
Condition of B 0 Ito m (wet / dry) Dry
Plum b Within To Ie ra nce (yes/no) Yes
Casing Diameter(in)/Casing Lenath (ft) 26/37
N u m be r 0 f Bars / R e info rcing BarSize 6 /#6
L e ng th of R e info rcing S tee I (ft) 41.70
TJE1::e~_r:.iILi.f1.9. .~? s .c-O.fI1_p.~.~~ <!_Ia m / ~..n.u_=---:- ------4-:2-0. P.M-- ==-::"':::::=-=-:-'.- -._.~-- -.:.:.. ..:.:.~-=- ---:-.::::::::-::-:- . -'~- .--- .-
- --- ------ --
Tim e Con c re te was P la c e d (am / pm) NA
Depth of Pier From Top o f Con c re te (ft) 42.50
E leva tio n: S urfa ce (ft)" 9 8.50
Elevation: Top of Pier (ft).. 98.00
Elevation: Boltom of Pier (ft)" 5 5.50
E Ie va tio n: Top of BearinQ Stratum (ft.) .. 61 .50
Bearing Stratum (description) Blue s ha Ie
Note: See report # NA for Com pressive Strength Test Specim ens.
. Additional Penetration not requested unless no Ie d. HE levation by oth e rs
Technician: Chris Harbour Started: 05:45am
Report Distribution:
Orig: Duke Construction, LP (Dallas, TX) Attn: Mr. Paul Byrne
(1-ec copy)
1-cc City of Coppell Attn: Mr. Lee Stone
1-cc City of Coppell Attn: Mr. Larry Davis
Finished: 06:15pm Rone Engineering
p~..~
K. Scott Watson, AET
Project Manager
LIMITATIONS: The test results presented herein were prepared based upon the specific samples provided for testing. We assume no responsibility for variation in quality
(composition, appearance. etc.) or any other feature of similar subject matter provided by persons or conditions over which we have no control. Our letters and reports are
for the exclusive use of the clients to whom they are addressed and shall not be reproduced except in full without the written approval of Rone Engineering Services, Ltd.
(CH/LB) Page 4 of 4
Rone Engineering
.
8908 Ambassador Row, Dallas, TX 75247
7701 W Little York, Ste 600, Houston, TX 77040
4421 Freidrich, Ste 195, Austin, TX 78744
Corporate Phone: (214) 630-9745
Client:
Duke Construction, LP
14241 Dallas Pkwy, Ste 1000
Dallas, TX 75254-2936
Report of In-Place Density Testing
Report No.: 297813
Project No.: 0712932
Date of Service: 09/04/2007
Report Date: 09/08/2007
Project: Hemisphere's at Point West
Coppell, Texas
Services: Perform In-Place Density Testing
PROJECT DATA
Contractor: Duke Construction, LP
Test Method: ASTM D-6938
Gauge: Troxler 3430
Gauge Serial No: 35518
Test Mode: DT
Standard Counts
Moisture Density
Current: 730 Current: 2512
Previous: 734 Previous: 2501
MOISTURE DENSITY RELATIONS
Maximum
Moisture Density Project Requirements
MID No. Description % (pet) Moisture Density
272998 Brown I Silty Clay wi Organics 22.5 96.5 Optimum +4 95 min
.
FIELD DENSITY TESTS
Test Probe MID Moisture Wet Density Dry Density Density
No Test Location Depth No. % (pet) (pet) (%max)
Electric line
80' from south end of electric lines, 3' below 6" 272998 24.9 116.8 93.5 97
grade
Electric line
2 80' from south end of electric lines, 2' below 6" 272998 23.0 116.5 94.7 98
grade
Electric line
3 80' from south end of electric lines, l' below 6" 272998 22.6 117.0 95.4 99
grade
Electric line
4 80' from south end of electric lines, final 6" 272998 23.4 117.6 95.3 99
Electric line
5 280' from south end of electric lines, 3' below 6" 272998 22.9 116.8 95.0 98
grade
Electric line
6 280' from south end of electric lines, 2' below 6" 272998 24.7 117.7 94.4 98
grade
Electric line
7 280' from south end of electric lines, l' below 6" 272998 24.0 116.6 94.0 97
grade
LIMITATIONS: The test results presented herein were prepared based upon the specific samples provided for testing. We assume no responsibility for variation in quality
(composition, appearance. etc.) or any other feature of similar subject matter provided by persons or conditions over which we have no control. Our letters and reports are
for the exclusive use of the clients to whom they are addressed and shall not be reproduced except in full without the written approval of Rone Engineering Services, Ltd.
(CH/LB) Page 1 of 2
Rone Engineering
.
8908 Ambassador Row, Dallas, TX 75247
7701 W Little York, Ste 600, Houston, TX 77040
4421 Freidrich, Ste 195, Austin, TX 78744
Corporate Phone: (214) 630-9745
Client:
Duke Construction, LP
14241 Dallas Pkwy, Ste 1000
Dallas, TX 75254-2936
Report of In-Place Density Testing
Report No.: 297813
Project No.: 0712932
Date of Service: 09/04/2007
Report Date: 09/08/2007
Project: Hemisphere's at Point West
Coppell, Texas
Services: Perform In-Place Density Testing
FIELD DENSITY TESTS
Test Probe MID Moisture Wet Density Dry Density Density
No Test Location Depth No. % (pet) (pet) (%max)
Electric line
8 280' from south end of electric lines, final 6" 272998 24.3 116.8 94.0 97
Technician: Joe Jernigan Started: 09:00am
Report Distribution:
Orig: Duke Construction, LP (Dallas, TX) AUn: Mr. Paul Byrne
(1-ec copy)
1-cc City of Coppell AUn: Mr. Lee Stone
1-cc City of Coppell Attn: Mr. Larry Davis
Finished: 04:15pm Rone Engineering
P-~~
K. Scott Watson, AET
Project Manager
LIMITATIONS: The test results presented herein were prepared based upon the specific samples provided for testing. We assume no responsibility for variation in quality
(composition, appearance, etc.) or any other feature of similar subject matter provided by persons or conditions over which we have no control. Our letters and reports are
for the exclusive use of the clients to whom they are addressed and shall not be reproduced except in full without the written approval of Rone Engineering Services, LId
(CHILB) Page 2 of 2
Rone Engineering
.
8908 Ambassador Row, Dallas, TX 75247
7701 W Little York, Ste 600, Houston, TX 77040
4421 Freidrich, Ste 195, Austin, TX 78744
Corporate Phone: (214) 630-9745
Client:
Duke Construction, LP
14241 Dallas Pkwy, Ste 1000
Dallas, TX 75254-2936
Report of Drilled Pier Inspection
Report No.: 297381
Project No.: 0712932
Date of Service: 08/30/2007
Report Date: 09/08/2007
Project: Hemisphere's at Point West
Coppell, Texas
Services: Straight Shaft Pier Inspection
D rille r: Auger
Pie r Id e ntifica tio n E 116 J.3/0.9
PierDiameter(in) 24 30
Depth of Pier From Surface (ft) 44.00 43.70
Depth of Bearing Stratum Fro m Surface 1ft) 3750 37.00
Required Penetration (ftl 5.00 5.00
Actual Penetration (ft)* 6.50 6.70
Condition of Bolt om (wet 1 dry) Dry Dry
Plumb Within Tolerance (ves Ino) Yes Yes
Casing Diameter(in)/Casina Lenath (ft) 2 6 13 7 .1 32/34.8
NumberofBars IReinforcina BarSize 6 1 #6 8 1 # 6
Length of Reinforcing S te e I (ft) 42.70 42.80
~Time~iJling...\I_~~..::C~p~ted (am~.!.!!..L:c~~ 1 :37 PM ~8.-P ~__ ____ - :...::c-...:= ----,_.__. - .. -~.- -
.-.-- ------- ..- -- -- -
Tim e Con c re te was P la c e d (am 1 pm) 2:30 PM 3:25 PM
De p th 0 f Pie r Fro m Top of Con c re Ie (ft) 43.50 41.20
E Ie va Ii 0 n: S u rfa c e (ft) ** 98.50 98.50
E Ie va Ii 0 n: Top of Pier (ft)** 98.00 96.00
Elevation: Bottom of Pier (ft)** 54.50 54.80
E Ie va ti 0 n : Top of Bearina Stratum (ft.) ** 61.00 61 .50
Bearing Stratum (description) Blue s ha Ie
Not e: See re port # NA for Com pressive Strength Test Specim ens.
.,. Additional Penetration not requested unless noted. HE levalion by others
Remarks: Piers completed on 8/29 and not placed, per Dick Cirrio with Duke Construction; no additional penetration
required.
Technician: Chris Harbour Started: 06:00am
Report Distribution:
Orig: Duke Construction, LP (Dallas, TX) Attn: Mr. Paul Byrne
(1-ec copy)
1-cc City of Coppell Attn: Mr. Lee Stone
1-cc City of Coppell AUn: Mr. Larry Davis
Finished: 04:00pm Rone Engineering
P-~~
K. Scott Watson, AET
Projecl Manager
LIMITATIONS: The test results presented herein were prepared based upon the specific samples provided for testing. We assume no responsibility for variation in quality
(composition, appearance, etc.) or any other feature of similar subject matter provided by persons or conditions over which we have no control. Our letters and reports are
for the exclusive use of the clients to whom they are addressed and shall not be reproduced except in full without the written approval of Rone Engineering Services, Ltd.
(CH/LB) Page 3 of 3
Rone Engineering
.
8908 Ambassador Row, Dallas, TX 75247
7701 W Little York, Ste 600, Houston, TX 77040
4421 Freidrich, Ste 195, Austin, TX 78744
Corporate Phone: (214) 630-9745
Client:
Duke Construction, LP
14241 Dallas Pkwy, Ste 1000
Dallas, TX 75254-2936
Report of Drilled Pier Inspection
Report No.: 297381
Project No.: 0712932
Date of Service: 08/30/2007
Report Date: 09/08/2007
Project: Hemisphere's at Point West
Coppell, Texas
Services: Straight Shaft Pier Inspection
D rille r: Auger
Pie r Id e n ti fi c a ti 0 n J /16 1/1 6 H /16 G /16 F /16
PierDiameter(in) 24 24 24 24 24
De 0 th 0 f Pie r Fro m S u rfa c e (ft) 44.00 42.60 42.50 43.00 43.50
Deoth of Bear in a Stratum Fro m Surface(ft) 37.50 37.00 36.50 37.40 37.00
Required P e netra tio n (ft) 5.00 5.00 5.00 5.00 5.00
Actual Penetration (ft)' 6.50 5.60 6.00 5.60 6.50
Condition of Bottom (wet/drv) D rv D rv D rv D rv D rv
P lu m b With i n Tole ra n c e (ve s / no) Yes Yes Yes Yes Yes
Casina Diameter(in)/Casina Lenath (ft) 26/37.5 26/36.5 26/36.5 26/37 .1 2 6 /3 6 .4
NumberofBars /Reinforcina BarSize 6 / # 6 6 / #6 6 / #6 6 / #6 6 / #6
Lenath of Reinforcina Steel (ft) 42.80 41 .30 41 .30 41 .80 42.30
_.T;~ ~?-.!.i..~IL!.~. o""'! ~ "._~~._~~)~_i!-~~ ;.t.~ ~) .~l!:-_-.:~~ " 11 :30 A-M ~~05 P~_ :..~"52E..~_ "." 1<.7 r M . .::- .l\}..f2-~ ..
.----.- - '~-'--'--'-.-~-----
Tim e Con c re te was P la c e d (a m /0 m) 9 :5 1 AM 1 0 :29 AM 11:17AM 1 1 :44 AM 1 :00 PM
Deoth of Pier From Too of Concrete (ft) 43.50 42.10 42.00 42.50 43.00
Elevation: S u rfa ce (ft).. 98.50 98.50 98.50 98.50 98.50
Elevation: Too of Pier (ft).. 98.00 98.00 98.00 98.00 98.00
Elevation: Botto m of Pie r (fl)" 5 4.50 55.90 56.00 55.50 55.00
Elevation: Too of Bear in a Stratum (ft.)" 61 .00 61 .50 62.00 61 .10 61 .50
Bearina Stratum (descriotion) Blue s ha Ie
Note See report # NA for Com pressive Strength Test S pecim ens.
'Additional Penetration not requested unless noted. HE levation by others
LIMITATIONS: The test results presented herein were prepared based upon the speCific samples provided for testing. We assume no responsibility for variation in quality
(composition, appearance, etc.) or any other feature of similar subject matter provided by persons or conditions over which we have no control. Our letters and reports are
for the exclusive use of the clients to whom they are addressed and shall not be reproduced except in full without the written approval of Rone Engineering Services, Ltd.
(CH/LB) Page 2 of 3
Rone Engineering
.
8908 Ambassador Row, Dallas, TX 75247
7701 W Little York, Ste 600, Houston, TX 77040
4421 Freidrich, Ste 195, Austin, TX 78744
Corporate Phone: (214) 630-9745
Client:
Duke Construction, LP
14241 Dallas Pkwy, Ste 1000
Dallas, TX 75254-2936
Report of Drilled Pier Inspection
Report No.: 297381
Project No.: 0712932
Date of Service: 08/30/2007
Report Date: 09/08/2007
Project: Hemisphere's at Point West
Coppell, Texas
Services: Straight Shaft Pier Inspection
Report of Inspection
D rille r: Auaer
Pie r Id e n ti fi c a ti 0 n F 11 5 G 115 H 11 5 1/1 5 J 11 5
PierDiameter(in) 24 24 24 24 24
Depth of Pier From Surface (ft) 43.00 43.00 44.50 45.00 43.90
Depth of Bear in a Stratum Fro m Surface(ft) 36.40 36.20 37.00 38.00 38.00
Required Penetration (ft) 5.00 5.00 5.00 5.00 5.00
Actual Penetration (ft)' 6.60 6.80 7.50 7.00 5.90
Condition of Boll om (wet I dry) Dry Dry Dry Dry Dry
P lu m b With i n Tole ra n c e (ve sIn 0) Yes Yes Yes Yes Yes
Casing Diameter(in\/Casing Length (ft) 26/36.4 26/36 26/36.5 2 6 13 7 26/37.4
iNl'nlO~r ofBciiS ,ReinforciilgBar Size o 1"# 6 (; 1#6 6 I #-6 d" .""c.Tif6 6,-#6
Length of Reinforcing Steel (ft) 40.80 41.30 42.10 43.90 42.60
Time Drillina was Completed (am Ipm) 7:31 AM 7 :4 9 AM 8: 1 1 AM 8 :2 7 AM 8 :4 6 AM
Time Concrete was Placed (am Ipm) 8:14 AM 8 :55 AM 9 :50 AM 10:15AM 1 1 :05 AM
Depth of Pier From Top of Concrete (ft) 42.50 42.50 44.00 44.50 43.40
Elevation: Surface (ft)** 98.50 98.50 98.50 98.50 98.50
Elevation: Top of Pier (ft)" 9 8.00 98.00 98.00 98.00 98.00
Elevation: Bolio m of Pier (ft)" 5 5.50 55.50 54.00 53.50 54.60
Elevation. Top of Bear in a Stratum (ft.)" 62.1 0 62.30 61 .50 60.50 60.50
Bearing Stratum (d e scriptio n) Blue shale
Note: See re port # fo r Com pre s s ive S tre n g th T est S p e c i men s.
'AdditionalPenetration notrequested unless noted. "Elevation byothers
LIMITATIONS: The test results presented herein were prepared based upon the specific samples provided for testing. We assume no responsibility for variation in quality
(composition, appearance, etc.) or any other feature of similar subject matter provided by persons or conditions over which we have no control. Our letters and reports are
for the exclusive use of the clients to whom they are addressed and shall not be reproduced except in full without the written approval of Rone Engineering Services, Ltd.
(CH/LB) Page 1 of 3
Rone Engineering
.
Client:
Duke Construction, LP
14241 Dallas Pkwy, Ste 1000
Dallas, TX 75254-2936
Project: Hemisphere's at Point West
Coppell, Texas
Services: Straight Shaft Pier Inspection
Report of Inspection
D rille r:
A UQ e r
Pier Identification
Pier Diameter (in)
Depth of Pier From Surface (ft)
Depth ofBearinQ Stratum From Surface (ft)
Required Penetration (ft)
A ctua I P e ne tra tio n (ft)'
Condition of Bottom (wet/dry)
Plumb Within Tolerance (ves 1 no)
C asinQ Diameter (in) 1 C asinQ LenQth (ft)
'NtHnOe, OJ Bd'S ;~p.<.,"f()((;lny-8a-rSCjLe
Length of Reinforcina Steel (ft)
Time Drillina was Completed (am Ipm)
Time Concrete was Placed (am Ipm)
Depth of Pier From Top of Concrete (ft)
Elevation: Surface (ft)'"
Elevation: Top of Pier (ft)**
Elevation: Bottom of Pier (ft)""
Elevation: Top ofBearinQ Stratum (ft.)**
Bearina Stratum (description)
B 11 3
24
44.10
37.60
5.00
6.50
Dry
Yes
26/37.2
--~--- '=-:---~ ~ -.::~-6.1 # ff
42.90
8:15 AM
9:00 AM
43.60
98.50
98.00
54.40
60.90
8908 Ambassador Row, Dallas, TX 75247
7701 W Little York, Ste 600, Houston, TX 77040
4421 Freidrich, Ste 195, Austin, TX 78744
Corporate Phone: (214) 630-9745
Report of Drilled Pier Inspection
Report No.: 297066
Project No.: 0712932
Date of Service: 08/28/2007
Report Date: 09/08/2007
C 11 3
24
44.40
38.50
5.00
5.90
Dry
Yes
26/38.5
.. T3 1# 6
43.20
7 :54 AM
9:30 AM
43.90
98.50
98.00
54.10
60.00
D 11 3
24
42.30
36.40
5.00
5.90
D rv
Yes
2 6/3 6 .4
, 61#6
41 .20
8:32 AM
9:55 AM
41 .80
98.50
98.00
56.20
62.10
Blue shale
E 113
24
42.40
36.50
5.00
5.90
Dry
Yes
26/36.5
- 6 1# 6 - --
41 .1 0
8 :4 9 AM
10:30 AM
41.90
98.50
98.00
56.10
62.00
Note: See re port # N A fo r Com pre s s i ve S tre n g th T est S p e c i men s .
"Additional Penetration not requested unless noted. **Elevation by others
F /13
24
43.20
36.50
5.00
6.70
Dry
Yes
26/36 .5
6 1 # 6
42.00
9:39 AM
11:00AM
42.70
98.50
98.00
55.30
62.00
LIMITATIONS: The test results presented herein were prepared based upon the specific samples provided for testing. We assume no responsibility for variation in quality
(composition, appearance, etc.) or any other feature of similar subject matter provided by persons or conditions over which we have no control. Our letters and reports are
for the exclusive use of the clients to whom they are addressed and shall not be reproduced except in full without the written approval of Rone Engineering Services, Ltd.
(CH/LB) Page 1 of 3
Rone Engineering
.
8908 Ambassador Row, Dallas, TX 75247
7701 W Little York, Ste 600, Houston, TX 77040
4421 Freidrich, Ste 195, Austin, TX 78744
Corporate Phone: (214) 630-9745
Client:
Duke Construction, LP
14241 Dallas Pkwy, Ste 1000
Dallas, TX 75254-2936
Report of Drilled Pier Inspection
Report No.: 297066
Project No.: 0712932
Date of Service: 08/28/2007
Report Date: 09/08/2007
Project: Hemisphere's at Point West
Coppell, Texas
Services: Straight Shaft Pier Inspection
D ri lie r: A ua e r
Pie r Id e ntifica tio n G /13 H /1 3 1/1 3 J 13 B.9/0.9
Pie r D i a mete r (i n) 24 24 24 24 30
De p th 0 f Pie r Fro m S urfa ce (ft) 44.00 44.50 45.00 42.50 47.40
Depth of Bearina Stratum Fro m Surface(ft) 36.40 37.80 38.30 37.00 36.50
Required Penetration (ft) 5.00 5.00 5.00 5.00 5.00
Actual Penetration (fl)' 7.60 6.70 6.70 5.50 10.90
Condition of Bottom (wet/dry) Dry Dry Dry Dry Dry
Plumb Within Tolerance (ves 1 no) Yes Yes Yes Yes Yes
Casing Diameter(in)/Casina Lenath (fl) 26/36.5 26/37 26/36.3 26/36 32/35.8
NumberofBars IReinforcing BarSize 6 1 # 6 6 1 #6 6 1 # 6 6 / #6 6 1 #6
Length of Reinforcina Steel (fl) 42.70 43.10 43.60 41.20 45.80
.t-J_;dLi:=__~~l;j..~~.~')~r:,~ m ~:!:.i_~ d__(~,~~l 1 ~ n1) 10:01 A~cc::. 10 :3 1 AM -,-~:1..:0 DAM- 1 1 .:.2..5 AM_ ~5.-.P _M _
-- .-.--,.- --~-- ._.,..~-~
Time Concrete was P la c e d (am 1 pm) 1 1 :40 AM 12: 19 PM 3:15 PM 3:40 PM 1 :40 P M
D e p th 0 f Pie r Fro m Top of Concrete (ft) 43.50 44.00 44.50 42.00 44.90
Elevation: Surface (ft)** 98.50 98.50 98.50 98.50 98.50
Elevation:Top of Pier (fl)** 98.00 98.00 98.00 98.00 96.00
Elevation: Bottom of Pie r (ft)** 54.50 54.00 53.50 56.00 51 .1 0
Elevation: Top of Bear in a Stratum (fl.)** 62.10 60.70 60.20 61.50 62.00
Bearing Stratum (d escriptio n) Blue sha Ie
Note See re port # NA for Compressive Strength Test Specimens.
* Additional Penetration not requested unless noted HE levation by others
LIMITATIONS: The test results presented herein were prepared based upon the specific samples provided for testing. We assume no responsibility for variation in quality
(composition, appearance, etc.) or any other feature of similar subject matter provided by persons or conditions over which we have no control. Our letters and reports are
for the exclusive use of the clients to whom they are addressed and shall not be reproduced except in full without the written approval of Rone Engineering Services, Ltd.
(CH/LB) Page 2 of 3
Rone Engineering
.
8908 Ambassador Row, Dallas, TX 75247
7701 W Little York, Ste 600, Houston, TX 77040
4421 Freidrich, Ste 195, Austin, TX 78744
Corporate Phone: (214) 630-9745
Client:
Duke Construction, LP
14241 Dallas Pkwy, Ste 1000
Dallas, TX 75254-2936
Report of Drilled Pier Inspection
Report No.: 297066
Project No.: 0712932
Date of Service: 08/28/2007
Report Date: 09/08/2007
Project: Hemisphere's at Point West
Coppell, Texas
Services: Straight Shaft Pier Inspection
D rille r: A UQ e r
Pie rid e ntifica tio n B.9/1.1
PierDiameter(in) 30
D e p th 0 f Pie r Fro m Surface (ft) 43.00
Depth ofBearinQ Stratum Fro m Surface (ft) 37.00
Required Penetration (ft) 5.00
Actual Penetration (ft)" 6.00
Condition of Bottom (wet 1 dry) Dry
Plumb Within Tolerance (ves Ino) Yes
Casinq Diameter(in)/Casinq LenQth(ft) 32/35
NumberofBars IReinforcinQ BarSize 8 1 #6
LenQth of Reinforcing Steel (ft) 41.00
~ jE'~ DriHin) _",,_~~",,_~-c__~_E'le!..e .E..l?.ITL i..f>_f1I.l._ .-----,,- _t:~:'i PM __ ...:-=.:-:....---- -. ----,.....- -' -=-- -- 1--- -- . ._.-. ...-
------
Time Con c re te was P la c e d (am 1 pm) 2:43 PM
Depth of Pier From Top of Concrete (ft) 40.50
Elevation: Surface (ft) .. 98.50
E Ie va ti 0 n: Top of P ie r (ft).. 96.00
Elevation: Bottom of Pier (ft)"" 55.50
E Ie va ti 0 n : Top of BearinQ Stratum (ft.) .. 61.50
BearinQ Stratum (d e scriptio n) Blue shale
Note: See report # NA for Com pressive Strength Test S pecim ens.
. Additional Penetration not requested unless noted. HE levation by others
Remarks: Initial bottom of pier from 8/24, 43 0, per Dick with Duke Construction, just wanted hole cleaned out and placed.
Technician: Chris Harbour Started: 05:45am
Report Distribution:
Orig: Duke Construction, LP (Dallas, TX) Attn: Mr. Paul Byrne
(1-ec copy)
1-cc City of Coppell Alln: Mr. Lee Stone
1-cc City of Coppell Attn: Mr. Larry Davis
Finished: 04:45pm Rone Engineering
p~~
K. Scott Watson, AET
Project Manager
LIMITATIONS: The test results presented herein were prepared based upon the specific samples provided for testing. We assume no responsibility for variation in quality
(composition, appearance, etc.) or any other feature of similar subject matter provided by persons or conditions over which we have no control. Our letters and reports are
for the exclusive use of the clients to whom they are addressed and shall not be reproduced except in full without the written approval of Rone Engineering Services, Ltd.
(CH/LB) Page 3 of 3
Rone Engineering
.
8908 Ambassador Row, Dallas, TX 75247
7701 W Little York, Ste 600, Houston, TX 77040
4421 Freidrich, Ste 195, Austin, TX 78744
Corporate Phone: (214) 630-9745
Client:
Duke Construction, LP
14241 Dallas Pkwy, Ste 1000
Dallas, TX 75254-2936
Report of In-Place Density Testing
Report No.: 297272
Project No.: 0712932
Date of Service: 08/29/2007
Report Date: 09/08/2007
Project: Hemisphere's at Point West
Coppell, Texas
Services: Perform In-Place Density Testing
PROJECT DATA
Contractor: Duke Construction, LP
Test Method: ASTM 0-6938
Gauge: Troxler 3430
Gauge Serial No: 35518
Test Mode: DT
Standard Counts
Moisture Density
Current: 735 Current: 2500
Previous: 729 Previous: 2514
MOISTURE DENSITY RELATIONS
Maximum
Moisture Density Project Requirements
MID No. Description % (pet) Moisture Density
272998 Brown I Silty Clay wI Organics 22.5 96.5 Minimum +4 92-96
FIELD DENSITY TESTS
Test Probe MID Moisture Wet Density Dry Density Density
No Test Location Depth No. % (pet) (pet) (%max)
-
Utility backfill
25' from south end of phone line, l' below grade 6" 272998 29.2 115.0 89.0 92
Utility backfill
2 25' from south end of phone line, final 6" 272998 30.4 115.7 88.7 92
Utility backfill
3 125' from south end of phone line, l' below 6" 272998 28.9 118.5 91.9 95
grade
Utility backfill
4 125' from south end of phone line, final 6" 272998 31.0 118.0 90.1 93
Utility backfill
5 25' from south end of power line, l' below grade 6" 272998 30.0 118.3 91.0 94
Utility backfill
6 25' from south end of power line, final 6" 272998 31.8 118.4 89.8 93
Utility backfill
7 125' from south end of power line, l' below 6" 272998 30.4 117.5 90.1 93
grade
Utility backfill
8 125' from south end of power line, final 6" 272998 31.5 118.5 90.1 93
LIMITATIONS: The test results presented herein were prepared based upon the specific samples provided for testing. We assume no responsibility for variation in quality
(composition, appearance, etc.) or any other feature of similar subject matter provided by persons or conditions over which we have no control. Our letters and reports are
for the exclusive use of the clients to whom they are addressed and shall not be reproduced except in full without the written approval of Rone Engineering Services, Ltd.
(CH/LB) Page 1 of 2
Rone Engineering
.
8908 Ambassador Row, Dallas, TX 75247
7701 W Little York, Ste 600, Houston, TX 77040
4421 Freidrich, Ste 195, Austin, TX 78744
Corporate Phone: (214) 630.9745
Client:
Duke Construction, LP
14241 Dallas Pkwy, Ste 1000
Dallas, TX 75254-2936
Report of In-Place Density Testing
Report No.: 297272
Project No.: 0712932
Date of Service: 08/29/2007
Report Date: 09/08/2007
Project: Hemisphere's at Point West
Coppell, Texas
Services: Perform In.Place Density Testing
FIELD DENSITY TESTS
Test Probe MID Moisture Wet Density Dry Density Density
No Test Location Depth No. % (pet) (pet) (%max)
-
Utility backfill
9 6" Sanitary sewer center line, 50' from north 6" 272998 29.2 115.1 89.1 92
end, 2' below grade
Utility backfill
10 6" Sanitary sewer center line, 50' from north 6" 272998 28.3 114.2 89.0 92
end, l' below grade
Utility backfill
11 6" Sanitary sewer center line, 50' from north 6" 272998 28.7 117.4 91.2 95
end, final
Technician: Joe Jernigan Started: 11 :OOam Finished: 01 :OOpm
Report Distribution:
Orig: Duke Construction, LP (Dallas, TX) Attn: Mr. Paul Byrne
(1.ec copy)
1.cc City of Coppell Attn: Mr. Lee Stone
1-cc City of Coppell Attn: Mr. Larry Davis
K. Scott Watson, AET
Project Manager
LIMITATIONS The test results presented herein were prepared based upon the specific samples provided for testing. We assume no responsibility for variation in quality
(composition. appearance, etc.) or any other feature of similar subject matter provided by persons or conditions over which we have no control. Our letters and reports are
for the exclusive use of the clients to whom they are addressed and shall not be reproduced except in full without the written approval of Rone Engineering Services. Ltd.
(CH/LB) Page 2 of 2