Duke Lesley 2A-LR070914
Rone Engineering
.
8908 Ambassador Row, Dallas, TX 75247
7701 W Little York, Ste 600, Houston, TX 77040
4421 Freidrich, Ste 195, Austin, TX 78744
Corporate Phone: (214) 630-9745
Client:
Duke Construction, LP
14241 Dallas Pkwy, Ste 1000
Dallas, TX 75254-2936
Report of Reinforcing Steel Inspection
Report No.: 297740
Project No.: 0712932
Date of Service: 09/01/2007
Report Date: 09/14/2007
Project: Hemisphere's at Point West
Coppell, Texas
Services: Reinforcing Steel Inspection
Report of Inspection
Locations and Items Inspected:
Building slab on grade, grid lines 1.1-11/A.1-C.
Item s Ins peel ed: Conforming Non 11ems Inspected: Co nfo rm ing Non Items Inspected: Co nfo rm ing Non
Conforming Conforming Conforming
P lacing Drawings Bar Length Column Ties Properly
Approved x and Shape x Tied and Spaced NA
Bar Size x Proper B ar Placement x Stirrup Spacing NA
Bar Grade x ProperiyTied x Stirrup Type NA
8 ars C iean x Dowel Bars in Place x Lapped Spilces x
Form Clean x Pro per Bar Suppo rts NA CornerBars NA
Numberof Bars x Pro per Co ver NA Mechanical Spilces NA
Discrepancies 1 Comments:
1. Chairs to be placed during concrete placement.
Technician: Chris Harbour Started: 10:00am
Report Distribution:
Orig: Duke Construction, LP (Dallas, TX) Attn: Mr. Paul Byrne
(1-ec copy)
1-cc City of Coppell Attn: Mr. Lee Stone
1-cc City of Coppell Attn: Mr. Larry Davis
Finished: 11 :30am
Rone Engineering
P-~~
K. Scott Watson, AET
Project Manager
LIMITATIONS: The test results presented herein were prepared based upon the specific samples provided for testing. We assume no responsibility for variation in quality
(composition, appearance, etc.) or any other feature of similar subject matter provided by persons or conditions over which we have no control. Our letters and reports are
for the exclusive use of the clients to whom they are addressed and shall not be reproduced except in full without the written approval of Rone Engineering Services, Ltd.
(TMIKW) Page 1 of 1
Rone Engineering
.
8908 Ambassador Row, Dallas, TX 75247
7701 W Little York, Ste 600, Houston, TX 77040
4421 Freidrich, Ste 195, Austin, TX 78744
Corporate Phone: (214) 630-9745
Client:
Duke Construction, LP
14241 Dallas Pkwy, Ste 1000
Dallas, TX 75254-2936
Report of Reinforcing Steel Inspection
Report No.: 297829
Project No.: 0712932
Date of Service: 09/04/2007
Report Date: 09/14/2007
Project: Hemisphere's at Point West
Cappell, Texas
Services: Reinforcing Steel Inspection
Report of Inspection
Locations and Items Inspected:
3 pie r caps, 9 rid line s J .2/010.9-1.1, K .9-L.1/1.5-2, K.9-L.1/3.
Items Inspected: Co nfo rm ing Non Items Inspected: Co nfo rm ing Non Ilem s Ins peeled: Conforming Non
Co nforming Conforming Conforming
P lac ing Drawings Bar Length Column Ties Properly
Approved x and Shape x Tied and Spaced NA
Bar Size x P ra per Bar P lacem ent x Stirrup Spacing x
Bar Grade x Pro perly Tied x Stirrup Type x
Bars Clean x DowelBars in Place x Lapped Splices x
Form Clean x Pro per Bar Suppa rts x CornerBars NA
Numberof Bars x ProperCover x Mechanical Splices NA
Discrepancies 1 Comments:
No apparent discrepancies were noted at the locations listed above.
Technician: Chris Harbour Rone Engineering
See Report 297759 for technician time~~
Report Distribution: , , '" ' ' , ~
Orig: Duke Construction, LP (Dallas, TX) Altn: Mr. Paul Byrne ',. ,. , " '.' ~'
(1-ec copy) ,-
1-cc City of Coppell Altn: Mr. Lee Stone K S It W t AET
. L D' ,co a son,
1-cc City of Coppell Altn: Mr. arry aVls p . t M
rOJec anager
LIMITATIONS: The test results presented herein were prepared based upon the specific samples provided for testing. We assume no responsibility for variation in quality
(composition, appearance, etc.) or any other feature of similar subject matter provided by persons or conditions over which we have no control. Our letters and reports are
for the exclusive use of the clients to whom they are addressed and shall not be reproduced except in full without the written approval of Rone Engineering Services. Ltd.
(fM/KW) Page 1 of 1
Rone Engineering
.
8908 Ambassador Row, Dallas, TX 75247
7701 W Little York, Ste 600, Houston, TX 77040
4421 Freidrich, Ste 195, Austin, TX 78744
Corporate Phone: (214) 630-9745
Client:
Duke Construction, LP
14241 Dallas Pkwy, Ste 1000
Dallas, TX 75254-2936
Report of Reinforcing Steel Inspection
Report No.: 297942
Project No.: 0712932
Date of Service: 09/06/2007
Report Date: 09/14/2007
Project: Hemisphere's at Point West
Coppell, Texas
Services:
Report of Inspection
Locations and Items Inspected:
Building slab on grade, grid lines E-G/1.1-11.
Items Inspected: Conforming Non Items Inspected" Co nto rm ing Non Item sins peeted: Co nfo rm ing Non
Conforming Conforming Conforming
Placing Drawings Bar Length Column Ties Pro perly
Approved x and Shape x Tied and Spaced NA
Bar Size x Pro per Bar P lac em ent x Stirrup Spacing NA
Bar Grade x Pro perly Tied x Stirrup Type NA
Bars Clean x Dowel Bars in Place NA Lapped Splices x
Form Clean x Pro per B ar Supports NA Corner Bars NA
Numberof Bars x Proper Cover x Mechanical Splices NA
Discrepancies / Comments:
1. Dowels and chairs to be placed during concrete placement.
Technician: Chris Harbour Started: 05:45am
Report Distribution:
Orig: Duke Construction, LP (Dallas, TX) Attn: Mr. Paul Byrne
(1-ec copy)
1-cc City of Coppell Attn: Mr. Lee Stone
1-cc City of Coppell Attn: Mr. Larry Davis
Finished: 08:45am
Rone Engineering
~~~
K. Scott Watson, AET
Project Manager
LIMITATIONS: The test results presented herein were prepared based upon the specific samples provided for testing. We assume no responsibility for variation in quality
(composition, appearance, etc.) or any other feature of similar subject matter provided by persons or conditions over which we have no control. Our letters and reports are
for the exclusive use of the clients to whom they are addressed and shall not be reproduced except in full without the written approval of Rone Engineering Services, Ltd.
(TMIKW) Page 1 of 1
Rone Engineering
.
8908 Ambassador Row, Dallas, TX 75247
7701 W Little York, Ste 600, Houston, TX 77040
4421 Freidrich, Ste 195, Austin, TX 78744
Corporate Phone: (214) 630-9745
Client:
Duke Construction, LP
14241 Dallas Pkwy, Ste 1000
Dallas, TX 75254-2936
Report of Reinforcing Steel Inspection
Report No.: 298161
Project No.: 0712932
Date of Service: 09/07/2007
Report Date: 09/14/2007
Project: Hemisphere's at Point West
Coppell, Texas
Services: Reinforcing Steel Inspection
Report of Inspection
Locations and Items Inspected:
Building slab on grade, grid lines J-K.9/1.1-11.
Item s Inspected' Co nfo rming Non Ilem s Ins peeled: Co nfo rm ing Non lIem sins peeted: Co nfo rming Non
Conforming Co nfo rm ing Conforming
P lacing Drawings Bar Length CD lum n Ties Pro parly
Appro ved x and Shape x Tied and Spaced NA
Bar Size x Proper Bar P lac em ent x Stirrup Spacing NA
Bar Grade x Pro perly Tied x Stirrup Type NA
Bars Clean x Dowel Bars in Place x Lapped Splices x
Form Clean x Proper Bar Suppo rts x Co mer 8 ars NA
Number of Bars x ProperCover x Mechanical Splices NA
Discrepancies / Comments:
1. Chairs to be placed during concrete placement.
Technician: Chris Harbour
Rone Engineering
seeReport298032fortechniCiantime", ~ ',' ','~, ~,.'-,""'" ',' ','
Paul Byrne ~
K. Scott Watson, AET
Project Manager
Report Distribution:
Orig: Duke Construction. LP (Dallas, TX) Attn: Mr,
(1-ec copy)
1-cc City of Coppell Attn: Mr. Lee Stone
1-cc City of Coppell Attn: Mr. Larry Davis
~
LIMITATIONS: The test results presented herein were prepared based upon the specific samples provided for testing, We assume no responsibility for variation in quality
(composition, appearance, etc,) or any other feature of similar subject matter provided by persons or conditions over which we have no control. Our letters and reports are
for the exclusive use of the clients to whom they are addressed and shall not be reproduced except in full without the written approval of Rone Engineering Services, Ltd,
(TM/KW) Page 1 of 1
Rone Engineering
.
8908 Ambassador Row, Dallas, TX 75247
7701 W Little York, Ste 600, Houston, TX 77040
4421 Freidrich, Ste 195, Austin, TX 78744
Corporate Phone: (214) 630-9745
Client:
Duke Construction, LP
14241 Dallas Pkwy, Ste 1000
Dallas, TX 75254-2936
Report of Reinforcing Steel Inspection
Report No.: 298221
Project No.: 0712932
Date of Service: 09/08/2007
Report Date: 09/14/2007
Project: Hemisphere's at Point West
Coppell, Texas
Services: Reinforcing Steel Inspection
Report of Inspection
Locations and Items Inspected:
Building slab on grade, grid lines E-G/1.1-11, re-inspection after steel and
poly removed following rain event to allow subgrade to dry.
Items Inspected. Conforming Non Items Inspected: Co nfo rm ing Non Item sins pected: Conforming Non
Conforming Conforming CD nfo rm ing
Placing Drawings Bar Length Column Ties Pro perly
Approved x and Shape x Tied and Spaced NA
Bar Size x Proper B ar Placement x Stirrup Spacing NA
Bar Grade x Pro perly Tied x Stirrup Type NA
Bars Clean x Dowel Bars in Place x Lapped Splices x
Form Clean x Pro per Bar Suppa rts x Corner Bars NA
Num ber of Bars x ProperCover x Mechanical Splices NA
Discrepancies / Comments:
1. Chairs to be added during concrete placement.
Technician: Chris Harbour Rone Engineering
See Report 298197 for technician time~~
Report Distribution: .. . .
Orig: Duke Construction, LP (Dallas, TX) Alln: Mr. Paul Byrne . .. ... ..... ... . . . ·
(1-ec copy) .
1-cc C~ty of Coppell Alln: Mr. Lee Stone. K. Scott Watson, AET
1-cc City of Coppell Alln: Mr. Larry DavIs p . t M
rOJec anager
:~
LIMITATIONS: The test results presented herein were prepared based upon the specific samples provided for testing. We assume no responsibility for variation in quality
(composition, appearance, etc.) or any other feature of similar subject matter provided by persons or conditions over which we have no control. Our letters and reports are
for the exclusive use of the clients to whom they are addressed and shall not be reproduced except in full without the written approval of Rone Engineering Services, Ltd.
(TMlKW) Page 1 of 1
Rone Engineering
.
8908 Ambassador Row, Dallas, TX 75247
7701 W Little York, Ste 600, Houston, TX 77040
4421 Freidrich, Ste 195, Austin, TX 78744
Corporate Phone: (214) 630-9745
Client:
Duke Construction, LP
14241 Dallas Pkwy, Ste 1000
Dallas, TX 75254-2936
Report of In-Place Density Testing
Report No.: 298123
Project No.: 0712932
Date of Service: 09/07/2007
Report Date: 09/14/2007
Project: Hemisphere's at Point West
Coppell, Texas
Services: Perform In-Place Density Testing
PROJECT DATA
Contractor: Duke Construction, LP
Test Method: ASTM D-6938
Gauge: Troxler 3430
Gauge Serial No: 35518
Test Mode: DT
Standard Counts
Moisture Density
Current: 730 Current: 2519
Previous: 731 Previous: 2494
MOISTURE DENSITY RELATIONS
Maximum
Moisture Density Project Requirements
MID No. Description % (pet) Moisture Density
272998 Brown / Silty Clay wI Organics 22.5 96.5 Optimum +4 95 min
FIELD DENSITY TESTS
Test Probe MID Moisture Wet Density Dry Density Density
No Test Location Depth No. % (pet) (pet) (% max)
Trench fill
480' from south end of electric line, 3' below 6" 272998 23.1 117.1 95.1 99
grade
Trench fill
2 480' from south end of electric line, 2' below 6" 272998 23.0 117.5 95.5 99
grade
Trench fill
3 480' from south end of electric line, l' below 6" 272998 22.9 116.4 94.7 98
grade
Trench fill
4 480' from south end of electric line, final 6" 272998 23.7 116.3 94.0 97
Technician: Joe Jernigan
Report Distribution:
Orig: Duke Construction, LP (Dallas, TX) Altn: Mr. Paul Byrne
(1-ec copy)
1-cc City of Coppell Altn: Mr. Lee Stone
1-cc City of Coppell Altn: Mr. Larry Davis
Started: 12: 15pm Finished: 01 :45pm
Rone Engineering
p~~
K. Scott Watson, AET
Project Manager
LIMITATIONS: The test results presented herein were prepared based upon the specific samples provided for testing. We assume no responsibility for variation in quality
(composition, appearance, etc.) or any other feature of similar subject matter provided by persons or conditions over which we have no control. Our letters and reports are
for the exclusive use of the clients to whom they are addressed and shall not be reproduced except in full without the written approval of Rone Engineering Services, Ltd.
(LB/JB) Page 1 of 1
Rone Engineering
.
8908 Ambassador Row, Dallas, TX 75247
7701 W Little York, Ste 600, Houston, TX 77040
4421 Freidrich, Ste 195, Austin, TX 78744
Corporate Phone: (214) 630-9745
Client:
Duke Construction, LP
14241 Dallas Pkwy, Ste 1000
Dallas, TX 75254-2936
Report of Drilled Pier Inspection Cancellation
Report No.: 297881
Project No.: 0712932
Date of Service: 09/05/2007
Report Date: 09/14/2007
Project: Hemisphere's at Point West
Coppell, Texas
Services: Drilled Pier Inspection Cancellation
Report of Cancellation
On this date a Rone Engineering Services, Ltd. representative arrived on site as scheduled. Upon arrival, our
representative was informed that testing/inspection was cancelled for the day.
Technician: Chris Harbour Started: 05:45am
Report Distribution:
Orig: Duke Construction, LP (Dallas, TX) Attn: Mr. Paul Byrne
(1-ec copy)
1-cc City of Coppell Attn: Mr. Lee Stone
1-cc City of Coppell Attn: Mr. Larry Davis
Finished: 07:45am
Rone Engineering
P--~ ~
K. Scott Watson, AET
Project Manager
LIMITATIONS: The test results presented herein were prepared based upon the specific samples provided for testing. We assume no responsibility for variation in quality
(composition, appearance. etc.) or any other feature of similar subject matter provided by persons or conditions over which we have no control. Our letters and reports are
for the exclusive use of the clients to whom they are addressed and shall not be reproduced except in full without the written approval of Rone Engineering Services, Ltd.
(CH/JB) Page 1 of 1
Rone Engineering
.
8908 Ambassador Row, Dallas, TX 75247
7701 W Little York, Ste 600, Houston, TX 77040
4421 Freidrich, Ste 195, Austin, TX 78744
Corporate Phone: (214) 630-9745
Client:
Duke Construction, LP
14241 Dallas Pkwy, Ste 1000
Dallas, TX 75254-2936
Report of Drilled Pier Inspection
Report No.: 298032
Project No.: 0712932
Date of Service: 09/07/2007
Report Date: 09/14/2007
Project: Hemisphere's at Point West
Coppell, Texas
Services: Straight Shaft Pier Inspection
Report of Inspection
D ri lie r: A ug e r
Pier Identification K/20 J 120 J 119 K 121 J /21
PierDiameter(in) 24 24 24 24 24
Depth of Pier From Surface (ft) 43.30 43.60 43.50 43.00 43.40
Depth ofBearinq Stratum Fro m Surface(ft) 37.00 38.00 37.00 37.00 38.00
Required Penetration (ft) 5.00 5.00 5.00 5.00 5.00
Actual Penetration (ft)" 6.30 5.60 6.50 6.00 5.40
Condition of Bottom (wet/dry) Dry Dry D rv Dry Dry
Plumb Within Tolerance (yes Ino) Ye s Yes Yes Yes Yes
Casing Diameter (in) I C asinq Lenqth (ft) 26/36.9 26/38 26/37 26/37 26
NumberofBars IReinforcing BarSize 6 1#6 6 1#6 6 / #6 6 / # 6 6 1#6
Length of Reinforcing Steel (ft) 42.00 42.40 42.20 41.80 42.1 0
Time Drilling was Completed (am Ipm) 8:20 AM 8:55 AM 9 :40 A M 10:03AM 10:15 AM
Time Concrete was Placed (am Ipm) 9:05AM 1 0 :0 0 AM 10:35 AM 11:20AM 11:50AM
Depth of Pier From Top of Concrete (ft) 42.80 43.10 43.00 42.50 42.90
Elevation: Surface (ft)** 98.50 98.50 98.50 98.50 98.50
Elevation: Top of Pier (ft)"" 98.00 98.00 98.00 98.00 98.00
E Ie va Ii 0 n: B 0 Ito m 0 f Pie r (ft)"" 55.20 54.90 55.00 55.50 55.1 0
Elevation: Top ofBearinq Stratum (ft.)** 61 .50 60.50 61 .50 61 .50 60.50
Bearinq Stratum (d escriptio n) Blue shale
Note:See report# NA forCompressive StrengthTestSpecimens.
"Additional Penetration not requested unless noted. ""Elevation by others
LIMITATIONS: The test results presented herein were prepared based upon the specific samples provided for testing. We assume no responsibility for variation in quality
(composition, appearance, etc.) or any other feature of similar subject matter provided by persons or conditions over which we have no control. Our letters and reports are
for the exclusive use of the clients to whom they are addressed and shall not be reproduced except in full without the written approval of Rone Engineering Services, Ltd.
(CH/KW) Page 1 of 4
Rone Engineering
.
8908 Ambassador Row, Dallas, TX 75247
7701 W Little York, Ste 600, Houston, TX 77040
4421 Freidrich, Ste 195, Austin, TX 78744
Corporate Phone: (214) 630-9745
Client:
Duke Construction, LP
14241 Dallas Pkwy, Ste 1000
Dallas, TX 75254-2936
Report of Drilled Pier Inspection
Report No.: 298032
Project No.: 0712932
Date of Service: 09/07/2007
Report Date: 09/14/2007
Project: Hemisphere's at Point West
Coppell, Texas
Services: Straight Shaft Pier Inspection
D ri lie r: Auqer
Pie rid e ntifica tio n K 12 2 J 122 J 123 J 12 4 K/23
Pie r D i a mete r (i n) 24 24 24 24 24
Depth of Pier From Surface (ft) 43.00 43.50 42.00 42.10 '44.90
Deoth ofBearino Stratum Fro m Surface(ft) 37.20 37.00 36.80 36.50 37.50
Reauired Penetration (ft) 5.00 5.00 5.00 5.00 5.00
Actual Penetration (ft)' 5.80 6.50 5.20 5.60 7.40
Condition ofBotlom (wet/drv) D rv D rv D rv Dry D rv
Plumb Within Tolerance (ves Ino) Yes Ye s Yes Yes Yes
Casino Diameter(in)/Casino Lenoth (ft) 2 6 13 7 2 6/3 6 .9 26/36.8 26/36.9 2 6 13 7
NumberofBars IReinforcino BarSize 6 1#6 6 1#6 6 1#6 6 1#6 6 1#6
Lenoth of Reinforcino Steel (ft) 41 .80 42.30 41.70 40.80 43.70
Time Drillina was Completed (am Ipm) 1 0 :3 0 A M 1 1 :09 AM 11:36AM 12 :03 PM 1 :19 PM
Time Concrete was Placed (am 10m) 12:19 PM 1 2 :42 P M 1 :09 PM 1 :27 P M 1 :50 PM
Depth of Pier From Top of Concrete (ft) 42.50 43.00 41.50 41.60 44.40
Elevation: Surface (ft).. 98.50 98.50 98.50 98.50 98.50
Elevation: Too of Pier (ft).. 98.00 98.00 98.00 98.00 98.00
E Ie va ti 0 n: B 0 tlo m 0 f Pie r (ft) ** 55.50 55.00 56.50 56.40 53.60
E Ie va ti 0 n : Too ofBearino Stratum (ft.)** 61 .30 61 .50 61.70 62.00 61.00
Bearina Stratum (descriotion) Blue shale
Not e: See re port # NA for Com pres sive Strength Test S pecim ens.
* Additional Penetration not requested unless noted **E levalion by others
LIMITATIONS: The test results presented herein were prepared based upon the specific samples provided for testing. We assume no responsibility for variation in quality
(composition, appearance, etc.) or any other feature of similar subject matter provided by persons or conditions over which we have no control. Our letters and reports are
for the exclusive use of the clients to whom they are addressed and shall not be reproduced except in full without the written approval of Rone Engineering Services, Ltd.
(CH/KW) Page 2 of 4
Rone Engineering
.
8908 Ambassador Row, Dallas, TX 75247
7701 W Little York, Ste 600, Houston, TX 77040
4421 Freidrich, Ste 195, Austin, TX 78744
Corporate Phone: (214) 630-9745
Client:
Duke Construction, LP
14241 Dallas Pkwy, Ste 1000
Dallas, TX 75254-2936
Report of Drilled Pier Inspection
Report No.: 298032
Project No.:. 0712932
Date of Service: 09/07/2007
Report Date: 09/14/2007
Project: Hemisphere's at Point West
Cappell, Texas
Services: Straight Shaft Pier Inspection
D ri lie r: A ug e r
Pie rid e ntifica tio n K 124 K 12 5 J 12 5 J 12 6 K 126
PierDiameter(in) 24 24 24 24 24
Depth of Pier From Surface (ft) 43.40 42.70 43.70 42.70 43.20
Depth of Bearing Stratum Fro m S u rfa c e (ft) 37.30 37.20 36.80 37.30 37.40
R e qui re d Pen e tr a ti 0 n (ft) 5.00 5.00 5.00 5.00 5.00
Actual Penetration (ft)' 6.10 5.50 6.90 5.40 5.80
Condition of Bottom (wet/dry) Dry Dry Dry Dry Dry
Plumb Within Tolerance (yes Ino) Yes Yes Yes Yes Yes
Casing Diameter(in)/Casing Length (ft) 2 6 13 7 26/36.5 26/36.6 26/37 2 6 13 7 .1
NumberofBars IReinforcing BarSize 6 1 #6 6 1 #6 6 1 #6 6 1 #6 6 1 #6
Length of Reinforcing Steel (ft) 42.20 41.50 42.40 41.60 42.1 0
Time DrillinQ was Completed (am Ipm) 1 :38 PM 2 :05 PM 2:33 PM 3 :00 P M 3 :2 8 P M
Time Concrete was Placed (am Ipm) 2:10 PM 2 :40 P M 3 :0 5 P M 3 :4 5 P M 4:30 PM
Depth of Pier From Top of Concrete (ft) 42.90 42.20 43.20 42.20 42.70
E Ie va tio n: S urfa ce (ft)** 98.50 98.50 98.50 98.50 98.50
Elevation: Top of Pier (ft)" 9 8 .00 9 8.00 98.00 98.00 98.00
Elevation: Bottom of Pier (ft)" 5 5.10 55.80 54.80 55.80 55.30
Elevation: Top ofBearinQ Stratum (ft.)" 61 .20 61 .30 61 .70 61 .20 61 .10
Bearing Stratum (description) B lu e s h a Ie
No Ie: See re port # NA for Compressive Strength Test Specimens.
. Additional Penetration not requested unless noted. uE levation by others
LIMITATIONS: The test results presented herein were prepared based upon the specific samples provided for testing. We assume no responsibility for variation in quality
(composition, appearance, etc.) or any other feature of similar subject matter provided by persons or conditions over which we have no control. Our letters and reports are
for the exclusive use of the clients to whom they are addressed and shall not be reproduced except in full without the written approval of Rone Engineering Services, Ltd.
(CH/KW) Page 3 of 4
Rone Engineering
.
8908 Ambassador Row, Dallas, TX 75247
7701 W Little York, Ste 600, Houston, TX 77040
4421 Freidrich, Ste 195, Austin, TX 78744
Corporate Phone: (214) 630-9745
Client:
Duke Construction, LP
14241 Dallas Pkwy, Ste 1000
Dallas, TX 75254-2936
Report of Drilled Pier Inspection
Report No.: 298032
Project No.: 0712932
Date of Service: 09/07/2007
Report Date: 09/14/2007
Project: Hemisphere's at Point West
Coppell, Texas
Services: Straight Shaft Pier Inspection
o rille r: Auger
Pier Identification K 12 7
Pier Diameter (in) 24
De p th 0 f Pie r Fro m S u rfa c e (ft) 44.40
Depth of Bearing Stratum Fro m Surface(ft) 38.00
Required Penetration (ft) 5.00
A ctua 1 P e ne tra tio n (ft)' 6.40
Condition of Bottom (wet 1 d ry) Dry
Plumb Within Tolerance (yes Ino) Yes
Casing Diameter(in)/Casing LenQth (ft) 26/37.7
NumberofBars IReinforcing BarSize 6 1 #6
Length of Reinforcing Steel (ft) 43.20
Time Drilling was Completed (am 1 pm) 3:56 PM
Tim e Con c re te was P la c e d (a m 1 pm) 4:55 PM
Depth of Pier From Top of Concrete (ft) 43.90
Elevation: Surface (ft).. 98.50
E Ie va ti 0 n: Top 0 f Pie r (ft).. 98.00
Elevation: Bottom of Pier (ft)" 5 4 .10
Elevation: Top of BearlnQ Stratum (fl.)" 60.50
Bearing Stratum (description) Blue sha Ie
Not e: See re port # NA for Com pressive Strength T est S pee im ens.
. Additional Penetration not requested unless noted. HE levation by others
Technician: Chris Harbour Started: 05:45am
Report Distribution:
Orig: Duke Construction, LP (Dallas, TX) Attn: Mr. Paul Byrne
(1-ec copy)
1-cc City of Coppell Attn: Mr. Lee Stone
1-cc City of Coppell Attn: Mr. Larry Davis
Finished: 05:45pm Rone Engineering
P-~
~
K. Scott Watson, AET
Project Manager
LIMITATIONS: The test results presented herein were prepared based upon the specific samples provided for testing. We assume no responsibility for variation in quality
(composition, appearance, etc.) or any other feature of similar subject matter provided by persons or conditions over which we have no control. Our letters and reports are
for the exclusive use of the clients to whom they are addressed and shall not be reproduced except in full without the written approval of Rone Engineering Services, Ltd.
(CH/KW) Page 4 of 4
Rone Engineering
.
8908 Ambassador Row, Dallas, TX 75247
7701 W Little York, Ste 600, Houston, TX 77040
4421 Freidrich, Ste 195, Austin, TX 78744
Corporate Phone: (214) 630-9745
Client:
Duke Construction, LP
14241 Dallas Pkwy, Ste 1000
Dallas, T 4-2936
Report of Drilled Pier Inspection
Report No.: 298197
Project No.: 0712932
Date of Service: 09/08/2007
Report Date: 09/14/2007
Hemisphere's at Point W
Coppell, Texas
s: Strai ier Inspection
Report of Inspection
D '11
A
rJ e r: ug e r
Pie r Id e ntifica tio n K 12 8 K 12 9 J 127 J 12 8 J 129
Pier Diameter (in) 24 24 24 24 24
D e p th 0 f P ie r Fro m S u rfa c e (ft) 45.00 45.70 44.00 42.80 41.70
Depth of Bearing Stratum Fro m Surface(ft) 37.00 37.60 38.00 37.00 36.60
Required Penetration (ft) 5.00 5.00 5.00 5.00 5.00
Actual Penetration (ft)" 8.00 8.10 6.00 5.80 5.10
Condition of Bottom (wet/dry) Dry Dry Dry Dry Dry
Plumb Within Tolerance (yes Ino) Yes Yes Yes Yes Yes
Casing Diameter(in)/Casing Length (ft) 26/37 26/37.5 26/37 2 6 13 7 26/36.6
NumberofBars IReinforcing BarSize 6 1#6 6 1#6 6 1#6 6 1#6 6 1#6
Length of Reinforcing Steel (ft) 43.70 44.50 42.80 41.60 40.50
Time Drilling was Completed (am Ipm) 8:00 AM 8:30 AM 8 :50 AM 9 :3 0 A M 10:00 AM
Time Concrete was Placed (am Ipm) 9 :4 5 AM 10:30 AM 11:00AM 1 1 :27 A M 12:15 PM
Depth of Pier From Top of Concrete (ft) 44.50 45.20 43.50 42.30 41.20
Elevation: Surface (ft).. 98.50 98.50 98.50 98.50 98.50
E Ie va ti 0 n: Top 0 f Pie r (ft) ** 98.00 98.00 98.00 98.00 98.00
Elevation: Bottom of Pier (ft)"" 53.50 52.80 54.50 55.70 56.80
Elevation: Top of Bearing Stratum (ft.)** 61.50 60.90 60.50 61 .50 61.90
Bearing Stratum (description) Blue shale
Note:See report# NA forCompressive StrengthTestSpecimens.
"Additional Penetration not requested unless noted. "Elevation by others
!'lie
LIMITATIONS: The test results presented herein were prepared based upon the specific samples provided for testing. We assume no responsibility for variation in quality
(composition, appearance, etc.) or any other feature of similar subject matter provided by persons or conditions over which we have no control. Our letters and reports are
for the exclusive use of the clients to whom they are addressed and shall not be reproduced except in full without the written approval of Rone Engineering Services, Ltd.
(CH/KW) Page 1 of 3
Rone Engineering
.
8908 Ambassador Row, Dallas, TX 75247
7701 W Little York, Ste 600, Houston, TX 77040
4421 Freidrich, Ste 195, Austin, TX 78744
Corporate Phone: (214) 630-9745
Client:
Duke Construction, LP
14241 Dallas Pkwy, Ste 1000
Dallas, TX 75254-2936
Report of Drilled Pier Inspection
Report No.: 298197
Project No.: 0712932
Date of Service: 09/08/2007
Report Date: 09/14/2007
Project: Hemisphere's at Point West
Cappell, Texas
Services: Straight Shaft Pier Inspection
D rille r: Auger
Pie r Id e ntifica tio n C /22 B /22 C /2 3 B /23 B /2 4
PierDiameter(in) 24 24 24 24 24
Depth of Pier From Surface (ft) 43.40 43.00 43.1 0 42.90 43.20
Depth of Bearing Stratum Fro m S urfa ce (ft) 38.00 38.00 38.00 37.60 37.20
Required Penetration (ft) 5.00 5.00 5.00 5.00 5.00
A ctua I P e ne tra tio n (ft)* 5.40 5.00 5.1 0 5.30 6.00
Condition of Bottom (wet/dry) Dry Dry Dry Dry Dry
Plumb Within Tolerance (yes /no) Yes Ye s Yes Yes Yes
Casing D iam eter (in) / Casing Length (ft) 2 6 /3 8 26/38 26/38 26/37.6 26/37.2
N u m b e r 0 f Bar s / Rei n fo rei n g Bar S i z e 6 / # 6 6 / #6 6 / # 6 6 / # 6 6 / #6
Length of Reinforcing Steel (ft) 42.1 0 41 .80 42.00 41 .70 42.1 0
Tim e D ri IIi n g was Com pie te d (a m / pm) 10:36AM 1 0 :5 3 AM 11:14AM 1 1 : 3 1 AM 1 1 :50 A M
Time Concrete was Placed (am / pm) 1 2 :4 0 P M 1 :09 P M 1 :31 PM 1 :50 PM 2:13 PM
Depth of Pier From Top 0 f Con c re te (ft) 42.90 42.50 42.60 42.40 42.70
Elevation: Surface (ft).. 98.50 98.50 98.50 98.50 98.50
Elevation: Top of Pier (ft).. 98.00 98.00 98.00 98.00 98.00
Elevation: Bottom of Pier (ft).. 55.1 0 55.50 55.40 55.60 55.30
E Ie va tio n: Top of Bearing Stratum (ft.)" 60.50 60.50 60.50 60.90 61 .30
Bearing Stratum (d e scrip tio n) B lu e s h a Ie
Note: See report # NA to reo m pre s s ive S t re n 9 t h Test S pecim ens.
. Additional Penetration not requested unless noted HE levation by others
LIMITATIONS: The test results presented herein were prepared based upon the specific samples provided for testing. We assume no responsibility for variation in quality
(composition, appearance, etc.) or any other feature of similar subject matter provided by persons or conditions over which we have no control. Our letters and reports are
for the exclusive use of the clients to whom they are addressed and shall not be reproduced except in full without the written approval of Rone Engineering Services, Ltd.
(CHIKW) Page 2 of 3
Rone Engineering
.
8908 Ambassador Row, Dallas, TX 75247
7701 W Little York, Ste 600, Houston, TX 77040
4421 Freidrich, Ste 195, Austin, TX 78744
Corporate Phone: (214) 630-9745
Client:
Duke Construction, LP
14241 Dallas Pkwy, Ste 1000
Dallas, TX 75254-2936
Report of Drilled Pier Inspection
Report No.: 298197
Project No.: 0712932
Date of Service: 09/08/2007
Report Date: 09/14/2007
Project: Hemisphere's at Point West
Coppell, Texas
Services: Straight Shaft Pier Inspection
D rille r: M cK innev
Pier Identification C /24 B /2 5 C /25
PierDiameter(in) 24 24 24
D eo th 0 f Pie r Fro m S u rfa c e (ft) 43.70 44.00 44.40
Depth of Bearino Stratum Fro m S u rfa c e (ft) 38.00 38.00 38.50
R e quire d P e netra tio n (ft) 5.00 5.00 5.00
A ctua I P e ne tra tio n (ft)- 5.70 6.00 5.90
Condition of Bolt om (wet / dry) Dry Dry Dry
Plumb Within Tolerance (ves Ino) Yes Yes Yes
Casino Diameter(in)/Casino Lenoth (ft) 2 6 /3 8 2 6 /3 8 26/38 .1
NumberofBars /Reinforcing BarSize 6 / #6 6 / #6 6 / #6
Lenoth of Reinforcing Steel (ft) 42.50 42.80 43.30
Time Drillina was Completed (am /pm) 12:30 PM 1 2 :5 0 PM 1:18 PM
Tim e Con c re te was P la c e d (a m / pm) 2 :36 PM 3:00 P M 3 :20 P M
Depth of Pier From Top of Concrete (ft) 43.20 43.50 43.90
Elevation: Surface (ft)** 98.50 98.50 98.50
Elevation: Top of Pier (ft)** 98.00 98.00 98.00
Elevation: Bottom of Pier (ft)-- 54.80 54.50 54.1 0
Elevation: Top of Bear in a Stratum (ft.) ** 60.50 60.50 60.00
Bearina Stratum (d e scrip tio n) B lu e s h a Ie
Not e: See re port # NA for Compressive Strength Test Specimens.
. Additional Penetration not requested unless noted HE levation by others
Technician: Chris Harbour Started: 05:45am
Report Distribution:
Orig: Duke Construction, LP (Dallas, TX) AUn: Mr. Paul Byrne
(1-ec copy)
1-cc City of Coppell AUn: Mr. Lee Stone
1-cc City of Coppell AUn: Mr. Larry Davis
Finished: 03:45pm Rone Engineering
p~
~
K. Scott Watson, AET
Project Manager
LIMITATIONS: The test results presented herein were prepared based upon the specific samples provided for testing. We assume no responsibility for variation in quality
(composition, appearance, etc.) or any other feature of similar subject matter provided by persons or conditions over which we have no control. Our letters and reports are
for the exclusive use of the clients to whom they are addressed and shall not be reproduced except in full without the written approval of Rone Engineering Services, Ltd.
(CH/KW) Page 3 of 3