CITY OF COPPELL
CHANGE OR EXTRA WORK ORDER
~@~)f.
PROJECT: Bethel Road I Project # ST 99-05
CONTRACTOR: Tiseo Paving Company
OWNER: City of Coppell
CHANGE ORDER NO.:
Four (4)
DATE:
September 21, 2007
Item Description
Quantity Unit
Unit
Price
Total
1.
2.
3.
4.
Changes to Storm Drain Line D:
Additional Staking
Connect RCP to Box Culvert
Restocking Fee for unused RCP
Remove Existing 16" Valve
Total Revision to Contract Amount
4 EA 250.00 $1,000.00
4 EA 800.00 $3,200.00
1 LS 6,072.00 $6,072.00
1 LS 3,975.00 $3,975.00
$14,247.00
$7,293,659.00
0
$8,000.00
$8,580.00
$14,247.00
$7,324,486.00
0
573 Calendar Days
ADD:
Previous contract amount
Net increase in contract amount Change Order #1
Net increase in contract amount Change Order #2
Net increase in contract amount Change Order #3
Net increase in contract amount Change Order #4
Revised contract amount
Net increase in contract time of completion
Revised Contract time of completion
The contractor hereby accepts this Contract adjustment as a final and complete adjustment in full
accord and satisfaction of all past and future liability originating under any clause in the Contract
by rea:t:his:pSi;~ to the con:.c: I.,
Recorrubended ~y ~eer Date
~~~..
Agreed to by Contra'G:tor
./ "':>>
..~/./
9 - :2 7 -07
Date
.~...~. .....,...-
/.:; . r
/ j);
/ v .
~
/'
Accef)ted by E:ity
Date
.
PAVING COMPANY
P.O. Box 270040 Dallas. Texas 75227-0040
Telephone (972) 289-0723 Fax (972) 216-5637
September 17, 2007
City of Coppell
255 Parkway
Coppell, Texas 78019
Attn: Keith Marvin, P.E.
Re: Bethel Road ST 99-05
Remove Existing 16" Valve
Mr. Marvin,
Please review the following cost to remove an existing valve. The installation of the new
valve can be paid for under existing pay item 1-83-CA 16" Gate Valve. Dewatering,
removing the existing, and installing sleeves are included in the cost below.
Remove Existing 16" Valve - 1.0 LS @ 3,975.00
If you have any questions please call me at 972-289-0723
Sincerely,
~ _/'~.
Lance Smith
Project Administrator
&~ /974
.
PAVING COMPANY
PO. Box 270040 Dallas, Texas 75227-0040
Telephone (972) 289-0723 Fax (972) 216-5637
September 14,2007
City of Coppell
255 Parkway
Coppell, Texas 78019
Attn: Keith Marvin, P.E.
Re: Bethel Road ST 99-05
Changes to Line "D"
f\k Marvin,
Please review the following costs due to changes with Storm Drain Line "D". We
request payment for additional staking and pipe to box connections required with these
changes, there will also be a restocking fee due Johnson County Pipe for the RCP already
on site
Additional Staking
Connect RCP to Box Culvert
Restocking Fee for Unused RCP
4.0 EA @ 250.00 = 1,000.00
4.0 EA @ 800.00 = 3,200.00
1.0 LS @ 6,072.00 = 6,072.00
If you have any questions please call me at 972-289-0723
Sincerely,
;t~0 -d~~:1
Lance Smith
Project Administrator