ST9905-CS071009
CITY OF COPPELL
CHANGE OR EXTRA WORK ORDER
PROJECT: Bethel Road I Project # ST 99-05
CONTRACTOR: Tiseo Paving Company
OWNER: City of Coppell
CHANGE ORDER NO.: Five (5) DATE: October 9,2007 Page 10f2
Item Description Quantity Unit Unit Price Total
Minyard's Development:
ADD: Water Line @ Sta 50+06.5
1. Additional Traffic Control 1 LS 750.00 $750.00
2. Additional Staking 1 LS 250.00 $250.00
3. 16" x 8" Tapping Sleeve & Valve 1 EA 3,850.00 $3,850.00
4. Aspha1t/F1exbase Street Repair 1 LS 1,500.00 $1,500.00
5. Bore w / Casing Under Existing 25 LF 230.00 $5,750.00
Street
6. Bore w/o Casing Under Existing 12 LF 115.00 $1,380.00
Box
7. Two 450 Bends & Plug 1 LS 1,750.00 $1,750.00
8. 8" PVC 97 LF 55.25 $5,359.25
9. Testing 1 LS 700.00 $700.00
Sewer Line @ Sta 50+ 18.85
10. Additional Traffic Control 1 LS 750.00 $750.00
11. Additional Staking 1 LS 250.00 $250.00
12. Steel Plate & MH Safety Ring 1 LS 2,200.00 $2,200.00
13. Asphalt/F1exbase Street Repair 1 LS 2,500.00 $2,500.00
14. Bore w/o Casing under Box 12 LF 115.00 $1,380.00
15. 8" Plug 1 EA 200.00 $200.00
16. Testing 1 LS 700.00 $700.00
17. 8" PVC Sewer Line 65 LF 63.75 $4,143.75
18. 4-ft Diameter Manhole 1 EA 4,200.00 $4,200.00
Median Openings
19. 9" Concrete Pavement
357 SY 29.00 $10,353.00
7.5 TON 105.00 $787.50
357 SY 2.95 $1,053.15
2 EA 1,200.00 $2,400.00
67 SY 83.00 $5,561.00
$57,767.65
$7,293,659.00
0
$8,000.00
$8,580.00
$14,247.00
$57,767.65
$7,382,253.65
0
573 Calendar Days
20. Lime @ 42 lbs/SY
21. 8" Stabilized Subgrade
22. Median Noses
23. Stamped Concrete
Total Revision to Contract Amount
Previous contract amount
Net increase in contract amount Change Order #1
Net increase in contract amount Change Order #2
Net increase in contract amount Change Order #3
Net increase in contract amount Change Order #4
Net increase in contract amount Change Order #5
Revised contract amount
Net increase in contract time of completion
Revised Contract time of completion
The contractor hereby accepts this Contract adjustment as a final and complete adjustment in full
accord and satisfaction of all past and future liability originating under any clause in the Contract
by reason of this revision to the Contract.
rI...u-. ,-f)JJ .0 .9.7
RWt~ nde~ b~Engineer Date
g~/~cJ
Date
Ac
Page 2 Of2