Loading...
DR9001-CS 900115COPPELL PUBLIC WORKS DATE: TO: FROM: RE: January 15, 1990 Steve Goram, Director of Public Works Russell R. Doy~ity Engineer i1~~.' Connell/SkaggsUDrainage Contract between Skyhawk Venture and the City of Coppell / Follow Up to the Monday, January 12, 1990 meeting between Mark Connell, His Engineer and City Staff As you requested, attached is a summary of alternatives regarding subject contract. We have committed to Mark Connell to respond to him within five working days. Attached is the only documentation (found in the City Secretary's files) about the participation in the funding of the construction of the Sandy Lake and Denton Tap Roads intersection. There was no contract, per se, available. It appears Connell Development Company could claim a credit of $50,000 (if the transaction took place (and I understand it did)), from any assessment during the construction of Sandy Lake Road west of Denton Tap Road. We would probably need to have another in house meeting before meeting again with Connell depending how you want this handled. Please let me know if you need anything else on this matter. you. MRKCONEL.RRD · ~ { Thank CONNELL/SKAGGS - SKYHAWK VENTURE Request For Revision of the Agreement with The City of Coppell regarding Drainage Improvements from Sandy Lake Road to New High School Culvert Alternatives Mark Connell's Request is to allow only partial improvements at this time due to added costs to him due to trench safety laws. That is: Permit Connell to Build 2- 12' x 4' box culverts along Connell/Skaggs tract only. Temporary channel connecting the 2- 12' x 4' box culvert and the High school's 10 x 8 box culvert. (This channel does not provide sufficient design capacity.) 3. Waive any reimbursement. 4. Upon completion of items 1 & 2, then no other obligations regarding said agreement. Comments A 10 x 8 or 2- 12 x 4 box culverts will still be necessary to be constructed for 668 linear feet along the Boorhem/Hinckley Properties with possibly tWO (2) transition structures (estimated costs over 1/4 million dollars) Connell's length is only 556 if (46%) and per his estimate (attached) will cost (est) $379,000. 2. Connell agreed (1/12/90) to continue to hold City harmless. 3. Screening wall has to be added in. Connell's Engineering Report referred to in the file, needs to be furnished to the city; is not on file and he has not yet furnished another copy (as requested by the City Engineer). 5. Lined ditch was estimated to cost $80,000, making Connell's total cost to be estimated at $460,000. 6. Hinckley probably won't give easements. City participate in rest of needed funding/$300,O00? with Connell or waive street assessment (estimated to be $300,000 with a possible $50,000 credit). Original agreement with Connell had Connell providing the funding irrespective of total costs. City take $345,000, do some minor improvements to protect property along Shady Dale Lane and hold remaining finds for when property develops and/or other funding becomes available. Problems for Each Alternative Less than design capacity; Connell out of indemnity~hold harmless to City, possible damage to Shady Dale property and others including Denton Tap roadway. B. Costs City now and interest in future. No problems if Connell performs. Less than, design capacity, Connell out of indemnity~hold harmless to city, possible damage to Shady Dale property and others including Denton Tap roadway. It~rn Description Unit Qty J-NO:nstr. Cb., Inc. lqebom, Inc. P.O. Box 530 11181 Horry Hines 1113 ISml~hire Jane Suite 139 Richordson, ~1X75680 l~ll~s, ~X75229 Ff~P ND.3354-88-3-2 ~g 10, 1988 Bud<el~v P.O. Box1894 Richardson, TR75080 Unit Unit Unit Price A~t Price Am~t Price Armmt Box Culvert and hppurtenonces IF 1232 Upstream Transi t ica IS 1 Trmch Safety IF 1232 $353.13 435,056.16 324.68 400,000.00 319.00 393,008.00 $41,000.00 41,000.00 65,000.00 65,000.00 42,049.00 42,049.00 $183.00 225,456.00 231.16 284,789.12 468.47 577,155.04 $701,512.16 $749,789.12 $1,012,212.04 4 Trench Safety Program (Dctble Sheet Piles) Alternate Trench Safety Progrgns So~mitted for P~ie~v *Yertical Wide Flon~m BUm~ with Tin~er Lagging. **Factory Built, CSH~ ~A~)roved Trenc~ ~ $165.00 ~130.00 500.00 *280.32 3354a/0421