Bethel BP-CS071106 Page 1 of 1 Rhonda Adloo - Creekview / Bethel Road From: Ken Griffin To: Matt Goodwin Date: 11/6/2007 9:30 AM Subject: Creekview / Bethel Road CC: Keith Marvin; Rhonda Adloo Matt Here's the cost breakdown for the Development Agreement that was approved by Council: Total cost of Change Order to Tieso - $270,088.40 Total cost of two median openings - $49,733.75 Total cost of Creekview to be paid by the City and the Developer - $220,354.65 (270,088.40 - 49,733.75 == 220,354.65) Developer responsibility - $110,177.33 (220,354.65/2 == 110,177.33) Credit to developer for installation of water line in Creekview - 18,214.00 Total due from developer - $91,963.33 (110,177.33 - 18,214 == $91,963.33) Hope this helps. Ken Griffin file://C:\Documents and Settings\rbrother\Local Settings\Temp\XPgrpwise\47303420City _... 1/11/2008