Matt
Here's the cost breakdown for the Development Agreement that was approved by Council:
Total cost of Change Order to Tieso - $270,088.40
Total cost of two median openings - $49,733.75
Total cost of Creekview to be paid by the City and the Developer - $220,354.65 (270,088.40 -
49,733.75 == 220,354.65)
Developer responsibility - $110,177.33 (220,354.65/2 == 110,177.33)
Credit to developer for installation of water line in Creekview - 18,214.00
Total due from developer - $91,963.33 (110,177.33 - 18,214 == $91,963.33)