Report of Concrete Compressive Strength Test
Report No.: 295024
Project No.: 0612510
Date of Service: 08/09/2007
Report Date: 09/11/2007
Project: Lesley Infrastructure
Services: Obtain samples of fresh concrete at the placement locations, perform required testing, cast compressive strength samples and bring
samples back to the laboratory for curing and testing in accordance with applicable standards.
PROJECT DATA
Contractor:
Concrete Supplier: Lacy
Plant: On site
Specification Requirements
Strf'ngth: 3,600 psi @ 28 days
Slump (in.): 4" maximum
Air (%): 3% - 6%
Test Method: ASTM C-172
ASTM C-31 (except 10,1.2)
ASTM C-143
ASTM C-231
ASTM C-1064
ASTM C-138
ASTM C-39
Mix Design I.D.: 5194
Placement Date: 08/09/2007
Weather Conditions: Clear
Time Sampled: 07:15am
Temperature - Air: 790F
Truck No: NA
Air Content: 3.8%
Overall Placement Location:
Paving for Dividend Street, Station 0+00 to 19+00, eastbound lane
Measured
Slump
(inches)
1.0
Batch time: 07:05am
Concrete: .l60F
Ticket No: NA
Unit Weight (pet): NA
Sample Location:
Station 1 +25
REPORT OF TESTS
Concrete Compressive Cylinder 6" x 12"
Cylinder Maximum Compressive
Marked Date Age Diameter Area Load Strength Fracture
Set No. Tested (days) (in) (in') (Ibs) (psi) Type
1 1 08/16/2007 7 6.00 28,27 83,610 2,960 Unbonded Cap
1 2 09/06/2007 28 6.00 28.27 104,930 3,710 Shear
1 3 09/06/2007 28 6.00 28.27 102,360 3,620 Cone/Split
Average 3,670
1 4 08/14/2007 5 6.00 28.27 75,950 2,690 Unbonded Cap
LIMITATIONS: The test results presented herein were prepared based upon the specific samples provided for testing. We assume no responsibility for variation in quality
(compositIon, appearance, etc.) or any other feature of similar subject matter provided by persons or conditions over whIch we have no control. Our letters and reports are
for the exclusive use of the clients to whom they are addressed and shall not be reproduced except In full without the written approval of Rone Engineering Services. Ltd.
(LBILB) Page 1 of 9
Rone Engineering
fIJ
8908 Ambassador Row, Dallas, TX 75247
7701 W Little York, Ste 600, Houston, TX 77040
4421 Freldrlch, Ste 195, Austin, TX 78744
Corporate Phone: (214) 630-9745
Client: Duke Construction, LP
14241 Dallas Pkwy, Ste 1000
Dallas, TX 75254-2936
Report of Concrete Compressive Strength Test
Report No.: 295024
Project No.: 0612510
Date of Service: 08/09/2007
Report Date: 09/11/2007
Project: Lesley Infrastructure
Services: Obtain samples of fresh concrete at the placement locations, perform required testing, cast compressive strength samples and bring
samples back to the laboratory for curing and testing in accordance with applicable standards.
PROJECT DATA
Contractor:
Concrete Supplier: Lacy
Plant: On site
Specification Requirements
Strength: 3,601 psi @ 28 days
Slump (in.): 4" maximum
Air (%): 3% - 6%
Test Method: ASTM C-172
ASTM C-31 (except 10.1.2)
ASTM C-143
ASTM C-231
ASTM C-1064
ASTM C-138
ASTM C-39
Mix Design 1.0.: 5194
Placement Date: 08109/2007
Weather Conditions: Clear
Time Sampled: 08:10am
TemperatLire - Air: 840F
Truck No: NA
Air Content: 3.6%
Overall Placement Location:
Paving for Dividend Street, Station 0+00 to 19+00, eastbound lane
Batch time: 08:00am
Concrete: 800F
Ticket No: NA
Unit Weight (pet): NA
Measured
Slump
(inches)
0.75
Sample Location:
Station 2+50
REPORT OF TESTS
Concrete Compressive Cylinder 6" x 12"
Cylinder Maximum Compressive
Marked Date 'Age Diameter Area Load Strength Fracture
Set No. Tested (days) (in) (in") (Ibs) (psi) Type
2 1 08/16/2007 7 6.00 28.27 88,620 3,130 Unbonded Cap
2 2 09/06/2007 28 6.00 28.27 109,910 3,890 Shear
2 3 09/06/2007 28 6.00 28.27 112.460 3,980 Cone/Shear
Average 3,930
2 4 08/14/2007 5 6.00 28.27 84,020 2,970 Unbonded Cap
LIMITATIONS: The test results presented herein were prepared based upon the specific samples provided for testing. We assume no responsibility for variation In quality
(composition, appearance, etc.) or any other feature of similar subject matter provided by persons or conditions over which we have no control. Our letters and reports are
for the exclusive use of the clients to whom they are addressed and shall not be reproduced except in full without the written approval of Rone Engineering Services, Ltd.
(LBILB) Page 2 of 9
Rone Engineering
.
Client: Duke Construction, LP
14241 Dallas Pkwy, Ste 1000
Dallas, TX 75254-2936
8908 Ambassador Row, Dallas, TX 75247
7701 W Little York, Ste 600, Houston, TX 77040
4421 Freldrich, Ste 195, Austin, TX 78744
Corporate Phone: (214) 630-9745
Report of Concrete Compressive Strength Test
Report No.: 295024
Project No.: 0612510
Date of Service: 08/09/2007
Report Date: 09/11/2007
Project: Lesley Infrastructure
Services: Obtain samples offresh concrete at the placement locations, perform required testing, cast compressive strength samples and bring
samples back to the laboratory for curing and testing in accordance with applicable standards.
PROJECT DATA
Contractor:
Concrete Supplier: Lacy
Plant: On site
Specification Requirements
Strength: 3,600 psi @ 28 days
Slump (in.): 4" maximum
Air (%): 3% - 6%
Test Method: ASTM C-172
ASTM C-31 (except 10.1.2)
ASTM C-143
ASTM C-231
. ASTM C-1064
ASTM C-138
ASTM C-39
Mix Design I.D.: 5194
Placement Date: 08/09/2007
Weather Conditions: Clear
Time Sampled: 08:45am
Temperature - Air: 850F
Truck No: NA
Air Content: 3.2%
Overall Placement Location:
Paving for Dividend Street, Station 0+00 to 19+00, eastbound lane
Measured
Slump
(inches)
0.25
Batch time: 08:40am
Concrete: 840F
Ticket No: NA
Unit Weight (pcf): NA
Sample Location:
Station 3+75
REPORT OF TESTS
Concrete Compressive Cylinder 6" x 12"
Cylinder Maximum Compressive
Marked Date Age Diameter Area Load Strength Fracture
Set No. Tested (days) (in) (In2) (Ibs) (psi) Type
3 1 08/16/2007 7 6.00 28.27 90,760 3,210 Unbonded Cap
3 2 09/06/2007 28 6.00 28.27 126,150 4,460 Cone/Split
3 3 09/06/2007 28 6.00 28.27 110,010 3,890 Cone/Split
Average 4,180
3 4 08/14/2007 5 6.00 28.27 81,080 2,870 Unbonded Cap
L1MffA T10NS: The test results presented herein were prepared based upon the specific samples provided for testing. We assume no responsJblllty for varlallon in quality
(oomposlUon, appearance, etc.) or any other feature of similar subject matter provided by persons or conditions over which we have no control. Our letters and reports are
for the exclusive use of the clients to whom they are addressed and shall not be reproduced except in full wUhoutthe written approval of Rone Engineering Services, Ltd.
(LB/LB) Page 3 of 9
Rone Engineering
..
Client: Duke Construction, LP
14241 Dallas Pkwy, Ste 1000
Dallas, TX 75254-2936
8908 Ambassador Row, Dallas, TX 75247
7701 W Little York, Ste 600, Houston, TX 77040
4421 Freldrlch, Ste 195, Austin, TX 78744
Corporate Phone: (214) 630-9745
Report of Concrete Compressive Strength Test
Report No.: 295024
Project No.: 0612510
Date of Service: 08/09/2007
Report Date: 09/11/2007
Project: Lesley Infrastructure
Services: Obtain samples offresh concrete at the placement locations, perfonn required testing, cast compressive strength samples and bring
samples back to the laboratory for curing and testing in accordance with applicable standards.
Contractor:
Concrete Supplier: Lacy
Plant: On site
Specification Requirements
Strength: 3,600 psi @28 days
Slump (in.): 4" maximum
Air (%): 3% - 6%
Test Method: ASTM C-172
ASTM C-31 (except 10.1.2)
ASTM C-143
ASTM C-231
ASTM C-1064
ASTM C-138
ASTM C-39
PROJECT DATA
Mix Design 1.0.: 5194
Placement Date: 08/09/2007
Weather Conditions: Clear
Time Sampled: 09:15am
Tempr'rature - Air: 880F
Truck No: NA
Air Content: 3.5%
Overall Placement Location:
Paving for Dividend Street, Station 0+00 to 19+00, eastbound lane
Measured
Slump
(inches)
0.75
Batch time: 09: 1 Oam
Concrete: 870F
Ticket No: NA
Unit Weight (pet): NA
Sample Location:
Station 5+80
REPORT OF TESTS
Concrete Compressive Cylinder 6" x 12"
Cylinder Maximum Compressive
Marked Date Age Diameter Area Load Strength Fracture
Set No. Tested (days) (in) (inO) (Ibs) (psi) Type
4 1 08/16/2007 7 6.00 28.27 102,510 3,630 Unbonded Cap
4 2 09/06/2007 28 6.00 28.27 122,190 4,320 Cone/Shear
4 3 09/06/2007 28 6.00 28.27 124,850 4,420 Cone/Split
Average 4,370
4 4 08/14/2007 5 6.00 28.27 88,340 3,120 Unbonded Cap
LIMITATIONS: The test results presented herein were prepared based upon the specific samples provided for testing. We assume no responsibility for variation in quality
(composlUon, appearance, etc.) or any other feature of similar subject matter provided by persons or conditions over which we have no control. Our letters and reporls are
for the exclusive use of the clients to whom they are addressed and shall not be reproduced except in full without the written approval of Rone Engineering Services, Ltd.
(LBlLB) Page 4 of 9
Rone Eng.ineering
.
Client: Duke Construction, LP
14241 Dallas Pkwy, Ste 1000
Dallas, TX 75254-2936
8908 Ambassador Row, Dallas, TX 75247
7701 W L1We York, Ste 600, Houston, TX 77040
4421 Freldrlch, Ste 195, Austin, TX 78744
Corporate Phone: (214) 630-9745
Report of Concrete Compressive Strength Test
Report No.: 295024
Project No.: 0612510
Date of Service: 08/09/2007
Report Date: 09/11/2007
Project: Lesley Infrastructure
Services: Obtain samples of fresh concrete at the placement locations, perform required testing, cast compressive strength samples and bring
samples back to the laboratory for curing and testing in accordance with applicable standards.
PROJECT DATA
Contractor:
Concrete Supplier: Lacy
Plant: On site
Specification Requirements
Strength: 3,600 psi @ 28 days
Slump (in.): 4" maximum
Air (%): 3% - 6%
Test Method: ASTM C-172
ASTM C-31 (except 10.1.2)
ASTM C-143
ASTM C-231
ASTM C-1064
ASTM C-138
ASTM C-39
Mix Design I.D.: 5194
Placement Date: 08/09/2007
Weather Conditions: Clear
Time Sampled: 1 0:45am
Temperature - Air: 8f'oF
Truck No: NA
Air Content: 3.8%
Overall Placement Location:
Paving for Dividend Street, Station 0+00 to 19+00, eastbound lane
Measured
Slump
(inches)
0.75
Batch time: 1 0:40am
Concrete: 920F
Ticket No: NA
Unit Weight (pcf): NA
Sample Location:
Station 9+00
REPORT OF TESTS
Concrete Compressive Cylinder 6" x 12"
Cylinder Maximum Compressive
Marked Date Age Diameter Area Load Strength Fracture
Set No. Tested (days) (in) (In2) (Ibs) (psi) Type
5 1 08/16/2007 7 6.00 28.27 87,900 3,110 Unbonded Cap
5 2 09/06/2007 28 6.00 28.27 110,130 3,900 Cone/Split
5 3 09/06/2007 28 6.00 28.27 102,460 3,620 Cone/Shear
Average 3,760
5 4 08/14/2007 5 6.00 28.27 80,630 2,850 Unbonded Cap
UMITATIONS: The test results presented herein were prepared based upon the specific samples provided for testing. We assume no responsibility for variaUon In quality
(eomposIUon, appearance, etc.) or any other feature of similar subject matter provided by persons or condiUons over which we have no control. Our letters and reports are
for the exclusive use of the enents to whom they are addressed and shall not be reproduced except In full without the written approval of Rane Engineering Services, Ltd.
(LB/LB) Page 5 of 9
Rone Engineering
..
Client: Duke Construction, LP
14241 Dallas Pkwy, Ste 1000
Dallas, TX 75254-2936
8908 Ambassador Row, Dallas, TX 76247
7701 W Little York, Ste 600, Houston, TX 77040
4421 Freldrlch, Ste 195, Austin, TX 78744
Corporate Phone: (214) 630-9745
Report of Concrete Compressive Strength Test
Report No.: 295024
Project No.: 0612510
Date of Service: 08/09/2007
Report Date: 09/11/2007
Project: Lesley Infrastructure
Services: Obtain samples of fresh concrete at the placement locations, perform required testing, cast compressive strength samples and bring
samples back to the laboratory for curing and testing in accordance with applicable standards.
Contractor:
Concrete Supplier: Lacy
Plant: On site
Specification Requirements
Strength: 3,600 psi @ 28 days
Slump (in.): 4" maximum
Air (%): 3% - 6%
Test Method: ASTM C-172
ASTM C-31 (except 10.1.2)
ASTM C-143
ASTM C-231
ASTM C-1064
ASTM C-138
ASTM C-39
PROJECT DATA
Mix Design I.D.: 5194
Placement Date: 08/09/2007
Weather Conditions: Clear
Time Sampled: 12:00pm
Temperature - Air: 930F
Truck No: NA
Air Content: 4.3%
Overall Placement Location:
Paving for Dividend Street, Station 0+00 to 19+00, eastbound lane
Measured
Slump
(inches)
1.0
Batch time: 11 :50am
Concre ':e: 950F
Ticket No: NA
Unit Weight (pcf): NA
Sample Location:
Station 11 +85
REPORT OF TESTS
Concrete Compressive Cylinder 6" x 12"
Cylinder Maximum Compressive
Marked Date Age Diameter Area Load Strength Fracture
Set No. Tested (days) (in) (lnl) (Ibs) (psi) Type
6 1 08/16/2007 7 6.00 28.27 82,370 2,910 Unbonded Cap
6 2 09/06/2007 28 6.00 28.27 99,500 3,520 Cone/Split
6 3 09/06/2007 28 6.00 28.27 104,410 3,690 Cone/Shear
Average 3,610
6 4 08/14/2007 5 6.00 28.27 80,320 2,840 Unbonded Cap
LIMITATIONS: The test results presented herein were prepared based upon the specific samples provided for tesllng. We assume no responsibility for variation in quality
(composillon, appearance, etc.) or any other feature of similar subject matter provided by persons or conditions over which we have no control. Our letters and reports are
for the exclusive use of the clients to whom they are addressed and shall not be reproduced except In full without the written approval of Rone Engineering Services, Ltd.
(LB/LB) Page 6 of 9
Rone Engineering
.
Client: Duke Construction, LP
14241 Dallas Pkwy, Ste 1000
Dallas, TX 75254-2936
8908 Ambassador Row, Dallas, TX 75247
7701 W Little York, Ste 600, Houston, TX 77040
4421 Freldrlch, Ste 195, Austin, TX 78744
Corporate Phone: (214) 630-9745
Report of Concrete Compressive Strength Test
Report No.: 295024
Project No.: 0612510
Date of Service: 08/09/2007
Report Date: 09/11/2007
Project: Lesley Infrastructure
Services: Obtain samples of fresh concrete at the placement locations, perform required testing, cast compressive strength samples and bring
samples back to the laboratory for curing and testing in accordance with applicable standards.
PROJECT DATA
Contractor:
Concrete Supplier: Lacy
Plant: On site
Specification Requirements
Strength~ 3,600 psi @ 28 days
Slump (in.): 4" maximum
Air (%): 3% - 6%
Test Method: ASTM C-172
ASTM C-31 (except 10.1.2)
ASTM C-143
ASTM C-231
ASTM C-1064
ASTM C-138
ASTM C-39
Mix Design 1.0.: 5194
Placement Date: 08/09/2007
Weather Conditions: Clear
Time Sampled: 12:50pm
Temperature - Air: 930F
Truck No: NA
Air Content: 4.7%
Overall Placement Location:
Paving for Dividend Street, Station 0+00 to 19+00, eastbound lane
Measured
Slump
(inches)
1.25
Batch time: 12:40pm
Concrete: 940F
Ticket No: NA
Unit Weight (pet): NA
Sample Location:
Station 13+50
REPORT OF TESTS
Concrete Compressive Cylinder 6" x 12"
Cylinder Maximum Compressive
Marked Date Age Diameter Area Load Strength Fracture
Set No. Tested (days) (In) (in') (Ibs) (psi) Type
7 1 08/1612007 7 6.00 28.27 55,510 1,960 Unbonded Cap
7 2 09/06/2007 28 6.00 28.27 81,450 2,880 Cone/Split
7 3 09/06/2007 28 6.00 28.27 85,680 3,030 Cone/Split
Average 2,960 *
7 4 08/14/2007 5 6.00 28.27 59,240 2,100 nUnbonded Cap
* Does not comply with specified strength
L1MITA TlONS: The test results presented herein were prepared based upon the specific samples provided for testing. We assume no responsibility for varlatJon In quality
(composiUon, appearance, etc.) or any other feature of similar subject matter provided by persons or conditions over which we have no control. Our letters and reports are
for the exclusive use of the clients to whom they are addressed and shall not be reproduced except in full without the written approval of Rone engineering Services, ltd.
(LB/LB) Page 7 of 9
Rone Engineering
"
Client: Duke Construction, LP
14241 Dallas Pkwy, Ste 1000
Dallas, TX 75254-2936
8908 Ambassador Row, Dallas, TX 75247
7701 W L1We York, Ste 600, Houston, TX 77040
4421 Freldrlch, 8te 195, Austin, TX 78744
Corporate Phone: (214) 630-9745
Report of Concrete Compressive Strength Test
Report No.: 295024
Project No.: 0612510
Date of Service: 08/09/2007
Report Date: 09/11/2007
Project: Lesley Infrastructure
Services: Obtain samples of fresh concrete at the placement locations, perform required testing, cast compressive strength samples and bring
samples back to the laboratory for curing and testing in accordance with applicable standards.
Contractor:
Concrete Supplier: Lacy
Plant: On site
Specification Requirements
Strength: 3,600 psi @ 28 days
Slump (in.): 4" maximum
Air (%): 3% - 6%
Test Method: ASTM C-172
ASTM C-31 (except 10.1.2)
ASTM C-143
ASTM C-231
ASTM C-1064
ASTM C-138
ASTM C-39
PROJECT DATA
Mix Design 1.0.: 5194
Placement Date: 08/09/2007
Weather Conditions: Clear
Time Sampled: 01 :40pm
Temperature - Air: 960F
Truck No: NA
Air Content: 4.2%
Overall Placement Location:
Paving for Dividend Street, Station 0+00 to 19+00, eastbound lane
Measured
Slump
(inches)
1.0
Batch time: 01 :35pm
Concrete: 960F
Ticket No: NA
Unit Weight (pet): NA
Sample Location:
Station 15+25
REPORT OF TESTS
Concrete Compressive Cylinder 6" x 12"
Cylinder Maximum Compressive
Marked Date Age Diameter Area Load Strength Fracture
Set No. Tested (days) (in) (in') (Ibs) (psi) Type
8 1 08/16/2007 7 6.00 28.27 76,380 2,700 Unbonded Cap
8 2 09/06/2007 28 6.00 28.27 94,400 3,340 Cone/Split
8 3 09/06/2007 28 6.00 28.27 95,880 3,390 Shear
Average 3,360 ..
8 4 08/14/2007 5 6.00 28.27 73,520 2,600 Unbonded Cap
.. Does not comply with specified strength
LIMITATIONS: The test results presented herein were prepared based upon the specific samples provided for tesllng. We assume no responsibility for variation In quality
(oomposillon, appearance, etc.) or any other feature of similar subject matter provided by persons or conditions over which we have no control. Our letters and reports are
for the exclusive use of the clients to whom they are addressed and shall not be reproduced except in full without the written approval of Rone Engineering Services, Ltd.
(LB/LB) Page 8 of 9
Rone Engineering
..
Client: Duke Construction, LP
14241 Dallas Pkwy, Ste 1000
Dallas, TX 75254-2936
8908 Ambassador Row, Dallas, TX 75247
7701 W Little York, Ste 600, Houston, TX 77040
4421 Freldrlch, Ste 195, Austin, TX 78744
Corporate Phone: (214) 630.9745
Report of Concrete Compressive Strength Test
Report No.: 295024
Project No.: 0612510
Date of Service: 08/09/2007
Report Date: 09/11/2007
Project: Lesley Infrastructure
Services: Obtain samples of fresh concrete at the placement locations, perform required testing, cast compressive strength samples and bring
samples back to the laboratory for curing and testing in accordance with applicable standards.
Contractor:
Concrete Supplier: Lacy
Plant: On site
Specification Requirements
Strength: 3,600 psi @ 28 days
Slump (in.): 4" maximum
Air (%): 3% - 6%
Test Method: ASTM C-172
ASTM C-31 (except 10.1.2)
ASTM C-143
ASTM C-231
ASTM C-1064
ASTM C-138
ASTM C-39
PROJECT DATA
Mix Design 1.0.: 5194
Placement Date: 08/09/2007
Weather Conditions: Clear
Time Sampled: 02:10pm
Temperature - Air: 960F
Truck No: NA
Air Content: 4.1 %
Overall Placement Location:
Paving for Dividend Street, Station 0+00 to 19+00, eastbound lane
Measured
Slump
(inches)
1.25
Batch time: 02:00pm
Concrete: 1000F
Ticket No: NA
Unit Weight (pcf): NA
Sample Location:
Station 16+50
REPORT OF TESTS
Concrete Compressive Cylinder 6" x 12"
Cylinder Maximum Compressive
Marked Date Age Diameter Area Load Strength Fracture
Set No. Tested (days) (In) (in') (Ibs) (psi) Type
9 1 08/16/2007 7 6.00 28.27 84,670 2,990 Unbonded Cap
9 2 09/06/2007 28 6.00 28.27 106,330 3,760 Cone/Split
9 3 09/06/2007 28 6.00 28.27 101,820 3,600 Cone/Split
Average 3,680
9 4 08/14/2007 5 6.00 28.27 85,820 3,040 Un bonded Cap
Finished: 03:45pm Rone Engmeermg
,azk
Started: 06:00am
Technician: Ryan Rawlinson
Report Distribution:
Orlg: Duke Construction, LP (Dallas, TX)
Attn: Mr. Alex Bennett PE (1-ec copy)
1-cc City of Coppel! Attn: Mr. Larry Davis
1-ec Lacy Construction Attn: Mr. Kevin Briles
1-cc City of Coppell Attn: Mr. Lee Stone
~
K. Scott Watson, AET
Project Manager
LIMITATIONS: The test results presented herein were prepared based upon the specific samples provided for testing. We assume no responsibility for variation In quality
(composition, appearance, etc.) or any other feature of similar subject matter provided by persons or conditions over which we have no control. Our letters and reports are
for the exclusive use of the clients to whom they are addressed and shall not be reproduced except in full without the written approval of Rone Engineering Services, Ltd.
(LBILB) Page 9 of 9
Rone Engineering
.
Client: Duke Construction, LP
14241 Dallas Pkwy, Ste 1000
Dallas, TX 75254-2936
8908 Ambassador Row, Dallas, TX 75247
7701 W UttJe York, Ste 600, Houston, TX 77040
4421 Freldrlch, Ste 195, Austin, TX 78744
Corporate Phone: (2141 630.9745
Report of Concrete Compressive Strength Test
Report No.: 295294
Project No.: 0612510
Date of Service: 08/11/2007
Report Date: 09/11/2007
Project: Lesley Infrastructure
Services: Obtain samples of fresh concrete at the placement locations, perform required testing, cast compressive strength samples and bring
samples back to the laboratory for curing and testing in accordance with applicable standards.
PROJECT DATA
Contractor:
Concrete Supplier: Lacey
Plant: On site
Specification Requirements
Strength: 3,600 psi @ 28 days
Slump (in.): 4" maximum
Air (%): 3% - 6%
Test Method: ASTM C-172
ASTM C-31 (except 10.1.2)
ASTM C-143
ASTM C-231
ASTM C-1064
ASTM C-138
ASTM C-39
Batch time: 06:55am
Concrete: 850F
Ticket No: NA
Unit Weight (pet): NA
Measured
Slump
(inches)
3.0
Mix Design 1.0.: 5194
Placement Date: 08/11/2007
Weather Conditions: Clear
Time Sampled: 07:00am
Temperature - Air: 830F
Truck No: NA
Air Content: 3.9%
Overall Placement Location:
Paving, median and turn lanes, Beltline Rd. into project, 300' north, 15' west from
south end (cont)
Sample Location:
280' north, 13' west from south end turn lane
REPORT OF TESTS
Concrete Compressive Cylinder 6" x 12"
Cylinder Maximum Compressive
Marked Date Age Diameter Area Load Strength Fracture
Set No. Tested (days) (in) (in") (Ibs) (psi) Type
1 1 08/18/2007 7 6.00 28.27 60,130 2,130 Unbonded Cap
1 2 09/08/2007 28 6.00 28.27 78,060 2,760 Cone/Split
1 3 09/08/2007 28 6.00 28.27 69,520 2,460 Cone/Split
Average 2,610 it
4 08/15/2007 4 6.00 28.27 52,870 1,870 Unbonded Cap
* Does not comply with specified strength
Remarks: Cant: turn lane paving for Dividend S1. Station 49+00 to 47+50
LIMITATIONS: The test resulls presented herein were prepared based upon the specific samples provided for testing. We assume no responsibility for variation In quality
(composition, appearance, etc.) or any other feature of similar subject mailer provided by persons or conditions over which we have no control. Our letters and reports are
for the exclusIve use of the clients to whom they are addressed and shall not be reproduced except in full without the wrillen approval of Rone Engineering Services, Ltd.
(OMflS) Page 1 of 2
Rone Engineering
.
Client: Duke Construction, LP
14241 Dallas Pkwy, Ste 1000
Dallas, TX 75254-2936
8908 Ambassador Row, Dallas, TX 75247
7701 W Little York, Ste 600, Houston, TX 77040
4421 Freldrlch, Ste 195, Austin, TX 78744
Corporate Phone: (2141630..9745
Report of Concrete Compressive Strength Test
Report No.: 295294
Project No.: 0612510
Date of Service: 08/11/2007
Report Date: 09/11/2007
Project: Lesley Infrastructure
Services: Obtain samples of fresh concrete at the placement locations, perform required testing, cast compressive strength samples and bring
samples back to the laboratory for curing and testing in accordance with applicable standards.
PROJECT DATA
Contractor:
Concrete Supplier: Lacey
Plant: On site
Specification Requirements
Strength: 3,600 psi @ 28 days
Slump (in.): 4" maximum
Air (%): 3% - 6%
Test Method: ASTM C-172
ASTM C-31 (except 10.1.2)
ASTM C-143
ASTM C-231
ASTM C-1064
ASTM C-138
ASTM C-39
Batch time: 1 0:40am
Concrete: 980F
Ticket No: NA
Unit Weight (pet): NA
Measured
Slump
(inches)
3.75
Mix Design 1.0.: 5194
Placement Date: 08/11/2007
Weather Conditions: Clear
Time Sampled: . .1 0:45am
Temperature - Air: 910F
Truck No: NA
Air Content: 4.4%
Overall Placement Location:
Paving, median and turn lanes, Beltline Rd. into project, 300' north, 15' west from
south end (cant)
Sample Location:
120' north, 7' west from south end turn lane
REPORT OF TESTS
Concrete Compressive Cylinder 6" x 12"
Cylinder Maximum Compressive
Marked Date Age Diameter Area Load Strength Fracture
Set No. Tested (days) (in) (in') (Ibs) (psi) Type
2 1 08/18/2007 7 6.00 28.27 75,670 2,680 Unbonded Cap
2 2 HOLD
Comments: Destroyed in Field
2 3 09/08/2007 28 6.00 28.27 83,240 2,940 Cone/Split
2 4 08/15/2007 4 6.00 28.27 65,350 2,310 Unbonded Cap
Finished: 01 :45am R E. .
~~
Started: 05:15am
Technician: Ryan Rawlinson
Report Distribution:
Orig: Duke Construction, LP (Dallas, TX)
Attn: Mr. Alex Bennett PE (1-ec copy)
1-cc City of Coppell Attn: Mr. Larry Davis
1-ec Lacy Construction Attn: Mr. Kevin Briles
1-cc City of Coppell Attn: Mr. Lee Stone
~
K. Scott Watson, AET
Project Manager
LIMITATIONS: The test resulls presented herein were prepared based upon the specific samples provided for testing. We assume no responsibility for variation in quality
(composition, appearance, etc.) or any other feature of similar SUbject matter provided by persons or conditions over which we have no control. Our lelters and reports are
for the exclusive use of the clients to whom they are addressed and shall not be reproduced except in full without the written approval of Rone Engineering Services, Ltd.
(DMlLB) Page 2 of 2