DR9101-CS 910619June 19, 1991
Mr. Mike Sperling
M-S Utilities
Route 5, Box 91
Rockwa11, Texas 75087
De~haz,. Starek & Tang, Inc.
Engineers · Planners
Re: Oak Trail Drainage Improvements
Coppe11, Texas
Dear Mr. Sperling:
In accordance with the executed contract documents on the
referenced project, this is the Notice to Proceed. You are
hereby requested to proceed with construction on this
project on June 24, 1991. The allowable construction time
is sixty (60) calendar days. Therefore, the date of
completion is August 22, 1991.
Please contact Carol Knewitz at 650-1200 (work) to arrange
a meeting to discuss any questions about the construction
process and its possible impact on her property.
Distribute copies of the enclosed flyer announcing this
project to area residences 48 hours prior to construction
as discussed in the preconstruction meeting.
If you have any questions, please call me at 748-6740.
Sincerely,
Paul A. Tucker
Engineering Associate
PAT/smh
89256.20