Loading...
DR9101-CS 910523 (2)The City With A Beautiful Future P.O, Box 478 Coppell, Texas 75019 214 - 462 - 0022 May 23, 1991 City of Coppell Oak Trail Drainage NOTICE TO RESIDENTS This is to notify you that construction of a new underground storm drainage pipe in your neighborhood will begin in a few weeks. M-S Utilities is the contractor for the drainage improvement project. The pipeline will begin at 121 Oak Trail Drive and will proceed north along Oak Trail Drive and east along Willoway Lane to a point just west of Shady Dale Lane. Access to homes will be maintained at all times. However, Willoway Lane will be closed to traffic for 4 to 6 weeks. Total construction time for this project will be 8 to 10 weeks. If you have any questions or concerns during the construction, please call Paul Tucker of DeShazo, Starek & Tang at (214) 748-6740.