Kimbel 7&8-CS080408 (2)
THE.CITY.OF
April 8, 2008
Brandon O'Donald, P.E.
O'Donald Engineering
1601 E. Lamar Blvd. Ste. 210
Arlington, TX 76054
RE: Kimbel Addition Lot 8R
Construction Plan Review Comments
The City of Coppell has reviewed the referenced plans and has the following comments
to offer:
General/Coversheet-
1. Add North to 134 MacArthur address.
2. Add Kimbel Addition to title.
3. Remove the standard details from the plans set. Keep only the site specific details.
(The contractor should have a copy of the standard details with him at all times).
Site Plan and Drainae:e Area Map-
4. Correctly label the proposed IS" and 12" storm sewer line on the plan.
Pavine: Plan -
5. If you plan on not using lime or cement stabilization for the subgrade, you must
request a variance on the sub-grade, which requires submitting a letter for approval
with the geotechnical report.
6. Include in the notes "The contractor must submit a traffic control plan to the City of
Coppel! engineering department at least 48 hours prior to start of work."
7. F ol!ow the city standard details for the construction joints.
Water and Sanitary Sewer Plan -
8. Revise the General Notes according to the City of Coppell Standards.
Erosion control Plan -
9. Label correctly.
With these comments addressed the plans will be approved. The City of Coppell requires
three sets of final construction plans for its use; your office should submit as many
additional sets for stamping as is necessary for construction operations. All contractors
and subcontractors onsite must have a copy of the plans approved by the City of Coppel!
along with a copy of the City's standard construction details.
255 PARKWAY * P.O.BOX 9478 * COPPELL TX 75019 * TEL 972/462 0022 * FAX 972/304 3673
All fees must be paid prior to release of this project for construction. The City charges a
2% inspection fee for all private construction outside the building's footprint. This
includes dirt work, paving, storm drains, water lines, sewer lines, drainage pipes, etc. that
are private. For all installations in the public right-of-way or easement, the City charges a
4% fee. A check for inspection fees made to the City of Coppell should be submitted to
this office along with the Construction Development Permit Application and a copy of
the Construction Site Notice. For your convenience a spreadsheet is attached to the
permit application for use in calculating the inspection fees. A copy of the contract(s)
should be attached for verification purposes. If you have any questions, please contact
me at your convenience.
Sincerely,