ST9905-CN070628
CITY OF COPPELL
CHANGE OR EXTRA WORK ORDER
PROJECT: Bethel Road I Project # ST 99-05
CONTRACTOR: Tiseo Paving Company
OWNER: City of Coppell
CHANGE ORDER NO.:
Three (3)
DATE: June 28, 2007
Description
Quantity Unit
Total
Unit
Price
Line Lowering of 16" RCCP:
Add:
1. 16" RCCP spoil ends & manuf.
services Freeport & Bethel
1
LS
2. Crew Time (5-6 hrs)
1
1
LS
LS
3. Extra Equipment Compressor,
Pumps & Shoring
4. Subs Profit/Overhead
5. Tiseo Profit/Overhead
1
1
LS
LS
3,500 $3,500.00
2,500 $2,500.00
1,200 $1,200.00
600 $600.00
792 $780.00
Total Revision to Contract Amount Change Order #3
$8,580.00
Original contract amount
Net increase in contract amount Change Order #1
Net increase in contract amount Change Order #2
Net increase in contract amount Change Order #3
Revised contract amount
Net increase in contract time of completion
Revised Contract time of completion
$7,293,659.00
o
$8,000.00
$8,580.00
$7,310,239.00
3
573 Calendar Days
Page 1 of 2
The contractor hereby accepts this Contract adjustment as a final and complete adjustment in full
accord and satisfaction of all past and future liability originating under any clause in the Contract by
reason of this revision to the Contract.
-~}7
Date
~~~
Agreed to y TIseo Pavmg Company
Date
Page 2 of 2