ST9905-CN071009
CITY OF COPPELL
CHANGE OR EXTRA WORK ORDER
PROJECT: Bethel Road I Project # ST 99-05
CONTRACTOR: Tiseo Paving Company
OWNER: City of Coppell
CHANGE ORDER NO.: Five (5) DA TE: October 9, 2007 Page 1 Of 2
Item Description Quantity Unit Unit Price Total
Minyard's Development:
ADD: Water Line @ Sta 50+06.5
1. Additional Traffic Control LS 750.00 $750.00
2. Additional Staking LS 250.00 $250.00
3. 16" x 8" Tapping Sleeve & Valve EA 3,850.00 $3,850.00
4. Asphalt/Flexbase Street Repair 1 LS 1,500.00 $1,500.00
5. Bore w / Casing Under Existing 25 LF 230.00 $5,750.00
Street
6. Bore w/o Casing Under Existing 12 LF 115 . 00 $1,380.00
Box
7. Two 450 Bends & Plug LS 1,750.00 $1,750.00
8. 8" PVC 97 LF 55.25 $5,359.25
9. Testing LS 700.00 $700.00
Sewer Line @ Sta 50+ 18.85
10. Additional Traffic Control 1 LS 750.00 $750.00
11. Additional Staking 1 LS 250.00 $250.00
12. Steel Plate & MH Safety Ring LS 2,200.00 $2,200.00
13. Asphalt/Flexbase Street Repair LS 2,500.00 $2,500.00
14. Bore w/o Casing under Box 12 LF 115.00 $1,380.00
15. 8" Plug EA 200.00 $200.00
16. Testing LS 700.00 $700.00
17. 8" PVC Sewer Line 65 LF 63.75 $4,143.75
18. 4-ft Diameter Manhole EA 4,200.00 $4,200.00
19.
20.
2l.
22.
23.
Median Openings
9" Concrete Pavement
357
7.5
357
2
67
Lime @ 42 lbs/SY
8" Stabilized Subgrade
Median Noses
Stamped Concrete
Total Revision to Contract Amount
SY
TON
SY
EA
SY
29.00
105.00
2.95
1,200.00
83.00
$10,353.00
$787.50
$1,053.15
$2,400.00
$5,561.00
$57,767.65
Previous contract amount
Net increase in contract amount Change Order #1
Net increase in contract amount Change Order #2
Net increase in contract amount Change Order #3
Net increase in contract amount Change Order #4
Net increase in contract amount Change Order #5
Revised contract amount
Net increase in contract time of completion
Revised Contract time of completion
$7,293,659.00
o
$8,000.00
$8,580.00
$14,247.00
$57,767.65
$7,382,253.65
o
573 Calendar Days
The contractor hereby accepts this Contract adjustment as a final and complete adjustment in full
accord and satisfaction of all past and future liability originating under any clause in the Contract
by reason of this revision to the Contract.
r{~ t-P_JJ 10 '9.7
lkCd~ nde~ b~~Engineer Date
g-- /~ C)
Date
Page 2 Of 2