Loading...
SS9301-CS 930713 (2) -- "5 ~ '1 ~ -0 I CITY OF COPPELL CHANGE OR EXTRA WORK ORDER PROJECT: Grapevine Creek Sewer Trunk Project Branches I and II CONTRACTOR: Kenko Inc. Contractors OWNER: City of Coppell CHANGE ORDER NO.: 3 DATE: 7/13/93 CHANGE OR EXTRA WORK TO BE DONE Delete 589 feet of 30" PVC Sewer Pipe (20-25) 589 feet @ $98.00 per foot - $ 57,722.00 Add 589 feet of Micro-tunnel & pipe 589 feet of Micro-tunnel & pipe @ $270.00 per foot $159,030.00 Total cost of proposed changes $101,308.00 Previous contract amount Net increase in contract amount Revised contract amount Net increase in contract time of completion Revised contract time of completion $2,815,005.50 $ 101,308.00 $2,916,313.50 N/A No Change The contractor hereby accepts this Contract adjustment as a final and complete adjustment in full accord and satisfaction of all past and future liability originating under any clause in the Contract by reason of this revision to the Contract. Recommended by the City Engineer: Date: ~ Date: 7i9/? 1 ( Z;;:z Date: 7),43