CITY OF COPPELL
CHANGE OR EXTRA WORK ORDER
PROJECT:
Grapevine Creek Sewer Trunk Project
Branches I and II
CONTRACTOR:
Kenko Inc. Contractors
OWNER:
City of Coppell
CHANGE ORDER NO.: 3
DATE: 7/13/93
CHANGE OR EXTRA WORK TO BE DONE
Delete 589 feet of 30" PVC Sewer Pipe (20-25)
589 feet @ $98.00 per foot
- $ 57,722.00
Add
589 feet of Micro-tunnel & pipe
589 feet of Micro-tunnel & pipe @ $270.00 per foot
$159,030.00
Total cost of proposed changes
$101,308.00
Previous contract amount
Net increase in contract amount
Revised contract amount
Net increase in contract time of completion
Revised contract time of completion
$2,815,005.50
$ 101,308.00
$2,916,313.50
N/A
No Change
The contractor hereby accepts this Contract adjustment as a final and complete adjustment in full
accord and satisfaction of all past and future liability originating under any clause in the Contract
by reason of this revision to the Contract.