SS9301-AG 930713 i \.~,f l^ ~ . VU. - AGENDA REQUEST FORM CITY COUNCIL MEETING July 13. 1993 ITEM NUMBER J '7 ITEM CAPfION: Consideration and approval or Change Order #3 to the Grapevine Creek Sewer Trunk Main Branches I and II in the amount or $101,308.00 and authorizing the Mayor to sign. SUBMITTED BY: . sr~~~~:w~ OTHER REP.: DATE: EVALUATION OF ITEM: CITY DATE APPROVED RY u' CfU~CIL '1 I,j q '$ I See attached memo. BUDGET AMT. vJ+ I AMT. + 1- BUDGET AMT. ESTIMATED L FINANCIAL REVIEW BY iJ1a..-.. f COMMENTS: Wat<< & Sewer Rev.,... ...... Seri. 1991 Wat<< & Sewer ReveIlIIe..... Series 1992 $2,490,000 1.500.. $3,990,000 3.247.. $742.'" Paid & Encumbered at of "'30-93 .Available as of 6-30-93 Funds can come from this avail.... W- REVIEWED BY CM.dAl:;J~ . LEGAL REVIEW BY: AGENDA REQUEST FORM REVISED 2/93 MEMORANDUM To: Mayor and City Council Kenneth M. Griffin, P.E., City Engineer ~ From: RE: Consideration and approval of Change Order #3 to the Grapevine Creek Sewer Trunk Main Branches I and n in the amount of $101,308.00 and authorizing the Mayor to sign. Date: July 13, 1993 For some time now the City has been negotiating with Mr. Don Carter and Mr. Jay Riney for the acquisition of temporary construction easements across their property. The total square footage of the easement the City has been trying to obtain is 77,898 square feet. This easement in essence extends from Moore Road westward to Grapevine Creek (see attached exhibit). On June 6th, 1993, the contractor, my inspector, Mr. Jim King (representing Mr. Carter) and myself walked the project to determine the extent of tree removal and potential damage to the property. The first 1500 feet of Mr. Carter's property had various trees where the City would have to remove limbs and in some cases entire trees, but in all cases it was sporadic on the removal of the trees. To install the sewer line on the west 300 feet of Mr. Carter's property and across Mr. Riney's property would necessitate the removal of ever tree within the easement. Even with the removal of all the trees, it was still questionable whether or not the contractor would have adequate space to stock pile materials and access the project. In essence, to open cut to install the sewer line would necessitate the removal of approximately 30 to 35 trees and would entirely change the view of the property. Immediately south of Mr. Riney's property, the City had already bid the project to begin the micro-tunnelling process from the north side of Grapevine Creek to the west side of Denton Tap Road. This includes micro-tunnelling the entire stretch of Bethel Road in the Creekview Subdivision. It is doubtful that Mr. Carter will be willing to negotiate with the City on the acquisition of the easement if the City holds to its position of open cutting the last three hundred feet of Mr. Carter's property and removing every tree in that area. However, after a meeting on July 7, 1993 with Mr. Carter, there is an indication by Mr. Carter that he will grant us a temporary easement, grant us the ability to move the sewer line to avoid some of his other trees and then grant us a new 20 foot easement over the top of the new sewer line and allow us to remove trees and branches on the east side of the property as necessary to install the line if in return the City will micro-tunnel the last 300 feet of his property and the 300 feet on the adjacent property thereby saving all the trees in this area. The cost to micro-tunnel this project $101,308.00. Currently, the section of the sewer line installation from MacArthur to Moore Road has basically been completed. This is about 37% of the entire project. As of yet, the City has encountered no unusual situations or circumstances which would necessitate a change in the scope of the project. Council may recall that when this project was awarded I indicated that there was a strong potential for various change orders throughout installation of this project due to the complexity of the project and the unknowns encountered dealing with the construction of the project. The Engineering Department's recommendation is to approve Change Order # 3 in the amount of $101,308.00 to micro-tunnel an additional 589 feet on this project. Staff will be available to answer any questions. -- CITY OF COPPELL CHANGE OR EXTRA WORK ORDER PROJECT: Grapevine Creek Sewer Trunk Project Branches I and II CONTRACTOR: Kenko Inc. Contractors OWNER: City of Coppell CHANGE ORDER NO.: 3 DATE: 7/13/93 CHANGE OR EXTRA WORK TO BE DONE Delete 589 feet of 30" PVC Sewer Pipe (20-25) 589 feet @ $98.00 per foot - $ 57,722.00 Add 589 feet of Micro-tunnel & pipe 589 feet of Micro-tunnel & pipe @ $270.00 per foot f I Total cost of proposed changes I $159,030.00 $101,308.00 Previous contract amount Net increase in contract amount Revised contract amount Net increase in contract time of completion Revised contract time of completion $2,815,005.50 $ 101,308.00 $2,916,313.50 N/A No Change The contractor hereby accepts this Contract adjustment as a final and complete adjustment in full accord and satisfaction of all past and future liability originating under any clause in the Contract by reason of this revision to the Contract. y the City Engineer: , Date: 7/ ' ~ /0... 3 Date: '//9/1 :1 Date: 7); /$Z;> / ' - CITY OF COPPELL CHANGE OR EXTRA WORK ORDER PROJECT: Grapevine Creek Sewer Trunk Project Branches I and II CONTRACTOR: Kenko Inc. Contractors OWNER: City of Coppell CHANGE ORDER NO.: 3 DATE: 7/13/93 CHANGE OR EXTRA WORK TO BE DONE Delete 589 feet of 30" PVC Sewer Pipe (20-25) 589 feet @ $98.00 per foot - $ 57,722.00 Add 589 feet of Micro-tunnel & pipe 589 feet of Micro-tunnel & pipe @ $270.00 per foot $159,030.00 $101,308.00 Total cost of proposed changes Previous contract amount Net increase in contract amount Revised contract amount Net increase in contract time of completion Revised contract time of completion $2,815,005.50 $ 101,308.00 $2,916,313.50 N/A No Change The contractor hereby accepts this Contract adjustment as a final and complete adjustment in full accord and satisfaction of all past and future liability originating under any clause in the Contract by reason of this revision to the Contract. Recommended by the City Engineer: , Date: 7/'~ I ~ Date: .7//~/7 J Accepted by the Owner: Date: 1a7d37/93 113:51 Z 12149315474 KENKO INC P.la2 ~!!!!f9= July 7, ] 993 City ot Coppell 255 Parkway Boulevard Coppall, TX 750]9 Attn: Hr. Ken Griffin, r.E. Rc: Grapevine Creek SowAr Trunk Main - Branch J Ci ty 01 Coppe] 1, 'J'X Kenko Job #9306 * Additional mico-tunnel . Rta. 83+24 to Sta. 89+13 Dear Sirs: Tn response to your request, the fOllowing are COSt5 involved in changintg the sewer on the referenced project fro~ Station 83+24 to Station 89+13 to micro-tunnelling in lieu of open cut. Add: 589 Li.near Foot 589 Linear ft~oot Micro-tunnel 0 30" FBROLS Pipe 0 $] 5!1. 00/1 f $.115.00/1f S 91,295.00 _6:1,735.00 Subtota.l (Add) $1!,9. 030.00 pelate: 589 Linear Foot 2610-4 30" PVC (20'-25' Depth) . $98.00 $ 57. 722~Q.Q. Subtotal (De]ete) $ 57,r/22.00 Not Chango Add $]01,308.00 If this Change Order. is approved, please forward the appropriate Please call if YOU have any questions. . ~ a1 erely. (Ua/J/~~-. llaniel R. F~~~p:;r--' Kenko, Inc. 50U'n1~1':.~TERN DIVISIO~~. I 6415 ^t1dl~ml f{lI,., Ste. ~~.IU - Dallas~ :f~_.!J').?-48 . (2'.4) 9.} J -94~~~!!!.~ .(214)P31-S4 ?~.____ WEsn~KN UIVJSION - Post Orfit;C Box 8':' 1 - Calimesa, calilornla 9:l;520 . (7 J II) 795.2568 - Fa/( (714) 795.184.0 '--... ~'.- ... --- "-" . ...-.... - .. ... ... COf{"'ORA'l~ OFFlCL - 1694 91sl AVCllut~ . blalne. Minnesota 55'1'19 - (612) 786-65 II) . Fax (612) 786-6602 J- \ ' t ' \ ,~ \ " '~ \ :; !~\ 6~ ",," ~ ; \ \~ \ .. L- ...... \" '--, -- \-\~~j.\ ___________________._~~,I-----i \ '____--\ \ .. \ \ .. .. \ ~ , , I , I I _.~ - -----t I ! ~ ,.; II! \ l"") 'l1: "" ~ <5 <l) Q() r::: l:l 6 "" ~ Q() r::: ;.::: <l) r::: r::: i! e ~ ~ '(:;> .tz .~ ~ ~ <l) ... (;) ~ &; , \ , \ " \ - .....;, ..; 00 0\ 00 t-.. ~ t-.. '- .... r::: <l) E: <l) ~ te (;) 0-/::1 ~ S ... te 8 t' ~ (;) ~ ~ "Q> .tz :~ .::s ~ <l) ... (;) ~ &; ---- ~'J "'--0 , _.,-'~.j 8 ! ~ ; S C i ~ I .'f/# - H.LlION ~ acres, located at the southwest comer of Freeport Parkway and Bethel Road in the City of Coppell. Mayor Pro Tern Robertson moved to approve Ordinance No. 93607 designating Minyards Foods, Inc. Tax Abatement Area as Reinvestment Zone No.1 (TAR-I); pursuant to Section 312.201 of the Property Redevelopment and Tax Abatement Act, said area being the property owned by Minyards Foods, Inc., and described as Tract 1, Abstract 1439, consisting of 62.528 acres, located at the southwest comer of Freeport Parkway and Bethel Road in the City of Coppell. Council member Reitman seconded the motion; the motion carried 6-0 with Mayor Pro Tern Robertson and Council members Weaver, Stahly, Reitman, Mayo, and Garrison voting in favor of the motion. 16. A. Reconsideration of action taken regarding an ordinance for Case #PD-129(R) to change the zoning designation from (TC) to (PD-SF-9) on a parcel of land located at the southwest comer of Parkway Boulevard and Denton Tap Road. Mayor Pro Tern Robertson moved to reconsider the action taken regarding an ordinance for Case #PD-129-(R) to change the zoning designation from (TC) to (PD-SF-9) on a parcel of land located at the southwest comer of Parkway Boulevard and Denton Tap Road. Council member Garrison seconded the motion; the motion carried 5-1 with Mayor Pro Tern Robertson and Council members Stahly, Reitman, and Mayo voting in favor of the motion and Council member Weaver voting against the motion. Council member Garrison abstained which is considered as an affirmative vote per City of Coppell Home Rule Charter, ~3.11-B. B. Discussion and consideration of approving an ordinance for Case #PD-129(R) changing the zoning from (TC) to (PD-SF-9) on land located at the southwest comer of Parkway Boulevard and Denton Tap Road and authorizing the Mayor to sign. Mayor Pro Tern Robertson moved to approve Ordinance No. 915oo-A-37 for Case #PD-129(R) changing the zoning from (TC) to (PD-SF-9) on land located at the southwest comer of Parkway Boulevard and Denton Tap Road and authorizing the Mayor to sign. Councilmember Mayo seconded the motion; the motion carried 5-1 with Mayor Pro Tern Robertson and Council members Stahly, and Mayo voting in favor of the motion and Council member Weaver voting against the motion. Council members Reitman and Garrison abstained which is considered as an affirmative vote per City of Coppell Home Rule Charter, ~3.11-B. 17. Consideration and approval of Change Order #3 to the Grapevine Creek Sewer Trunk Main, Branches I and II in the amount of $101,308.00 and authorizing the Mayor to sign. Ken Griffin, City Engineer, made a presentation to the council. Mayor Pro Tern Robertson moved to approve Change Order #3 to the Grapevine Creek Sewer Truck Main Branches I and II in the amount of $101,308.00. Council member Mayo seconded the motion; the motion carried 6-0 with Mayor Pro Tern Robertson and Council members Weaver, Stahly, Reitman, Mayo, and Garrison voting in favor of the motion. The Consent Agenda Items 22 Band J were considered at this time. See Item 22 for minutes. EXECUTIVE SESSION (Closed to the Public) '1 ..... A. Article 6252-17, Section 2(e), and Senate Concurrent Resolution Number 83, discussion with City Attorney concerning matter involving privileged communications between attorney and client. CM071393 Page 5 of 9