DR9002-CS 901017COPPELL P~BLIC WORKS
October 17, 1990
Shohre Daneshmand, Civil Engineer
Larry D~Development Construction Inspector
Hill Drive Drainage
On Monday, March 5, 1990 the City of Coppell accepted bids for
localized drainage improvements for Hill Drive Alley drainage
improvement. The improvements included removal and replacement of
concrete alley pavement, placement of 18" RCP storm sewer and grate
inlets.
By City Council action on April 24, 1990 a contract was awarded to
S.¥.B. Construction Companyv P.O. Box 13614, Arlington, Tx with
construction activity com~Gencing on June 18, 1990.
A final inspection of the project has been confirmed by
representatives of the Public Works Department and accepted as
complete and inplace per contract.
S.¥.B. Construction Company has submitted the final payment request
for City Council consideration and approval (see attached).
If I can be of further assistance please let me know.
CLD/m?
HILLDRIV.CLD