DR9002-CS 900806COPP~LL PUBLIC WORKS
ME~RAND~M
August 6, 1990
~.Shohre Daneshmand, Acting City Engineer
Larry ~ ,~onstru¢:tion Inspector
Hill Drive Drainage
The R.C.P., inlet, and concrete alley paving is now complete and
in place in Phase I and Phase II of the Hill Drive Drainage between
Mockingbird and HAil Drive.
Pay estimate #2 has been received and is being processed along with
a notification letter to each resident, adjacent to the project,
informing them the alley section is open to traffic flow.
Upon receipt of the final pay request expected near September 1,
1990, the contractor requested that a council agenda item be
prepared and brought before the City Council, in order that final
payment be made.
Should you have any questions, please do not hesitate to contact
me.
Thank you.
CLD/bd
HILLDRI2.CLD