A pre-construction conference on the referenced project has been scheduled for
Thursday, June 19,2008 at 2:00 p.m. in the 2nd floor conference room in Town Center at
255 Parkway Blvd.
Please notify the franchised utility companies, contractors, sub-contractors, testing lab
and any other interested parties so that they may have a representative present. If you
have any questions concerning this project prior to the scheduled meeting, feel free to
contact me at (972) 304-3684.
~--
----
~
----
La
cc: Ken Griffin, P.E., Dir. of Engineering & Public Works
Glenn Hollowell, P.E., Asst. Dir. of Public Works
Lee Stone, Commercial Building Inspector
Tim Oates, Fire Marshal
255 PARKWAY * P.O.BOX 9478 * COPPELL TX 75019 * TEL 972/462 0022 * FAX 972/304 3673
2
RESPONSIBILITY FOR PRE-CONSTRUCTION
MEETING NOTIFICATION
The owner I owner's representative will be notified of the date, time and place of
the pre-construction meeting once it is scheduled by the Construction Inspector
assigned to the project.
It is the owner / owner representative's responsibility to notify the following
parties:
. Franchise Utilities (including but not limited to electric, gas, cable, &
telephone providers)
. Geotechnical firm
. Project Engineer
. Contractors or subcontractors for excavation, utility, & paving operations
. SWPPP representative