MacArthur Vista-LR070612
REECl EnGinEERinG
GEOTECHNICAL AND G R 0 U F'
ENVIRONMENTAL CONSULTANTS
REPORT OF REINFORCING
STEEL PLACEMENT OBSERVATION
MacArthur Vista Center
670 N. MacArthur Boulevard
Coppel!, Texas
REPORTED TO: MacArthur Vista, LP
12201 Merit Drive, Suite 170
Dallas, Texas 75251
ATTN: Mr. Alen Hinckley
REPORT NO. 33
REPORT DATE: 06-12-07
REG PROJECT NO. 14082
DATE OBSERVED: 05-22-07
TECHNICIAN: R. Weathersby
PAGE: 1 of 1
CONTRACTOR: Royal General Contractors, Inc.
I Items Observed:
I Sidewalk: 90'N-298'S, 68-89'W from west Vista Center
Building.
I Reference Plans or Notes Used: I Sheet 4
x IThere were no deviations noted.
The reinforcing steel placed at the above referenced locations was observed with
respect to the referenced portions of the contract documents.
Mail
Distribution: (1) MacArthur Vista, LPI
Mr. Alen Hinckley
(1) City of Coppell/Mr. Lee Stone
(1) City of Coppell/Mr. Rick O'Dell
(1) Daniels & Associatesl
Mr. Brent Lovelady
(1) Royal General Contractorsl
Mr. Bob Fowles
(1) Royal General Contractorsl
Mr. Micah Corn
(1) UBSE/Mr. Gary Ten Eyck
Submitted by:
REED ENGINEERING GROUP, LTD.
Original Signed By
Ronald F. Reed, P.E.
BW/rs