Loading...
ST9905-CN080915 CITY OF COPPELL CHANGE OR EXTRA WORK ORDER PROJECT: Bethel Road I Project # ST 99-05 CONTRACTOR: Tiseo Paving Company OWNER: City of Coppell CHANGE ORDER NO.: Ten (10) DATE: September 15,2008 Item Description Quantity Unit Unit Price Total ADD: 1. Remove & Replace Manhole 7 EA 1,250.00 $8,750.00 Cone 2. Crushed limestone material 1 LS 3,450.00 $3,450.00 3. Labor for Channel stabilization 1 LS 2,800.00 $2,800.00 4. Equipment charges 1 LS 4,325.00 $4,325.00 5. Contractor overhead 10% 1 LS 1,057.50 $1,057.50 Net Increase to Contract Amount $20,382.50 Total Change to Contract $20,382.50 ~ i;)'fte.Jrl;z-. f/~2/oi CHANGE ORDER NO.: Ten (10) DATE: September 15, 2008 Original contract amount Net increase in contract amount Change Order # 1 Net increase in contract amount Change Order #2 Net increase in contract amount Change Order #3 Net increase in contract amount Change Order #4 Net increase in contract amount Change Order #5 Net increase in contract amount Change Order #6 Net increase in contract amount Change Order #7 Net increase in contract amount Change Order #8 Net increase in contract amount Change Order #9 Net increase in contract amount Change Order #10 $7,293,659.00 o $8,000.00 $8,580.00 $14,247.00 $57,767.65 $270,088.40 $12,845.00 o $120,836.68 $20,382.50 Revised contract amount $7,806,406.23 570 Calendar Original contract time Days Previously approved additional time Additional time requested for this change Revised Contract time of completion 88 Days o Days 694 Calendar Days The contractor hereby accepts this Contract adjustment as a :final and complete adjustment in full accord and satisfaction of all past and future liability originating under any clause in the Contract by reason of this revision to the Contract. R~~ngineer q~I'-.f Date ./18 Y /Z"VJ Date