RE: Sandy Lake Oaks Addition, (Family Video)
Provisional Letter of Acceptance
Dear Mr. Mattice:
Representatives of the City of Coppell are issuing a Provisional Letter of Acceptance for the
referenced project with the following conditions:
1. There are several cracks around the entire parking lot that need to be sealed.
2. You must comply with the City of Coppell Stamped Concrete Ordinance.
3. The pipe inside the northwest drain box needs to be grouted.
4. A two-year maintenance bond for paving with supporting documents is required.
A final acceptance letter will be issued when all conditions have been met.
A follow-up inspection of the facilities will be conducted prior to the lapse of the two-year
bond period. If any punchlist items are noted at that time, you will be contacted to make
repairs. Thanks for your cooperation.
Sincerely,
~[)
Larry Davis
Construction Inspector
Office Phone: (972) 304-3684
Fax: (972) 304-3570
cc: Ken Griffin, P.E., Director of Engineering & Public Works
Glenn Hollowell, P.E., Asst. Director of Public Works
Greg Jones, Chief Building Official
Tim Oates, Deputy Chief/Prevention
Alan Ricord, FX: 616-285-8001
Bob Moyer, FX 616-285-8001