DEPT: Engineering
DATE: January 13, 2009
ITEM #: 1 5
AGENDA REQUEST FORM
THE'CiTY.OF
D \VORK SESSION
D CONSENT
[{] REGULAR
ITEM TYPE: CONTRACT/BID or PROPOSAL
ITEM CAPTION:
Consider approval of an Engineering Services contract amendment in the amount of $71 ,500 to a contract approved
on January 22, 2008 with Halff Associates, Inc.; for additional services related to the Southwestern Boulevard
Infrastructure Improvements (from South Coppell Road to east of Grapevine Creek), Project #ST 07-01; and authorizing
the City Manager to sign and execute any necessary documents.
GOAL(S):
~..
~
EXECUTIVE SUMMARY:
This contract amendment will cover the cost of redesign for building the Grapevine Creek bridge in two phases in
order to maintain one-way traffic eastbound for the duration of construction.
FINANCIAL COMMENTS:
Funds are available in the Street CIP accounts for this change order.
RECOMMENDED ACTION:
ACTION TAKEN BY COUNCIL:
Staff recommends approval of the contract amendment.
APPROVED BY
CITY COUNCIL
ON ABOVE DATE
Motion to Approve
M - Brancheau
S - Hunt
Vote - 7-0
. Libby Ball
tLc- 200901.14
15:37.13
-06'00'
I#Amend Halff Contract
=== HALFF
...
CITY OF COPPELL
CONSULTING ENGINEER'S CONTRACT
PROJECT NO. ST 07-01
AMENDMENT TO SCOPE OF SERVICES
I. Scope of Work
Halff Associates will provide engineering services required to modify the Southwestern
Boulevard Road and Bridge Improvement project construction plans and bidding
documents to reduce the roadway width from 45-feet to 41-feet. Services also include
bridge plan modifications to allow for construction of the Grapevine Creek bridge in 2
phases.
A. Provide updated schematic of new roadway and bridge layout showing reduced
width and transition to existing paving at Coppell Road.
B. Update construction plan set and bidding documents.
C. Provide suggested sequencing schematic showing how access is maintained
during construction.
II. Proiect Schedule
.
Obtain City approval of contract amendment
Prepare and gain approval of revised schematic layout
Update road and bridge plans.
Bidding
Execute construction contract and begin construction
Jan. 2009
Jan. 2009
Feb./Mar. 2009
Mar./Apr. 2009
Apr./May 2009
.
.
.
.
. 1:\250DDs\25816\Admin\Contracts\City of Coppell\Amendment Rd & Bridge\Amendment ST 07 -01.doc
~t;t1f~ 'INjo9
EiE HALFF
III. Compensation
Engineer shall be paid an additional lump sum amount of Seventy-one thousand five-
hundred and no/100 Dollars ($71,500). The amount includes the following:
Basic Plan Modification
Bridge Plan Modification (First Structure)
Second Bridge Plan
Sequencing Schematic
TOTAL
$24,000
$12,500
$30,000
$ 5.000
$71,500
AGREED:
THE CITY OF COPPELL
By:
ofJ?4'
AGREED/ACCEPTED:
HALFF ASSOCIATES, INC.
By:
()\~~
Date 1-2.0'1
~~(tpJl/
Att:&#'~
1:\25000s\25816\Admin\Contracts\City of Coppell\Amendment Rd & Bridge\Amendment ST 07 -01.doc