ST0003-CN090205CITY OF COPPELL CHANGE OR EXTRA WORK ORDER PROJECT: Coppell Road Project # ST 00 -03 CONTRACTOR: Tiseo Paving Company OWNER: City of Coppell CHANGE ORDER NO.: One (1) DATE: January 21, 2009 Pg 1 of 2 Item Description 1. Storm Sewer Modifications at Robertson Pools 2. Cut and Plug 8" Water Line (3 locations) 3. Install 4" Water Service to MHP 4. Temporary Sidewalk for Pedestrian Access to Wilson Elementary 5 Investigate & Repair existing water services Total Revision to Contract Amount Quantity Unit Unit Price Total 1 LS 6,464.70 $6,464.70 1 LS 3,052.50 $3,052.50 1 LS 4,348.30 $4,348.30 1 LS 3,850.00 $3,850.00 5 EA 770.00 3,850.00 $21,565.50 CHANGE ORDER NO.: One (1) Previous contract amount Net increase in contract amount Change Order #1 Revised contract amount Net increase in contract time of completion Contract time of completion Pg2of2 $2,857,846.30 $21,565.50 $2,879411.80 0 365 Calendar Days The contractor hereby accepts this Contract adjustment as a final and complete adjustment in full accord and satisfaction of all past and future liability originating under any clause in the Contract by reason of this revision to the Contract. %�-4n t -2b• 9 Recorridlended by ti Engineer Date a-59 Agre d to by Contractor Date L D'P Accepted y City ate P.O. Box 270040 Dallas, Texas 75227 -0040 January 20, 2009 0 Keith Marvin, P.E. City of Coppell 255 Parkway Coppell, Texas 78019 Re: Coppell Road ST 00 -03 Investigate and Repair Water Services Mr. Marvin, ff , d3 PAVING COMPANY Telephone (972) 289 -0723 Fax (972) 216 -5637 C- C') Z�-Z Please see the attached request for additional work. We have attached a breakdown from North Texas Contracting for your review. An additional 10% for Tiseo Paving Co. is requested below. NTC $3,500.00 TISEO10% 350.00 TOTAL $3,850.00 Sincerely -4 u Lance Smith Project Administrator E4r4&4ked 1974 North Texas Contracting, Inc 4999 Keller Haslet Road Keller, Texas 76248 817 - 430 -9500 / (F) 817 - 430 -9207 Date: January 15, 2009 Attn: Lance Smith Tiseo Paving Company Coppell Road Reconstruction Re: Revised Change Orders Mr. Smith: In response to the City's letter dated January 8, 2009 regarding change orders and their acceptance / denial we offer the following regarding the water services encountered on the project to date. NTC will agree to the creation of an item for the investigation and repair of existing water services in the amount of $ 700 per each. To date we have encountered 5 EA of these existing water services not shown on the plans that have been repaired and re- installed. Please forward our request for $ 3,500 for 5 EA water service repairs to the City for approval. NTC requests 3 calendar days be added to our contract for this work. Please let me know if you have any questions regarding this matter. Respectfully Submitted, Zach Fusilier Vice President T H E C I T Y O F COFFE LL 1� Q January 8, 2009 Lance Smith Tiseo Paving Company P.O. Box 270040 Dallas, Texas 78019 RE: Coppell Road ST 00 -03 Change order Request Dear Mr. Smith: The City of Coppell has received and reviewed your requested change orders dated December 31, 2008. We concur with the following changes, and will begin processing a change order: 1. Storm sewer modification at Robertson Pools. $6,464.70 2. Cut and plug 8" water line in three locations. $3,052.50 3. 4" water service to Golden Triangle. $4,348.30 4. Temporary sidewalk to maintain pedestrian access to Wilson Elementary. $3,850.00 This will result in a net increase to the contract in the amount of $17,715.50. We find the balance of the claims to be without merit. The claims associated with utility conflicts that do not result in substantial changes to the alignment or depth of the facilities to be constructed, or that do not result in the construction of any additional items (i.e., support structures) is not compensable. If you need further assistance, please contact me. Sincerely, Keith Marvin, P.E. Project Engineer Phone: (972)304 -3681 Fax: (972)304 -3570 255 PARKWAY * P.O.BOX 9478* COPPELL TX 75019 * TEL 972/462 0022 * FAX 972/304 3673 PAVING COMPANY P.O. Box 270040 Dallas, Texas 75227 -0040 Telephone (972) 289 -0723 Fax (972) 216 -5637 December 31, 2008 Keith Marvin, P.E. City of Coppell 255 Parkway Coppell, Texas 78019 Re: Coppell Road ST 00 -03 Temporary Sidewalk Mr. Marvin, Please see the attached request for additional work. We have attached a breakdown from North Texas Contracting for your review. An additional 10% for Tiseo Paving Co. is requested below. NTC $3,500.00 TISEO10% 350.00 TOTAL $3,850.00 Sincerely Lance Smith Project Administrator Sdw&4" 1974 North Texas Contracting, Inc. Jab Name: COPPELL ROAD Location: COPPELL, TX Bid Date: 6- Mar -08 Bid Time: 2:00 PM EXCAVATE / GRADE FOR SIDEWALK 4" # 10 CHAT WALKING PATH TOTAL CHANGE AMOUNT TOTAL ADDED DAYS FOR CHANGE 12/30/2008 1:36 PM Qty Unit ►FFIC 1 LS 4 LD $ 3,500.00 2 CAL Unit 0.00 0.00 500.00 500.00 750.00 3,000.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 PAVING COMPANY P.O. Box 270040 Dallas, Texas 75227 -0040 Telephone (972) 289 -0723 Fax (972) 216 -5637 December 31, 2008 Keith Marvin, P.E. City of Coppell 255 Parkway Coppell, Texas 78019 Re: Coppell Road ST 00 -03 Trailer Park 4" Water Service Mr. Marvin, Please see the attached request for additional work. We have attached a breakdown from North Texas Contracting for your review. An additional 10% for Tiseo Paving Co. is requested below. NTC $3,953.00 TISEO10% 395.30 TOTAL $4,348.30 Sincerely Lance Smith Project Administrator 54t4df4" 1974 North Texas Contracting, Inc 4999 Keller Haslet Road Keller, Texas 76248 817 - 430 -9500 / (F) 817 - 430 -9207 Date: September 8, 2008 Attn: lance Smith Tiseo Paving Company Coppell Road Reconstruction Re: Differing Conditions Onsite Mr. Smith: NTC encountered an existing 4" water service that serves the existing trailer park on the West side of Coppeli Road just North of Ruby. Per the onsite decision of the City's inspector, the 4" water service was replaced from the tie in point to the new main. A new 4" valve was also installed in this area to regulate flow to the Trailer Park if required. Please see the attached change order pricing for the cost incurred by our firm relating to this issue. Please review and forward to the City as soon as possible. I have attached a breakdown of our cost in a time and material format. Respectfully Subm' , Zach Fusilier Vice President INSTALL 4" VALVE, CUT IN TEE AND RE- CONNECT EX. 4" SERVICE t TRAILER PARK COPPELL ROAD CITY OF COPPELL 1 TISEO PAVING NORTH TEXAS CONTRACTING NTC LABOR (5 MAN CREW FOR 10 HOUR DAY 1112 DAY REQ'D FOR WORK) REGULAR REGULAR OT OVERTIME TOTAL HOURS RATES HOURS RATES LABOR CHARGED CHARGED ADDED AMOUNT SUPERINTENDENT (50%) 2.5 $ 33.75 0 $ 50.63 $ $4.38 FOREMAN 5.0 $ 25.50 0 $ 38.25 S 127.50 OPERATOR ( 2) 10.0 $ 16.00 0 $ 24.00 $ 160.00 PIPE LAYER (2) 10.0 $ 14.00 0 $ 21.00 $ 140.00 PIPE HELPER (2) 10.0 $ 12.50 0 $ 18.75 $ 125.00 SUBTOTAL LABOR $ GUAM EQUIPMENT SUPERVISORS TRUCK MR 2.5 $ 9.08 $ 22.70 FOREMANS TRUCK MR 5 $ 9.08 $ 45.40 TRACK EXCAVATOR MR 5 $ 93.65 $ 468.25 CASE 580 MR 0 $ 63.65 $ - LOADER 2YD MR 5 S 81.22 $ 405.10 SKID STEER MR 0 $ 54.93 $ - GENERATOR MR 0 S 24.58 $ - COMPACTOR ( RIDE ON 54 ") MR 5 $ 28.61 $ 143.05 ROAD PLATE RENTAL MR 0 $ 17.00 $ - DAILY SAFETY ITEMS/ PPE I CONSUMABLES MR 5 $ 7.50 $ 37.50 SUBTOTAL EQUIPMENT $ 1,123.00 MATERIALS a SUBCONTRACTORS UNIT QUANTITY UNIT PRICE TOTAL C GATE VALVE EA 1 $ 315.00 S 315.00 12' X 4" TEE EA 1 $ 208.00 S 208.00 4" DR -14 CL -200 PVC LF 20 3 8.25 S 125.00 12" MEGALUG RESTRAINER EA 2 S 86.00 S 192.00 4" MEGALUG RESTRAINER EA 3 $ 49.00 S 147.00 THRUST BLOCKING EA 2 $ 125.00 S 250.00 VALVE STACK Wl LID EA 1 $ 75.00 $ 75.00 EMBEDMENT LF 20 $ 4.00 $ 80.00 SUBTOTAL MATERIALS 8 SUBS $ 1,392.00 TOTALS TOTAL SUB 3 MATL COSTS LS 1 $ 1,392.00 S 1,392.00 TOTAL EQUIPMENT LS 1 $ 1,123.00 $ 1,123.00 TOTAL LABOR LS 1 $ 636.88 $ 636.88 TOTAL NTC COST $ 3,151.80 SURMN ON LABOR 7i DA25 $ 636.86 $ 270.67 OVERHEAD % 0.1 $ 3,422.55 $ 342.25 PROFIT % 0.08 S 3,764.80 $ 186.24 NTC BONDING ADJUSTMENT % 0 $ 3,963.04 S - TOTAL: $ 3,953.04 SAY: $ 3,933.00 NOTES PLEASE ADD ONE DAY TO CONTRACT FOR THIS WORK PAVING COMPANY P.O. Box 270040 Dallas, Texas 75227 -0040 Telephone (972) 289 -0723 Fax (972) 216 -5637 December 31, 2008 Keith Marvin, P.E. City of Coppell 255 Parkway Coppell, Texas 78019 Re: Coppell Road ST 00 -03 Cut & Plug 8" Water Service Mr. Marvin, Please see the attached request for additional work. We have attached a breakdown from North Texas Contracting for your review. An additional 10% for Tiseo Paving Co. is requested below. NTC $2,775.00 TISEO10% 277.50 TOTAL $3,052.50 Sincerely Lance Smith Project Administrator 64AW44d 1974 North Texas Contracting, Inc. Job Name: COPPELL ROAD Location: COPPELL, TX Bid Date: 6 -Mar -08 Bid Time: 2:00 PM 10102 CUT & PLUG EXISTING 8" WATER TOTAL NET CHANGE AMOUNT TOTAL ADDED DAYS FOR CHANGE 12/30/2008 1:26 PM Unit I Unit 3 EA 2,775.00 2 CAL 0.00 0.00 925.00 2,776.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 PAVING COMPANY P.O. Box 270040 Dallas, Texas 75227 -0040 Telephone (972) 289 -0723 Fax (972) 216 -5637 December 31, 2008 Keith Marvin, P.E. City of Coppell 255 Parkway Coppell, Texas 78019 Re: Coppell Road ST 00 -03 Existing Storm Sewer at Robertson's Pools Mr. Marvin, Please see the attached request for additional work. We have attached a breakdown from North Texas Contracting for your review. An additional 10% for Tiseo Paving Co. is requested below. NTC $5,877.00 TISEO10% 587.70 TOTAL $6,464.70 Sincerely Lance Smith Project Administrator 54M&aked 1974 North Texas Contracting, Inc 4999 Keller Haslet Road Keller, Texas 76248 817. 430 -9500 / (F) 817- 430 -9207 Date: July 14, 2008 Attn: lance Smith Tiseo Paving Company Coppell Road Reconstruction Re: Differing Conditions Onsite Mr. Smith: The City has requested installation of additional storm sewer items to accommodate an existing storm water system on Coppell Road immediately North of Robertson's Pools. The City has requested a 36" grate inlet, three 8" tee outlets and the connection to three existing storm water inlets including 8" pipe to facilitate the connections. Please see the attached breakdown of costs and the material prices for validity. Please review and forward accordingly. r CJ,-i (,--4 Res ct #uliy Subm ed, Zach Fusilier Vice President ej ADD 3 - 24" X 8" TEES WITH CONNECTIONS TO EX. INLETS 3 40 LF 8" PIPE COPPELL ROAD CITY OF COPPELL I TISEO PAVING NORTH TEXAS CONTRACTING NTC LABOR 116 MAN CREW FOR 10 HOUR DAY 1112 DAY REWD FOR WORK) SUPERINTENDENT (50%) FOREMAN OPERATOR(2) PIPE LAYER (2 ) PIPE HELPER (2 ) EQUIPMENT SUPERVISORS TRUCK FOREMANSTRUCK TRACK EXCAVATOR CASE S90 LOADER2YD SKID STEER GENERATOR COMPACTOR ( RIDE ON w) ROAD PLATE RENTAL DAILY SAFETY ITEMS/ PPE I CONSUMABLES MATERIALS 6 SUBCONTRACTORS REGULAR REGULAR HOURS RATES CHARGED RATES 2.5 $ 33.75 5.0 $ 25.50 10.0 $ 16.00 10.0 $ 14.00 10.0 $ 12.50 OT OVERTIME TOTAL HOURS $ 22.70 RATES LABOR CHARGED 9.08 ADDED AMOUNT 0 $ 50.63 S 84.38 0 $ 38.25 S 127.50 0 $ 24.00 $ 160.00 0 $ 21.00 $ 140.00 0 $ 18.75 S 125.00 SUBTOTAL LABOR $ 886.88 HR 2.5 $ 9.08 $ 22.70 HR 5 3 9.08 $ 45.40 HR 5 $ 93.65 $ 468.25 HR 0 $ 63.65 $ - HR 5 S 81.22 $ 406.10 HR 0 S 54.93 $ - HR 0 $ 24.58 S - HR 5 S 28.61 $ 143.05 HR 0 $ 17.00 $ - HR 5 $ 7.50 $ 37.50 SUBTOTAL EQUIPMENT $ 1,123.00 UNIT G&VWTIIY UNIT PRICE TOTAL 24"X W HDPE TEE / WYE FITTING EA 3 $ $50.00 $ 11950.00 24" HOPE SPLIT COUPLING EA 6 $ 120.00 $ 720.00 6` HDPE SPLIT COUPLINGS EA 3 $ 16.00 $ 46.00 SUBTOTAL MATERIALS & SUBS S 3,058.00 TOTALS TOTAL SUB & MATL COSTS LS 1 $ 3,058.00 $ 3,056.00 TOTAL EQUIPMENT LS 1 $ 1,123.00 $ 1,123.00 TOTAL LABOR LS 1 $ 636.88 $ 636.88 TOTAL NTC COST $ 4.817,88 BURDEN ON LABOR % 0.425 $ 636.88 $ 270.67 OVERHEAD % 0.1 $ 5.088.66 $ 608.66 PROFIT % 0.08 $ 5.697.40 $ 279.87 NTC BONDING ADJUSTMENT % 0 $ 5,877.27 $ - TOTAL: $ $1677.27 SAY: $ 5,877.00 Zach Fusilier From: Ryan.Moore@Ferguson.com Sent: Wednesday, July D9,2008 7:55 PM To: zfusilier@ntexcon.com Subject: FW: Email Bid# B112875 From: Ryan Moore - 788 DALLASWW [ mailto:ryan.moore0ferguson.com] Sent: Wednesday, July 09, 2008 7:53 PM To: Moore, Ryan C [Ferguson] - 0788 DALLASWW Subject: Email Bid# 6112875 Price Quotation # B I MS Ferguson Waterworks #788 2650 S Pipeline Road Euless, TX 76040 Phone: 817- 267 -3980 Fax: 917-267-3912 Bid No.......: 9112875 Bid Date..: 07/09/08 Quoted By: RCM Customer.: NORTH TEXAS CONTRACTING INC COPPELL ROAD 4999 KELLER HASLET RD KELLER, TX 76248 Cust PO#- -. Cast Phone: 817430 -9500 Terms..._.- NET 10TH PROX Ship To.......: NORTH TEXAS CONTRACTING INC COPPELL ROAD 4999 KELLER HASLET RD KELLER, TX 76248 .lob Name.: COPPELL ROAD Item Description Quantity Net Priee UM Total ' A2462AN 24X8 N 12 COR TEE 3 650.000 EA 1950.00 "A2412AA 'j 24 N12 HDPE SPLT COUP 6 120.000 EA 720.00 A0813AA ' 8 N 12 HDPE BOE SNAP COUP 3 16.000 EA 48.00 A08150020IB BX20 Tfi2 PROLINK ST SLD HDPE PIPE 40 8.300 FT 340.00 j GCBMMM 3X3X3 CATG 4 BASIN 1 1575.000 EA 1575.00 LOY'., Net Total: 4633.00 Tax: 382.23 Total: 5015.23 �8 Quoted prices are based upon receipt of the total quantity for immediate shipment (48 hours SHIPMENTS BEYOND 48 HOURS SHALL BE AT THE PRICE IN EFFECT AT TIME OF SHIPMENT. Quotations are offered contingent upon the Buyer's acceptance of Seller's terms and conditions. Seller objects to all other terms and conditions. Seller not responsible for delays or lack of product due to causes beyond our control. Purchaser's sole warranties, if any, are those provided by the manufacturer. SELLER DISCLAIMS ALL EXPRESS OR IMPLIED WARRANTIES, INCLUDING ALL IMPLIED WARRANTIES OF MERCHANTABILITY AND FITNESS OR FITNESS FOR A PARTICULAR PURPOSE, IN NO SPECIA EVENT WILL SELLER BE LIABLE FOR ANY INCIDENTAL, PUNITIVE, L OR CONSEQUENTIAL DAMAGES ARISING DIRECTLY OR INDIRECTLY FROM THE OPERATION OR USE OF THE PRODUCT. SELLER'S LIABILITY, IF ANY, SHALL BE LIMITED TO THE NET SALES PRICE RECEIVED BY SELLER. Complete Terms and Conditions are available upon request or can be viewed on the web at www.ferauson com/saIts- terms.html.