SS9901-CS001205Agenda City of Coppell DeForest Wastewater Lift Station and Force Main Improvements TC&B Job No. 15-30041-001 Progress Meeting No. 1 December 5, 2000 @ 2:30pm 1. Wastewater Flow Evaluation Report. 2. Lift Station Improvement Alternatives: LS-1 New Lift Station. LS-2 Temporary lift station during renovation of existing lift station. LS-3 Renovate existing lift station while it is in operation. 3. Odor Control Research Carbon Canister Adsorption System. Traditional Carbon Adsorption System. Biofilters. 4. Force Main Alternatives. FM-I Run parallel 24" force main to Samuel Street and parallel the existing 21" gravity sewer and 27" gravity sewer to Sandy Lake Lift Station with an additional 21" and 27" gravity sewer. FM-2 New 30" force main to Samuel Sand and parallel the existing 21" gravity sewer and 27" gravity sewer to Sandy Lake Lift Station with an additional 21" and 27" gravity sewer as in FM-1. FM-3 New 30" force main in MacArthur Boulevard and parallel the existing 27" gravity sewer to the Sandy Lake Lift Station with an additional 27" gravity sewer. FM-4 New 30" force main in MacArthur Boulevard to the existing Sandy Lake Lift Station wet well. FM-5 New 30" force main in MacArthur Boulevard to the existing force main out of the existing Sandy Lake Lift Station. 5. Project Schedule 6. Schedule Site Visit 6. Additional Items ,P:\Coppell\OeForest Lift Stotlon\DCN\ALT_LS_I.DCN 12/05/00 {.l;;; .... EXIST, 24"INTERCEPTOR SEWER C) EXIST. 16" RAW SEWAGE M~N TEMPORARY LFT STATION MODIFY EXISTING LFT STATION ICONNECT TO EXISTING FORCE MAIN DEFOREST ROAD N SCALE FEET 0 30 60 ALTERNATIVE LS-2 CITY OF COPPELL DEFOREST WASTEWATER LIFT STATION & FORCE blAIN IblPROVEblENTS Turner Collie ~Braden Inc. ENGINEERS · PLANNERS · PROJECT MANAGERS MODIFY EXISTING LIFT STATION IN PHASESI DEFOREST ROAD N SCALE IN FEET 0 30 60 ALTERNATIVE CITY OF COPPELL DEFOREST WAST£WATER LIFT STATION & FORCE MAIN IIIIPROVEt,,IEIfTS Turner Collie ~'Braden Inc. ENGINEERS · PLANNERS · PROJECT MANAG[RS .L EXISTING 16" & NEW 24" FORCE MAIN FORCE MAIN 21" GRAVI f SEWER LLEL 21 ;RAVITY SANDY LAKE ROAD EXISTING 27" GRAVITY SEWER SEWER & NEW PARALLEL 27" GRAVITY 'EW~ER LIFT STA~,~. ALTERNATIVE FM-I CITY OF COPPELL DEFOREST WASTEWATER LIFT STATION & FORCE MAIN IMPROVEMENTS Turner Collie ~Braden Inc. ENGINEERS · PLANNERS · PROJECT MANAGERS -J. -) NEW 30" FORCE MAIN 21" GRAVI SEWER _LEL 21"iGRAVITY EXISTING 27" GRAVITY SEWER SEWER & NEW PARALLEL 27" GRAVITY ~ WASTE¥/A-TE R LIFT STA'T.],O.N,. ALTERNATIVE FI~-~_ CITY OF COPPELL DEFOREST WASTEWATER LIFT STATION & FORCE WAIN IMPROVEI~ENT5 Turner Collie ~Braden Inc ENGINEERS * PLANNERS · PROJECT MANAGERS .L I NEW 30" FORCE MAIN SANDY LAKE ROAD LIFT EXISTING 27" GRAVITY SEWER 1 & NEW PARALLEL 27" GRAVITY SEWER J rER ALTERNATIVE Flit-3 CITY OF COPPELL DEFOREST WASTEWATER LIFT STATION & FORCE IIIAIN IIitPROVEIdENTS Turner Collie ~'Braden Inc ENGINEERS · PLANNERS · PROJECT MANAGERS J_ SANDY LAKE ROAD F"J'"'T'"T ~"i"' i~ NEW 30" FORCE MAINI E'I~ATER ALTERNATIVE FI~-4 CITY OF COPPELL DEFOREST WASTEWATER LIFT STATION & FORCE MAIN IltPROVEJtENT5 Turner Collie ~Braden Inc. ENGINEERS · PLANNERS · PROJECT MANAGERS I TNTTITr~ [\ \ .~x x ii ' SANDY LAKE ROAD ~ ~td ~__ s, I L~...LM ...... ~_;ii_.ii~ ~--] i~.i~i!!.L~..Li~ i! l/ ~ NEW 30" FORCE MAIN] i__ LIFT STA TIE INTO EXISTING 30" F.M. TO TRA ALTERNATIVE FtZ-5 CITY OF COPPELL DEFOREST WASTEWATER LIFT STATION & FORCE MAIN IMPROVEMENTS Turner Collie ~Braden Inc. ENGIN[ERS · PLANNERS · PROJECT MANAGERS 4000 4000 Feet ~',,,,~.