PZ Staff Report
ITEM #6
Page 1 of 3
CITY OF COPPELL
PLANNING DEPARTMENT
STAFF REPORT
CASE No.: PD-311R-LI – AstraZeneca Tank Farm
P&Z HEARING DATE: November 16, 2023
C.C. HEARING DATE: December 12, 2023
STAFF REP.: Mary Paron-Boswell, AICP Senior Planner
LOCATION: 508 Wrangler Dr
SIZE OF AREA: 8.015 acres
CURRENT ZONING: PD-311-LI (Planned Development- 311- Light Industrial)
REQUEST: PD-311-LI (Planned Development- 311- Light Industrial) to PD-311R-LI (Planned
Development- 311 Revised- Light Industrial) to allow an overhead tank line from
the accessory tank farm structure to the existing office warehouse on approximately
8 acres on a portion of Lot 3R1, Block 8 located at 508 Wrangler Drive, at the
request of ML Realty on behalf of AstraZeneca, being represented by Allen Hager,
DPR Construction.
APPLICANT: Owner: Developer:
ML Realty Partners DPR Construction
5950 Berkshire Lane 310 Comal St.
Suite 900 Suite 300
Dallas, TX 75225 Austin, TX 78702
972-265-0138 617-386-6911
rrainwater@holtlunsford.com allenh@dpr.com
Applicant: Engineering:
AstraZeneca DPS
508 Wrangler Dr. 959 Concord St. #100
Coppell, TX 75019 Framingham, MA 01701
508-532-6760
Aidan.Coleman@dpsgropglobal.com
HISTORY: AstraZeneca is a pharmaceutical company located on Wrangler Drive. This
particular location produces one product – Lokelma, which is a prescription
medicine that is used to treat adults with Hyperkalemia. Hyperkalemia is a
condition where the potassium levels in a person’s blood are too high and can lead
to potentially life-threatening health issues, especially for those with chronic kidney
disease (CKD). CKD affects approximately 200 million people worldwide. It is the
ITEM #6
Page 2 of 3
only place where this drug is produced worldwide. Currently they have six (6)
manufacturing lines and are proposing to expand it to eight (8). Staff has previously
approved administratively a parking expansion, minor building expansion and
utility yard. This new building addition requires a PD since they are asking for a
parking variance. Earlier this year, Council approved the addition of a tank farm
for the site with lines going underground from the tank farm to the main building.
HISTORIC COMMENT: This property has no noted historical significance.
TRANSPORTATION: Wrangler is a four-lane undivided street.
SURROUNDING LAND USE & ZONING:
North: Office Warehouse - Light Industrial (LI)
South: Office Warehouse (LI) & Coppell 9th Grade Center (PD-289R-C)
East: Light Industrial (LI)
West: Vacant - Light Industrial (LI) -9)
COMPREHENSIVE PLAN:
Coppell 2030, A Comprehensive Master Plan, shows this property as appropriate
for Industrial Special District.
DISCUSSION: In September of this year, AstraZeneca brought forth a request to construct a tank
farm structure on this site that would allow them to expand their production to meet
the increasing demand for their Lokelma drug that is only manufactured at this
facility. Since this was approved, they have started detailed construction
engineering and are now requesting a change in the method of moving the
chemicals from the tank farm to the building. The original plan showed the lines
for the chemicals to go underground from the tank farm into the adjacent building.
What they are now requesting is to allow the chemicals to travel in an above ground
pipe rack that will take the materials from the tank farm to the building.
Pipe Rack
The proposed pipe rack system would be exterior to the building and the enclosure
will span between the tank farm and the existing building. The top of the pipe rack
will be installed between the parapet line and the tank farm building roof line, to
not add additional elevation to the tank farm design. The enclosure shall have
removable panels to allow for maintenance and inspection access to the enclosed
components (piping, heat trace cabling and instrumentation, leak detection
instrumentation, exhaust fans, etc.). The rack will be designed to withstand wind
speeds of 120 mph, with wind exposure classification C provided by a steel
structural frame. The columns supporting the pipe rack will be protected with a
concrete pad at the base that is 3-ft high as well as safety guardrails that meet safety
requirements. The columns will also be in the landscaped areas which provides
further segregation and protection from the parking lot traffic flow. The pipe rack
is proposed to be 7’9” tall and 12’5” wide and elevated so that the bottom of the
pipe rack would be approximately 23-ft from the ground, approximately 10-ft
ITEM #6
Page 3 of 3
higher than the top of an 18-wheeler. A benefit of the pipe rack system versus the
underground lines is the accessibility to do maintenance, inspections and repairs if
necessary, versus the underground pipe vault which would need to be enclosed and
sealed and would require sections of the parking lot to be dug up if they needed to
access the underground pipe vault, being more disruptive to the overall operation
of the site.
Site Plan
This site plan still shows two phases, the first is the construction of a new building
for the proposed tank farm and the second is the proposed small 3,000-sf expansion
at the rear of the existing building if deemed necessary. The PD condition for
parking remains, with one slight deviation, the overhead pipe rack system will be
installed in a landscape island with bollards in place to allow separation from the
parking area, taking up two spaces. If phase 2 is constructed, they would still have
200 spaces in total, as previously approved. The pipe rack would be located
towards the back half of the site approximately 517-ft from Wrangler Drive and
painted to match the building.
Staff is in support of the request and recommends approval.
RECOMMENDATION TO THE PLANNING AND ZONING COMMISSION:
Staff is recommending APPROVAL of the request subject to the following conditions:
1. There may be additional comments during detailed engineering plan review.
2. PD Conditions:
a. To paint the pipe rack to match the building.
ALTERNATIVES:
1. Approval of the request
2. Denial of the request
3. Modification of the request
4. Take the case under advisement to a future date
ATTACHMENTS:
1. Detail Site Plan
2. Pipe Rack Design & Renderings
3. Landscape Plan
4. Narrative
5. Parking Memo