Staff Report PDITEM # 8
Page 1 of 2
CITY OF COPPELL
PLANNING DEPARTMENT
STAFF REPORT
CASE NO.: PD-289R-C, Coppell 9th Grade Campus Locker Room Building
P&Z HEARING DATE: March 17, 2022
C.C. HEARING DATE:April 12, 2022
STAFF REP.: Mary Paron-Boswell, Senior Planner
LOCATION: 1301 Wrangler Circle
SIZE OF AREA: 51.59 acres of property
CURRENT ZONING: PD-289-C (Planned Development 289-Commercial)
REQUEST: A zoning change request to PD-289R-C, (Planned Development-289-Revised -
Commercial), to revise the Planned Development to allow for a 2,800 square-foot
locker room.
APPLICANT: Owner: Engineer:
CISD Glenn Engineering
Dennis Womack Robert Howman
200 S. Denton Tap 4500 Fuller Dr. #220
Coppell, Texas 75019 Irving, Texas 75038
(214) 496-6000 (972) 989-2174
dwomack@coppellisd.com rahowman@glennengineering.com
HISTORY: In June 2001, Council approved a Site Plan to permit construction of a service
center with bus/maintenance vehicle parking, several building additions,
reconstruction of the concession building, and re-paving of the asphalt parking lot.
In 2017, Council approved a Planned Development to convert the middle school to
the Coppell 9th Grade Campus.
HISTORIC COMMENT: There is no historic significance associated with this property.
TRANSPORTATION: Wrangler Road is a C4U four-lane undivided roadway built within a 65-foot right-
of-way (narrowing to 60 feet to the west).
SURROUNDING LAND USE & ZONING:
North – Office/Warehouse; LI (Light Industrial)
South – Office/Warehouse; LI (Light Industrial)
East – Office & Warehouse Uses; LI (Light Industrial)
West – Office/Warehouse; LI (Light Industrial)
ITEM # 8
Page 2 of 2
COMPREHENSIVE PLAN: Coppell 2030, A Comprehensive Master Plan, designates this area as Industrial
Special District with school use noted.
DISCUSSION: The Coppell Independent School District is requesting to update and revise the
Detail Planned Development to reflect existing and proposed changes to the site.
This application is seeking approval to construct a 2,800 square-foot new locker
room to be used for the existing baseball and softball fields. The building will also
have storage space and a changeroom for referees. The building will be located
close to the ballfield’s existing concession stand, maintenance building, and
existing parking lot. There will be some sidewalks added around the building, along
the parking area and to the concession stand. There are no proposed changes in the
parking area. There are 629 spaces currently on-site. There are no landscaping
changes proposed.
Elevations & Signage:
As depicted on Elevation Sheet, the proposed locker room building is 18-feet 10-in
height. The primary color of the building will be “Pink Ruby” split face with two
horizontal lines in an “Austin Limestone” split face to match the existing buildings
on-site. The roof will be a charcoal grey standing seam metal roof. Signage on the
building will consist of the Coppell Cowboy star logo and “COPPELL ISD
BASEBALL AND SOFTBALL COMPLEX, written in 18-inch cast aluminum
letters, brushed stainless. Signage for the building will be approximately 67-sf. A
sign permit will be required for the signage.
Staff is recommending approval subject to the conditions outlined below.
RECOMMENDATION TO THE PLANNING AND ZONING COMMISSION:
Staff is recommending APPROVAL of this request subject to the following conditions:
1. The signage be approved as shown.
2. A sign permit will be required.
ALTERNATIVES:
1. Recommend approval of the request
2. Recommend disapproval of the request
3. Recommend modification of the request
4. Take under advisement for reconsideration at a later date
ATTACHMENTS:
1. Overall Site Plan
2. Detail Site Plan
3. Demolition Plan
4. Elevation & Signage Plan