April 7, 1987
Mr. Tom R~tledge
Teague Nail and Perkins,
915 FlorenCe Street
Ft. Worth, ~X 76102
Re: Coppell High School
Inc.
Dear Mr. Rutledge:
Pursuant to our April 6, 1987, telephone conversation, we
appreciate the information you provided us on the status of the
Coppell High School plans.
It is our understanding that the preliminary plat and plans have
been approved by P & Z and Council and that final plat has not
been submitted as of this point in time.
Based on the tight schedule everyone was working under, you
requested that the plans for the drainage and also the water and
sewer be reviewed and approved prior to final plat submittal.
The intention was to allow construction of these items, with City
approval, and then proceed with the final platting process at a
later date.
In order to facilitate the expeditious review of the plans, we
had requested you forward copies of plans to us for review at the
same time you submitted them to the City. The plans sent to us
on February 27, 1987, were held longer than normal, due to the
fact that you stated that "City comments for public drainage
improvements were being revised," and erroneously we anticipated
receiving an updated set to be reviewed. There was some
miscommunication apparently, and your March 26, 1987, letter to
SHWC, Inc., which we were copied, stated you received no response
to your February 27 submittals. AT that time, seeing the urgency
of the matter, we reviewed the plans and returned them to you on
March 30, 1987. From the information you provided, we understood
the city was reviewing the plans also.
You indicated that negotiations with' Univest are continuing on
the drainage improvements and that you are waiting on the
agreement to be finalized prior to resubmittal of the final
plans. You also indicated that: the land is under condemnation
proceedings and a court date is set as May 18, 1987; you would
like to proceed with construction of drainage and utilities as
17103 Preston Road · Suite 100 · LB 118 · Dallas, Texas. _48 · Phone 214/248-4900
close to May 20, 1987, as possible; and, you may possibly be
resubmitting the final plat within a short period of time to the
City for inclusion on P & Z and Council agendas.
We ask that to keep the City fully informed of any submittals,
requests for variances, etc., and on any future submittals you
submit the required information through the proper channels of
the City. We will be a part of the City staff that will review
your plans from an engineering standpoint. We will be involved
with review on the staff level, under the direction of the City
Manager. We would anticipate that other members of the staff,
such as inspection, planning, engineering, public works, police
and fire, etc., would have valuable input during the review
process.
Once you have incorporated all the comments, please submit six
final sets to our office in order that they can be stamped for
approval.
We apologize for any inconvenience or delays that we may have
caused due to communications, or lack thereof. If we can be of
any assistance, please do not hesitate to contact us.