Cpl Greens P1/FP-AG 970909 AGENDA II.QUEST FORM
~j~ CI'' CO0~CI~ MEE?ING: September 9, 1997
Consider approval of the CopPell. Greens, Phase One, Final Plat and Site
Plan, to allow the development of 120 lOts of the proposed 217-1ot
residential subdivision located along the west side of Denton Tap Road,
approximately 800 feet north of the 121 Bypass.
SUBMITTED BY: Gary L. Sieb
TI~: Director of Planning and Coz~unity Services
STAFF RECOt~ENDS: Al~roval X Denial
STAFF COte~NTS:
Date of P&Z Meeting: August 21, 1997
Decision of P&Z Commission: Approved (6-0) with Commissioners Redford,
Cruse, Lowry, McCaffrey, DeFilippo and Stewart voting in favor. None
opposed. Commissioner Jones resigned from the Commission.
Approval subject to Engineering comments (attached to Staff Report) and the
following recommended conditions:
1. The property owner must resolve which electric company will serve
the subdivision.
2. The City will not accept right-of-way dedication on Denton Tap
Road until the Texas-New Mexico power lines are either removed or
placed underground.
3. The TU Electric power-lines must be placed underground.
4. Eliminate the use of the term zero side of a home from the
homeowners association document.
5. The homeowners association document must be approved by the City
Attorney.
6. Substitute plant materials listed on the City's approved plant
palette for the following plant materials:
a. Soft-leaf Yucca
b. Red Yucca
c. Virginia Creeper
d. Blue Rug Juniper BY
CITY COC CIk
CITY OF COPPELL
PLANNING DEPARTMENT
STAFF REPORT
CASE: COPPELL GREENS, PHASE ONE, FINAL
PLAT AND SITE PLAN
P & Z HEARING DATE: August 21, 1997
C.C. HEARING DATE: September 9, 1997
LOCATION: Along the west side of Denton Tap Road, approximately 800 feet
north of the 121 Bypass.
SIZE OF AREA: 35.882 acres; 120 residential lots
CURRENT ZONING: PD-SF-7
REQUEST: Development of 120 lots of the proposed 217-1ot residential
subdivision.
APPLICANT: Owner: Engineer:
Argus Development Co. Dowdey, Anderson & Associates, Inc.
6400 Uptown Blvd. NE, Ste. 200W 5225 Village Creek Drive, Ste. 200
Alburquerque, NM 87110 Plano, TX 75093
(505) 889-3061 (972) 931-0694
HISTORY: On June 11, 1996 the Coppell City Council approved the rezoning of this
property from Light Industrial and Highway Commercial zoning to a residential
planned development. The preliminary plat was approved on October 8, 1996.
City Council did not grant the Planning and Zoning Commission to be the
authority responsible for the approval of the Final Plat for Coppell Greens.
TRANSPORTATION: Denton Tap Road is shown on the thoroughfare plan as a P6D,
six-lane divided roadway within a 110 foot wide right-of-way.
The road currently consists of a 2-lane asphalt section within a 90'
to 100' wide right-of-way. The 121 Bypass will be built to
freeway standards with access roads in 450 feet of right-of-way.
Item # 14
SURROUNDING LAND USE & ZONING:
North - vacant; City of Lewisville "LI" Light Industrial
South - vacant; "HC" Highway Commercial
East - vacant; City of Lewisville "LI" Light Industrial & "GB" General
Business
West - vacant; "LI" Light Industrial
COMPREHENSIVE PLAN: The Comprehensive Plan shows the property suitable for
medium-density residential use.
DISCUSSION: The submitted final plat is showing a slight variation from the initial
approval, with regards to lot layout, lot quantity, configuration of common
areas, and the addition of Dalmalley Lane. The developer will plat a total
of 222 residential lots, of which 120 are being platted this first phase.
The approved planned development showed a total of 226 residential lots
for this subdivision. As long as the developer does not exceed the total
number of lots approved for the planned development and the
modifications are minor, staff is comfortable accepting the plat. The only
notable deviation from the approved planned development pertains to the
subdivision screening wall and entry feature. The ordinance for Coppell
Greens shows a serpentine stone wall and a distinctive subdivision entry
sign with a water feature. The submitted plan only shows a typical
landscaped subdivision entry considerably different from what was
approved. Staff is of the opinion that either the existing landscape plans
needs to be modified to reflect what was approved or the planned
development should be amended.
Staff has a major concern that the developer has not made a determination
with regards to which electric company will serve this residential
subdivision. Currently, along the eastern side of Denton Tap Road right-
of-way Denton County Electric Cooperative maintains a three phase
overhead lines and along the western side of the Denton Tap Road right-
of-way TU Electric operates single phase overhead power lines. Until
recently, the Texas-New Mexico Power Company had single phase
overhead power lines paralleling those of TU Electric. In the hopes of
gaining the Vistas of Coppell account, the Texas-New Mexico Power
Company upgraded its lines from single phase to three-phase and
relocated these further west at the edge of the future Denton Tap Road
right-of-way. Currently, this three phase line is located on Coppell
Greens property without a proper easement. The Texas-New Mexico
Power Company did not obtain the Vistas of Coppell account, therefore,
they will not be serving the Coppell area. To further complicate matters,
the City does not have a franchise agreement with either Texas-New
Mexico Power Company or Denton County Electric Cooperative. From
staff perspective, the City should not accept right-of-way dedication on
Item # 14
Denton Tap Road until the Texas-New Mexico's power lines are removed
or placed underground. As to the TU Electric's power lines, they too
should be placed underground, which TU has agreed to do.
An issue raised during the Development Review process pertained to the
cul-de-sac lots, especially at Turnberry Lane. Staff was of the opinion
that the lots had too little frontage to install a 12 foot wide driveway,
along with the necessary water meters, GTE pedestals, TU boxes, street
lights and fire hydrants. The applicant has submitted a detail plan
showing this information. Upon review, staff has determined that placing
the houses further back on the lot as an attempt to increase the number of
the lots around the cul-de-sac is not a workable solution. The lengths of
the driveways are extended, thus increasing the total pavement coverage.
Staff is of the opinion that the cul-de-sac radius should be increased from
50 feet to 70 feet and a landscaped island be placed at the center. This
would increase the street frontage of each home, decrease the length of the
driveways, and provide more room in the front yard to accomodate
utilities.
RECOMMENDATION TO THE PLANNING AND ZONING COMMISSION:
Staff recommends approval of the final plat and site plan subject to the
following conditions being met:
1. Modify existing landscape plan to reflect what was approved with
the planned development or amend the planned development.
2. Provide a detail screening wall and subdivision entry sign
elevation.
3. The property owner must resolve which electric company will
serve the subdivision.
4. The City should not accept right-of-way dedication on Denton Tap
Road until the Texas-New Mexico power lines are either removed
or placed underground.
5. The TU Electric power lines must be placed underground.
6. Increase cul-de-sac radius on Turnberry lane from 50 feet to 70
feet and provide a landscape island at the center.
7. Eliminate the use of the term zero side of a home from the
homeowners association document.
8. The homeowners association document must be approved by the
City Attorney.
Item # 14
9. Substitute plant materials listed on the City's approved plant palette
for the following plant materials:
a. Soft-leaf Yucca
b. Red Yucca
c. Virginia Creeper
d. Blue Rug Juniper
10. Compliance with Engineering comments.
ALTERNATIVES: 1) Recommend approval of the request
2) Recommend disapproval of the request
3) Recommend modification of the request
4) Take under advisement for reconsideration at a later date.
ATTACHMENTS: 1) Final Plat
2) Landscape Plan
3) Turnberry Lane cul-de-sac sketch
4) Departmental Comments
Item # 14
DEVELOPMENT REVIEW COMM 2 819
ENGINEERING COMMENI
ITEM: Coppell Greens, P~e ~e, ~ ~ ~ S~e ~, ~ ~w
the ~e~pm~ of 120 ~ of ~e pm~sed 217-~t ~~
su~n ~ed ~ng the we~ ~ of ~n T~ R~,
~p~~~ 8~ fe~ north of the 121 ~s, ~ the ~e~ of
~w~, ~on ~ ~soc~es.
DRC DA~: J~y 31, 1~7 ~ Au~ 7, 1997
CO,ACT: M~ M~, P.E., ~~ ~ En~eer 0~3679)
COMMENT STA~S: v~r ~ vv ~n~ r ~VISED
AFTER P&Z
1. As per the comments made during the planned developmem process, there is an existing
pond on the property therefore the appropriate permits need to be filed with the federal
governmem i.e.E.P.A. 404 permit.
2. Appears it will be difficult to provide access to Lots 31-35 Block C on Turnberry. Please
provide additional detail.