Meadows P6/FP-CS 890628 PAUL S. UNZICKER, INC.
CONSULTING I:"' NGI N E ERS
8700 STEMMONS FREEWAY, SUITE 400
DALLAS, TEXAS 7S247
(214) 634-3300
June 28, 1989
Mr. Larry Davis
The City of Coppell
P.O. Box 478
Coppell, Texas 75019
Re:
Meadows Section Six - Phase One
Coppell, Texas
86062 0
Dear Mr. Davis:
We have revised the Final Plat and Engineering Plans for the referenced
development consistent with your review comments found on the returned markups.
The revisions to these plans can be found on the plan set submitted to you
during our meeting on June 26, 1989. In addition to the revisions made to this
plan set, the following should be noted regarding this project:
The City Council has requested that the Paving Improvements associated with
this project, especially in Samuel Boulevard, be completed prior to the
beginning of the new school year. This was requested during the Final Plat
process to ensure adequate safety and traffic flow around the elementary
school located on the west side of Samuel Boulevard.
Sidewalks are not required by City codes during Street Paving Improvements.
The sidewalks for those interior streets of this subdivision will be
constructed by the builders for each lot. The sidewalk in Samuel Boulevard
will be constructed by the developer after all Street Paving is completed;
the cost shared with St. Ann's Catholic Church. The church is also
responsible for the sidewalk on the south side of Woodmoore Drive. The
church is required to participate in this cost as requested by the City
Council during the Platting process of their development.
Be
A trench safety plan and geotechnical investigation was conducted by Alpha
Testing Service, Inc., especially for this project. A copy of the reports
was submitted to you under separate cover and has been included in the
Utility Contractors Contract Documents and Specifications.
A preconstruction meeting will be scheduled next week. I would appreciate
it very much if you would provide me with a list of all persons you wish to
attend. During this meeting, we will notify contractors of any changes to
the plans as originally approved, and of any concerns you wish to present
to them.
PAUL S. UNZICKER, P.E. DAVID M. SCHNURBUSCH, P.E.
President Vice President
Page 2
Mr. Larry Davis
June 28, 1989
I appreciate your comments regarding this plan set and look forward to working
with you during the construction phase of this development. If you have any
questions, please call.
Sincerely,
Project Manager
KRK: kc
Gordon Jones / D.T. Construction, Inc.
Jeff Hawkins / Pierce Lunsford, Inc.
Russell Doyle / City of Coppell
Kevin Pieffer / Ginn Inc.
Howard Pofford / City of Coppell