ParkW CC-1/FP-CS 900315 (2)Minutes of March 15, 1990
Planning & Zoning Commission
Page 3
Item 7:
Following discussion Commissioner Redford moved to approve Case
#ZC-524. Commissioner Gross seconded the motion: motion carried
(6-0) with Chairman Munsch and Commissioners Green, Gross,
Redford, Scott and Tunnell voting in favor of the motion.
pLATTING
Consider approval of a final plat for Meadows Addition, Section
6, Phase 2, located at the southeast corner of Parkway Boulevard
and Samuel Boulevard, at the request of Meadowglen Properties.
P&Z Coordinator Taryon Bowman introduced the item to the
Commission. Ms. Bowman stated this plat is actually Phase 2 of
the Meadows Addition, or Case #PD-105. If approved, this plat
will allow the construction of thirteen single-family structures
on 2.68 acres. She further stated that all DRC comments have
been addressed; therefore, staff has no objections to the plat.
Mr. Glen Hinckley was present to represent this item before the
Commission. He stated that all utilities are already in place,
and that this property should have been included with the final
plat with D.R. Horton's project directly adjacent to this
property. Mr. Hinckley stated that it was due to an oversight
that this property was not included.
Following discussion Commissioner Tunnell moved to approve the
final plat for the Meadows Addition, Section 6, Phase 2.
Co~missioner Scott seconded the motion; motion carried (6-0)
with Chairman Munsch and Commissioners Green, Gross, Redford,
Scott and Tunnell voting in favor of the motion.
Item 8:
Consider approval of a final plat for Park West Commerce
Center Addition (formerly Gateway Park @ Coppell), located at
the southwest corner of Southwestern Drive and Beltline Road, at
the request of Prentis/Copley Properties.
Director of Planning Gary L. Sieb introduced the item to the
Commission. Mr. Sieb stated that this is a 328 acre tract, with
the preliminary plat already approved. He also stated that
staff would recommend approval of this final plat, however, he
would like to point out that the Public Works Department has
several concerns, as outlined in their memo dated March 14,
1990. Mr. S/eh also stated that the applicant has included a
letter dated March 15, 1990, which says that they do agree to
follow through with all their construction drawings and
everything will be submitted for City approval within ninety
(90) days of this plat going to City Council.
Minutes of March 15, 1990
Planning & Zoning Commission
Page 4
DttAFT
More specifically, Mr. Sieb mentioned that the letter dated
March 14, 1990, and signed by Mr. Michael Tucker, Vice
President of Prentis, stated that all construction drawings
would be complete and submitted for City approval no later than
July 16, 1990.
Mr. Sieb also stated that Public Works has taken the stand that
sidewalks do need to be provided throughout this entire
project.
Mr. Mike Tucker of Prentiss Properties was present to represent
this item before the Commission. Mr. Tucker stated that they
feel they have worked out all of staff's concerns with their
letter dated March 15, 1990. He also stated that they had drawn
the plat to be consistent with the Thoroughfare Plan, which has
a six-lane right-of-way. He further stated that if Council
reduces the right-of-way to four lane divided, they would ask
Council to approve the plat with the condition that the
right-of-way be reduced to four-lane divided.
Following discussion Commissioner Gross moved to approve the
final plat for Park West Commerce Center with the condition that
they complete all the requirements outlined in the memo from the
Public Works Department, dated March 14, 1990, (ATTACHED) and
with the agreements stated in Mr. Tucker's letter of March 15,
1990 (ATTACHED). Commissioner Redford seconded the mot/on;
motion carried (6-0) with Chairman Munsch and Commissioners
Green, Gross, Redford, Scott and Tunnell voting in favor of the
motion.
Item 9: Consider approval of a preliminary plat for Gateway Business
Park Addition, located at the northwest corner of Freeport
Parkway and I.H. 635, at the request of Santa Fe Realty.
Director of Planning Gary L. Sieb introduced the item to the
Commission. Mr. Sieb stated that this subdivision plat also
relates to the thoroughfare amendment. He also stated that this
is a 103.82 acre tract of land, and that staff recommends
approval of this preliminary plat.
Mr. Weldon Davis of Santa Fe Pacific was present to represent
this item before the Commission. Mr. Davis stated that he felt
the plat was basically a very simple request, and that they have
no problem agreeing with staff conditions. Me further stated
that they will request Council to override the decision of the
Planning Commission to require a four-lane divided roadway, and
instead ask Council to approve an undivided street. Mr. Davis
stated that they feel the median would be a major detriment to
the industrial development.