9/14/00 memo re FP delay procesSep 14 O0 08:54a Gonzalez & Schneeber~ En~ 214-891-1437 p.1
Gonzalez & Schneeberg, Engineers &
2000
PROJECT MEMO
CLIENT: Dr. Tom Sherrill
PROJECT: Sherrili Vet Clinic
TO: Marcie Diamond
via fax: 972-304-7092
DATE: September 14, 2000
SHEET 1 OF 1 SHEETS
PROJECT NUMBER: 4647-00-08-06
FROM: Robert W. Schneeberg, P.E.
Topic: Delay of Processing Final Plat
As we discussed, we were unable to submit the plan revisions to your office by the required deadline
and since the site plan is being revised to adjust the size of the building it is apparent that the
approval of the site plan and the final plat should run concurrently. With this in mind, we
respectfully request that you delay processing of the final plat so that it may be approved with the
site plan revision.
We appreciate your assistance in the matter. Should you need any additional information or have
any questions, please call me at 214-891-1480.
Sincerely,
Robert W. Schneeberg, P.E.
cc: Dr. Tom Sherrill - fax: 972-393-2002
Mr. Leo Wehkamp - fax: 972-219-7099
4647memo.s14