Vlgs of C P3/FP-CS 910617 The City With A Beautiful Future
~June 17, 1991
P.O. Box 478
Coppell, Texas 75019
214 - 462 - 0022
Mr. Pat Atkins
Executive Vice President
Don Tipton, Consulting Engineers
6330 Beltline Road, Suite C
Garland, TX 75043
Re: Villages of Coppell PH-IIIA
Development Plans and Fee Assessment
Dear Mr. Atkins:
Attached please find four (4) approved sets of final construction plans
for the above referenced project. You will also find a list of the
development fee assessment related to this project, dated June 14, 1991.
Please provide a check in the amount of $58,125.42 made payable to the
City of Coppell and forward it to the attention of Ms. Carolyn Bebermeyer,
Finance Department, no later than Wednesday, July 10, 1991.
If you have any questions, please contact Ben dela Cruz or myself at (214)
393-1016. We appreciate your timely attention, and look forward to
working with you on this project.
Sincerely,
Acting City Engineer
MSD/bd
cc:
Gary L. Sieb, Director of Planning and Community Services
Steve Goram, Director of Public Works
Larry Davis, Construction Inspector
Taryon Bowman, P & Z Coordinator
Carolyn Bebermeyer, Finance Department
Steve Brooks, Grand Homes
VILLLTR
CITY OF COPPELL
DEVELOPMENT FEES
Date:
Project:
June 14, 1991
Villages of Coppell PH-IIIA
PAYABLE BY
TOTAL FEES 7-10-91
Park Fee Assessment
(65 lots X $150 Per Lot)
(50% due at final plat approval)
(50% due prior to bldg. permits
issuance
Water Impact Fee
(100% due prior to Council approval
of final plat)
Water Tap Inspection Fee
(100% due prior to issuance of
building permit)
Wastewater Impact Fee
(100% due prior to Council approval
of final plat)
Sewer Tap Inspection Fee
(100% due prior to issuance of
building permit)
Street Sign Assessment
(see attached)
Street Light Assessment
($292.60 X 7 poles)
(see attached)
Street Cut Permit
+ (2% of Construction cost)
in the amount of $362,148.00
provided by Don Tipton Engineers
TOTAL AMOUNT DUE:
TOTAL DUE BY JULY 10, 1991
$ 9,750.00
$ 42,900.00
6,500.00
$ 27,430.00*
$ 6,500.00
4,875.00
$ 42,900.00
$ 959.26 $ 959.26
$ 2,048.20 $ 2,048.20
100.00 $ 100.00
7,242.96 $ 7,242.96
$103,430.42
$ 58,125.42
$ 58,125.42
, NOTE:
IF PROPERTY TO BE DEVELOPED IS IN THE COPPELL MUNICIPAL UTILITY
DISTRICT #1, WASTEWATER IMPACT FEE SHALL BE ASSESSED, BUT SHALL
NOT BE COLLECTED UNTIL SUCH TIME AS AN INTERLOCAL AGREEMENT IS
MADE BETWEEN THE CITY AND MUD.
VILLA3A
COPPELL PUBLIC WORKS
Shohre Daneshmand, Acting City Engineer
Howard Pafford, Water Utilities Superintendent'
Water/Wastewater Fee Assessments for 'Villages of Coppell
Phase III A 6' ~
The following fees have been calculated for submittal to
developer.
Water Impact Fee
~ 5[0' ~ $[4' meters = ~E.$.U.'s 0660.00 each
100% due prior to Council approval' of final plat.
Wastewater Impact Pee
j,~518" x 314" meters = j,~E.$.U.'s 0422.00 each
100% due prior to Council approval of final plat.
Water Tap Inspection Pee
~Connections 0100.00 each
100% due prior to issuance of Building Permit.
Sewer Tap Inspection Pee
~Connections 0100.00 each
100% due prior to issuance Of Building Permit.
HLP/mp
PHASEIII.HLP
f o ~.-
The following assessment is being made in accordance with' the'-.i
City of Coppell Subdivision Ordinance Appendix A Chapter VI'ii A.
The following cost of those sign materials required · are based
on current pricing which is revi. ewed on a regular. basis.
~IG.b~ UNIT PR ICE QUANTITY EXTENDED PRICE
~53 ].0
"63 54
~65 1.2
$].1 G0
~.9~ as
_ toBo. ~g5
56'i, I
TOTAL
* Co:~-t breakdowns may be obtained from Public Works
17 ~ (.! tl (.' [; t . '
by written
COPPELL PUBLTC
DATE:
TO=
FROM=
RE:
February 7, 1991
Shohre Daneshmand, Acting City Engineer '"
Rick Wieland, Parks & Recreation Manager?~
Developmental Fees - Villages of Coppell - Phase III A 6' ~
Park Fees:
Villages of Coppell - Phase III A ~ ~
120 Lots @ $150.00 each
50% Due at t{me of final plat approval
50% Due prior to building permits being issued,
paid by builder(s)
$18,000.00
Should you have any questions regarding this matter, please contact
me.
RSW/mp
VIr~?.COPP. RSW
Street Li?_,ht Assessment
~or
The following assessment is being made in accordance with the
City of Coppell. Subdivision 'Ordinance Appendix A Chapter VI,
D. The following figures were supplied by T.P.. & L. for"
estimating this assessment.
$292.60 per light for every 200 feet of roadway.
You are being assessed for
to ~0 lights.
ft. of roadway, which totals
$292.60 x~P lights
~Before lights are installed contact Public Works -
Steve Goram, Director of Public Works or Per Birdaall, Street Foreman
ko have lighting plan approved.