Vlgs of C P4/FP-CS 910211COPPELL PUBLIC WORKS
MEMORANDUM
February 11, 1991
TO: Taryon Bowman, Planning & Zoning Coordinator
FROM .'
RE:
Shohre Daneshmand, Acting City Engineer ~
Final Plat - Villages of Coppell; Phase IV
We have reviewed the engineering plans for Villages of Coppell Phase IV as
submitted to our office for general conformance to the City of Coppell
Subdivision Ordinance and Standards. The following are our comments:
Minimum horizontal curvature, per Subdivision Ordinance, is 425 feet.
Provide a formal request for variance to the Subdivision Ordinance. The
recommended minimum horizontal curvature per the latest thoroughfare plan
is 300 feet.
The C factor for storm sewer design must be 0.65 and the rainfall
intensity I be 11.6 for minimum time of concentration (Tc) of 10 minutes.
If Tc = 15 minutes is used, please provide justification.
Provide an off-site drainage area map scale 1" = 200' or 300'..., etc.
Provide drainage area map for any off-site drainage.
Provide erosion control plan.
Show limits of 100 year floodplain on the final plat & drainage area map,
if applicable.
Ail provisions of the floodplain ordinance #87390 and the newly adopted
City-Wide Storm Water Master Plan must be complied with. We recommend
that there be no loss in valley storage.
Appropriate development fees must be paid - SEE ATTACHED
Provide a written response on all comments with explanations provided on
items not addressed as requested by staff.
A set of marked up plans and Public Works comments have already been
provided to Don Tipton Engineers for correction.
We have no objection to this project as long as all above comments are addressed.
MSD/sm
cc: Steven Goram, Director of Public Works
Ben dela Cruz, Engineer Technician
Public Works DRC Members
Pat Atkins, Don Tipton Engineering
VILLAGES OF COPPELL, PHASE IV
DEVELOPMENT FEES
Date: February 11, 1991
Street Sign Assessment
Street Light Assessment
Park Fee Assessment
90 Lots @ $150.00/ each
(50% due at time of final plat
approval)
(50% due prior to building
permits being issued
paid by builder)
Water Impact Fee
(100% due prior to Council approval
of final plat)
Water Tap Inspection Fee
(100% due prior to issuance of building
permit)
Sewer Impact Fee
(100% due prior to Council approval
of final plat)
Sewer Tap Inspection Fee
(100% due prior to issuance of building
permit)
Inspection Fee:
(2% of construction contract amount)
* Provide estimated construction costs
$1,144.06
$559.40
$13,500.00
$59,400.00
$9,000.00
$37,980.00
$9,000.00
DATE =
TO=
FROM=
COPPELL PUBLIC WOHK$
February I1, 1991 V /
Shohre Daneshmand, Acting City Engineer ,~A\
Howard Pafford, Water Utilities Superintende~
Water/Wastewater Fee Assessments for "Villages of Coppeli
Phase IV"
The following fees have been calculated
developer.
Water Impact Fee
90 5/8" x 3/4" meters = 90 E.S.U.'s 6660.00 each
100% due prior to Council approval of final plat.
Wastewater Impact Fee
90 5/8" x 3/4" meters = 90 E.S.U.'s 6422.00 each
100% due prior to Council approval of final plat.
Water Tap Inspection Fee
90 Connections 6100.00 each
100% due prior to issuance of Building Permit.
Sewer Tap Inspection Fee
90 Connections 6100.00 each
100% due prior to issuance of Building Permit.
HLP/mp
for submittal to
$59,400.00
$3 7,980. O0
$ 9,000.00
$ 9,000.00
PHASEIV.HLP
COPPELL PUBLIC WORKS
MEMORANDUM
DATE =
TO:
FROM:
RE:
February 8, 1991
Shohre Daneshmand, Acting City Engineer
Rick Wieland, Parks & Recreation Manager~
Developmental Fees - Villages of Coppell - Phase IV
Park Fees:
Villages of Coppell - Phase IV
90 Lots @ $150.00 each
50% Due at time of final plat approval
50% Due prior to building permits being issued,
paid by builder(s)
$13,500.00
Should you have any questions regarding this matter, please contact
me.
RSW/mp
VILLCOPP.RSW
The following assessment is being made in accordance with the
City of Coppell Subdivision Ordinance Appendix A Chapter VIII A.
The following cost of those sign materials required are based
on current pricing which is reviewed on a regular, basis.
UNIT PRICE
QUANTITY
EXTENDED PRICE
No Parking
Speed L J. mJ.t
Y ic ld
,Stop
.~.eat Name
SL'op & Street Combo
OTIIER
%
· ;,53 10
$63 5d
$65 12
:,q ]. 1 60
e'96 85
Cost breakdowns may be obtained, from Public Works by written
r e (.l u e s 't.
Street Light Assessment
for
The following assessment is being made in accordance with the
City of Coppell. Subdivision Ordinance ApPendix A Chapter VI,
D. The following figures were supplied by T.P. & L. for
estimating this assessment.
$292.60 per light for every 200 feet of roadway.
You are being assessed for ~O(~
to Iq lights.
ft. of roadway, which totals
$292.60 x ~ lights
*Before lights are installed contact Public Works -
Steve Goram, Director of Public Works or Per Birdsall, Street Foreman
to have lighting plan approved.