DRC commentsCOPPELL
Proiect ID PD-03-0069
Address 980 W Bethel Rd
CITY OF COPPELL
DRC REPORT
Project Name
COP?ELL
PD-185R-LI Coppell Industrial Addition (Tradepoi
Project Type
Application Date
Case Manager
Project Description
Re-Zoning PD
9/17/03
Marcie Diamond
98.84 acres of property from PD-185-LI to PD-185R-LI to attach a Detail Site Plan to allow for an approximate 350,183
square-foot expansion to the existing 600,000 square-foot building on Lot 1R and the development of an approximate
952,094 square-foot office/warehouse building on Lot 2
Agency
Building Inspection
Electric and Gas
Engineering
Fire Administration
Parks and Recreation
Planning Department
1 of 3
Reviewed By Review Date
Greg Jones 9/25/03
Jeff Curry 9/25/03
Teresa Turner 9/25/03
Travis Crump 9/25/03
John Elias 9/25/03
Mamie Diamond 9/24/03
Comments
No Comments Received
Zoning Change Acceptable
1. As I believe you are aware, the firs line for Building 1
is pressurized.
2. All water meters, fire vaults, etc. must be within the
ROW or in an easement.
3. Coordinate all work with plans for the futurs
improvements of Bethel Road. Contact Suzan Taylor,
CIP Coordinator, at 972-304-7019.
4. Are you proposing to construct the storm drain
system for Building 2 with the expansion of Building 17
5. Verify that enclosing the open channel within the
existing 20' drainage easement will not decrease the
capacity.
No Comments Received
No Comments
OVERALL COMMENT - NEED TO REDUCE THE
NUMBER OF SHEETS IN THE SUBMITTAL SET,
ELIMINATE THE REDUNDANCY, MAKE ALL PLANS
THE SAME SCALE·
Site Plan Sheets:
1. Eliminate Sheets A.1.1 and A.2.1, given that they are
at the same scale as sheet A.1.0.0, and add the Data
boxes to Sheet A.1.0.0
2. The name of this site plan is "Coppell Industrial
District, Lots 1R and 2, Block A". The buildings may still
be called Tradepoint Buildings 1 and 2.
3. Differentiate between Existing Building 1, it's
expansion, and Proposed Building 2, as well as existing
and proposed parking, truck courts, etc.
4. All easements (existing, proposed and to be
abandoned), need to be appropriately labeled and
consistent on all plan sheets and plat.
5. Will paving (fire lane and parking) be permitted over
the two drainage easements?
6. Data Boxes:
· Eliminate redundant notes.
· Revise the Zoning to PD185R-LI
· Indicate the existing office to warehouse ratio for
Mohawk and the required and provided parking.
· Indicate the maximum (typical) square footage (ratio) of
office to warehouse given the amount of parking
indicated.
7. Need to dimension driveways.
COP?ELL
Agency
Reviewed By
CITY OF COPPELL
DRC REPORT
Review Date
CO?PELL
Comments
8. Need to dimension existing rights-of-way for abutting
streets.
9. The Site Plan and Landscape Plan needs to be
consistent in terms of indicating required ~andscape
islands, especially in the future trailer parking areas.
· Are these areas going to be paved and landscaped
islands installed in the initial phase, or will it be
ground/cover landscaping until such time that trailer (or
car) parking is needed?
· A landscaped island is required every 15 parking
spaces if it is trailer or car parking.
10. A Note on Sheets A.1.1 and A.2.1 indicate that the
trash dumpster and compactor locations shall be
determined by the tenant, please revise the Note to
state that these shall not be located adjacent to Bethel
Road or Creekview Drive, and shall be located within
the truck court areas and be screened.
11. There is an existing, illegal, guardhouse on the
property. This needs to be removed. If a guardhouse
is desired, it must be compliant with the masonry
requirements, etc. and shown on the Site Plan,
Landscape Plan and Elevations. The port-o-potty must
also be removed·
12. Understanding that the applicant desires flexibility in
terms of parking, fa(;ade treatments, etc. depending on
the tenant, assurances need to be provided that all
future parking areas will be compliant with the
landscaping regulations as required in Article 31 of the
Zoning Ordnance and as specified in the existing PD
Conditions.
13. All existing PD Conditions will be carried forward to
this PD Amendment to attach a Detail Plan.
Landscape Plan Sheets
1. Make the Landscape Plan the same scale as the site
plan. Notes, tabulations, etc. may be on a separate
sheet(s), reduce the 12 sheet set to 2 (o r 3) sheets.
Analysis is difficult, at best, with the format as
submitted.
2, Provide dimensions and easement information on
the Landscape Plan,
3. Landscape Detail sheets (L2.13 and L·1.6): either
explain or delete references to Food Handler and Hours
of Operation.
4. Irrigation Plans DO NOT NEED TO BE
RE-SUBMI~I-ED
5. Need to designate the existing verses the proposed
landscaping in the detention area· The approved
Landscape Plan indicated approximately 100 caliper
inches of 3-inch Bald Cypress Trees to be installed in
the first phase of development.
6. It appears that this Landscape Plan is in general
accordance with the Landscape Plan approved in the
PD except for minor deviations in amount of building vs.
paving areas.
7. The Site Plan and Landscape Plan needs to be
consistent in terms of indicating required landscape
islands, especially in the future trailer parking areas.
· Are these areas going to be paved and landscaped
islands installed in the initial phase, or will it be
COFPELL
Agency
Reviewed By
CITY OF COPPELL
DRC REPORT
Review Date
COP?ELL
Comments
ground/cover landscaping until such time that trailer
parking is needed?
· A landscaped island is required every 15 parking
spaces if it is trailer or car parking.
Elevations
1. Building 1 - Sheet A4.1.2, Detail 1, labeled Front
Elevation Corner Entry, and indicates that this is for the
existing building., are revisions to the existing elevations
along Bethel Road proposed? These elevations do not
reflect the design of the existing building.
2. Building 1 Expansion, will the Front Corner Entries
along Creekview match the entries on Bethel Road?
(see 1 above)
3. Building 2
· Given that the west and east elevations are practically
identical, except for a random metal louver instead of a
dock door, again, we can reduce the bulk of paper
submitted by labeling them eastJwest elevations (typ.)
· Building l's entry features contain approximately 60%
glass (store front) Building 2 is proposed to be less
than 20% glass, it appears that the tilt wall is out of
porportion to the amount of glass. How will the
architecture, colors and materials from the 1 st to the
2nd building compliment each other?
· Given the size of this building, additional articulation is
recommended other than paint colors.
· Color renderings of all elevations both existing and
proposed would be helpful.
4. Signage-
· Per Section 12~29-3, Movement Control Signs can be a
maximum of 3 square feet. The proposed Directional
Signs exceed this size limitation.
· Sheets A4.1.2 and A4.2.2., Detail 1, Corner Elevations,
indicates a maximum 300 foot sign area. Per Section
12-29-4(D), In Industrial Zoned properties, the
maximum size of attached sign, located on walls 50 feet
or less in height can be a maximum of 200 square feet,
with maximum lettedlogo of 48 inches, revise
accordingly.
· Eliminate all redundant information.
COl'FELL
Project ID FP-03*0070
Address 980 W Bethel Rd
CITY OF COPPELL
DRC REPORT
Project Name
COl'FELL
Coppell industrial Addition (Tradepoint)
Project Type
Application Date
Case Manager
Project Description
Final Plat
9/17/03
Marcia Diamond
A replat of Lot 1, Block A, and a Final Plat of Lot 2, Block A, on 98.84 acres of property to allow for an approximate 350,163
square-foot expansion to the existing 600,000 square-foot building on Lot 1R and the development of an approximate
952,094 square-foot office/warehouse building on Lot 2
Agency
Building Inspection
Electric and Gas
Engineering
Fire Administration
Parks and Recreation
Planning Department
1 of
Reviewed By Review Date
Greg Jones 9/25/03
Jeff Curry 9/25/03
Teresa Turner 9/25/03
Travis Crump 9/25/03
John Elias 9/25/03
Marcia Diamond 9/24/03
Comments
No Comments Received
Plat Unacceptable, please contact Jeff Curry at
972-570-4126 to discuss Oncur easement
requirements.
1. In preparation for the future improvements to Bethel
Road, additional ROW dedications and temporary
easements are needed. I have included the necessary
documents to be included on the plat. Any ROW
dedications will be credited to the roadway impact fee
assessment.
2. Are you proposing to construct the storm drain
system for Building 2 with the expansion of Building 17
3. Verify that enclosing the open channel within the
existing 20' drainage easement will not decrease the
capacity.
4. It is difficult to determine what is proposed for
construction - Building 2 AND the expansion of Building
1 ? How will the construction phasing occur?
5. A firelane easement cannot overlap an existing
drainage easement.
6. Additional easements may be required during the
engineering review process.
No Comments Received
1. The name of the plat needs to remain Coppell
Industrial Addition, and this plat needs to be titled
Coppell Industrial Addition Lots 1R and 2, Block A,
Replat and Final Plat, being a replat of Lot 1, Block A,
and a Final Plat of Lot 2, Block A, of the Coppell
Industrial Addition.
· Correct all references to the name of the plat on page
2.
2. All easements (existing, proposed and to be
abandoned), need to be appropriately labeled and
consistent on all plan sheets and plat.
3. Will paving (fire lane and parking) be permitted over
the two drainage easements?
4. Correct the spelling of Hillwood's Address and the
typo's on page 2.
5. Revise curve data table to be in alphabetical/numeric
order.