CC approval on 7/6/04AGENDA REQUEST FORM
COPPELL
DEPT: Planning
DATE: July 6, 2004
ITEM #: 9
ITEM CAPTION:
PUBLIC HEARING:
Consider approval of the Four Seasons Addition, Lot 2R, (BCE Specialties, Inc.), Replat, being a replat of Lot 2 of
the Four Seasons Addition, to allow the construction of an approximate 57,302-square-foot office/warehouse on
4.1 acres of property located along at the southeast comer of Sandy Lake Road and Royal Lane.
GOAL(S):
APPROVED BY
CITY COUNCIL
ON ABO¥ E DATE
EXECUTIVE SUMMARY:
Date of P&Z Meetinm
Decision of P&Z Commission:
Motion to close the Public
Hearing and approve subject
to compliance with the
engineering comments.
M - York
- Brancheau
ote - 6-0
T unnell absent ' .-~ i!?
June 17, 2004
Approved (6-0) with Commissioners McCaffrey, Milosevich, Kittreli,
Halsey, Borchgardt and Reese voting in favor. None opposed.
Approval is recommended, subject to the following condition:
1 ) Compliance with the Engineering comments.
Staff recommends approval.
Agenda Request Form - Revised 02/04 Document Name: ~ 2Four Seasons RPL I-AR
CITY OF COPPELL
PLANNING DEPARTMENT
STAFF REPORT
CASE: Four Seasons Addition~ Lot 2R
(BCE Specialties, Inc.)~ Replat
P & Z HEARING DATE:
C.C. HEARING DATE:
June 17, 2004 (Continued from the Commission's May 20, 2004,
meeting.)
July 6, 2004
STAFF REP.:
Matt Steer, City Planner
LOCATION:
Southeast comer of Sandy Lake Road and Royal Lane.
SIZE OF AREA:
4.1 acres of property.
CURRENT ZONING:
LI (Light Industrial)
REQUEST:
Replat approval to allow the construction of an approximate
57,302-square-foot office/warehouse.
APPLICANT:
Page 1 of 4
Ovoler
Beth Cunningham
2860 Market Loop
Southlake, TX 76092
Phone: (817) 949-2030
Fax: (817) 488-9158
Architect
Hardy McCullah/MLM Architects, Inc.
Kyle McCullah
12221 Merit Drive, Suite 280
Dallas, TX 75251
Phone: (972) 385-1900
Fax: (972) 385-1937
Engineer
Pacheco Koch Consulting Engineers
C. Jack Evans
8350 N Central Expressway, Suite 1000
Dallas, TX 75206
Phone: (972) 235-3031
Fax: (972) 235-9544
Item # 5
HISTORY:
TRANSPORTATION:
In 1990, a Final Plat and Site Plan were approved for a 13.7-acre
tract of property. ~he original plans included the construction of a
152,000-square-foot building (existing) and a proposed Phase 2
expansion to include a 138,000-square-foot building on the property
adjacent to Sandy Lake Road, which was never constructed. In
1999, City Council approved a replat for the northern 4.1 acres to
make this tract a separate lot. This approval was subject to a
condition that any modification to the existing building would
require a site plan review and a replat.
The Planning and Zoning Commission denied the replat for this
property on May 20, 2004, due to changes that needed to be
made to the north and west elevations of the Site Plan package.
Both Royal Lane and Sandy Lake Road are projected to be C4D/6,
four-lane divided thoroughfares in a six-lane divided right-of-way.
SURROUNDING LAND USE & ZONING:
North- Vacant, LI (Light Industrial)
South - Stone Panels, Inc., LI (Light Industrial)
East - AmberPoint Business Park, LI (Light Industrial)
West - Vacant, LI (Light Industrial)
COMPREHENSIVE PLAN:
The Comprehensive Plan of May 1996 shows the property
as suitable for Light Industrial/Showroom.
DISCUSSION:
Page 2 of 4
This is a 4. l-acre replat of the Four Seasons Addition, Lot 2. A 57,302-
square-foot office/warehouse is proposed. BCE Specialties, Inc., an
elevator finishing company, will be the primary tenant and occupy 22,76 l-
square feet. The business does the interior finish-out of elevators, then
ships them to their final destination. The remaining six lease spaces will
range from 5,000- to 7,515-square feet, and the tenants are currently
unknown.
There are three proposed ingress/egress points (two from Sandy Lake and
one from Royal). The access point along Royal is shown at the south end of
the property, but will have to be relocated due to drainage concerns
regarding the location of a storm water inlet. The fire lane easement
encircles the building and is accessible off two of the three ingress/egress
Item # 5
points. The location of the fire lane easement will be need to be revised to
reflect the access point relocation along Royal. it will be reevaluated by the
Fire Marshal to ensure conformance with the City of Coppell standards.
The access point along Royal will not need to be relocated provided the
Engineering Department approves a modified drainage plan.
There is a 24' access easement depicted on the northeast comer of the
property. This will need to be extended to connect with the fire lane and be
renamed a fire lane and access easement.
There is a 24' fire lane and access easement shown connected by an
access easement to the east.
There are other minor technical details outlined in the plat conditions. After
those are met, the subdivision will meet the Subdivision Ordinance
requirements.
The technical details outlined in the plat conditions were met.
RECOMMENDATION TO THE PLANNING AND ZONING COMMISSION:
Staff recommends APPROVAL of the Replat, subject to the following conditions being
met:
2003.
7) Compliance with the attached Engineering comments.
ALTERNATIVES
1) Recommend approval of the request
Page 3 of 4
Item # 5
2) Recommend disapproval of the request
3) Recommend modification of the request
ATTACHMENTS: 1) Final plat
2) Engineering Comments
Page 4 of 4
Item # 5
SANDY LAKE ROAD
~1 . ~j~
- ? 2O04
oPMENT REVIEW COMMITTEE
I ENGINEERING COMMENTS
ITEM:
Four Seasons Addition, Lot 2R, (BCE Specialties~ Inc.), Replat~ being
a replat of Lot 2 of the Four Seasons Addition, to allow the construction of
an approximate 56,750-square-foot office/warehouse on 4.1 acres of
property located along at the southeast comer of Sandy Lake Road and
Royal Lane, at the request of C. Jack Evans, Pacheco Koch Consulting
Engineers.
STAFF REP.: Matt Steer PROJECT ID# RP-04-0020
DRC DA TE: April 29, 2004 and May 6,2004
CONTACT: Kenneth M. Griffin, P.E., Dir. o~CEngineering/Public Works 972/304-3686
COMMENT STATUS: ~FJ~r~J~4V~4?4z v~ FINAL RE!qtY..ED
Plat -
No comments.
Preliminary Grading Plan -
1. Regarding the note that says "Contractor to obtain permission in writing from property owner
prior to commencing offsite grading work"...the City will need that written permission
before the permit is issued.
2. There is an existing inlet at a low point in Royal Lane where you are showing to construct
your driveway. Due to the fact that it is a low point, the driveway should be relocated to
avoid the inlet.
Preliminary Drainage Plan -
1. Relocate driveway out of the way of the low point inlet in Royal Lane.
2. The timing of this project needs to be taken into consideration with the timing for the Sandy
Lake Road widening project. We expect that the road will be under construction beginning
in October of this year. if the drainage that is to be constructed with that project is not in
place, you will need temporary headwall structures on your outfalls, and some type of
temporary bridge structure for your driveways. Alternatively, you can construct the
driveways at a later date, but at any rate, coordination is a must for these projects.
Additional comments may be generated during full engineering review.