P&Z letter of approval-10/21/04COP?ELL
October 22, 2004
Mr. Brion Sargent
lA lnterior Architects
3232 McKinney Avenue, Suite 970
Dallas, TX 75204
RE: Gateway Business Park No. 2~ Lot 2~ Block A (Avaya)~ Site Plan Amendment
Dear Brion:
This letter is to inform you that the Gateway Business Park No. 2, Lot 2, Block A (Avaya),
Site Plan Amendment, to allow for the addition of three air conditioner chillers, an
additional transformer and modification of the previously approved generator plan on
property located at 1111 Freeport Parkway, was recormmended for approval by the Coppell
Planning and Zoning Commission on Thursday, October 21, 2004, subject to the following
conditions:
1) A tree removal permit will be required if trees are removed.
2) Dimension transformer sizes.
3) Add Live Oak trees in front of chiller screening wall.
4) Abide by comments of other departments (Engineering)
The date scheduled for consideration by the Coppell City Council is Tuesday, November 9,
2004, at 7 p.m. A representative for this case must be present at this meeting, which will be
held in Council Chambers at City Hall. Failure to represent this item may result in the
denial of this application. City Council has instructed staff to include in its agenda packets
only those items that accurately reflect conditions as reconunended by the Planning and
Zoning Commission. Therefore, please submit to the Planning Department three (3) folded
copies (24"x36") of revised plans on or before 12 noon, Wednesday~ October 27th. Also,
please submit one (1) 8 ~/2 x 11 paper reduction, along with one jpg, tiff, pdf or similar
electronic file.
If you have any questions, please contact the Planning Department at (972) 304-3678.
Sincerely,
b, A.I.C.P.
file
COl'FELL
CITY OF COPPELL
2nd DRC REPORT
COI I ELL
Project ID
Address
Project Type
~pplication Date
Case Manaqer
Proiect Descripliog
SPR 04 0063
1111 FreepodPkwy
Project Name
Gateway Business Park No2 Lot2 BlockA(Ava
Site Plan Amendment (Revision)
9/22/2004
Gary Sieb
To allow for the addition of three air conditioner chillers along the east side of the existing building
A~ en_c2~
Engineering
1 of 1
Comments
1 It appears this work may impact drainage in the area
2 There is both an 8" and a 3" water line in the proposed construction area
3 This work will require engineered drawings and a permit from the Engineering Department