Proiect 10
FP-07 -0076
Address Coppell Rd
Proiect Name
The Village At Old Coppell & Coppell Ser. Cntr
Proiect Type Final Plat
Application Date 6/22/2007
Case Manaaer Matt Steer
Proiect Description being a replat of Lot 1, Block A, Coppell Service Center and a final plat of the Village at Old Coppell to establish final
property boundaries of the Village at Old Coppell and reconfigure the Coppell Service Center boundaries to establish fire
lane and utility easements to allow the construction of a event center, two retail/hotel buildings, a pet bed and
Agency
Building Inspection
Electric
Engineering
1 of 1
Review Date
8/29/2007
8/30/2007
8/28/2007
Reviewed By
Greg Jones
Jeff Curry
Michael Garza
Fire Administration
Tim Oates
8/30/2007
Parks and Recreation
Planning Department
John Elias
Matt Steer
8/29/2007
8/30/2007
Comments
1. No comments.
No Comments Received
1. 15' utility easement and TXU easement should be
abandoned by separate instrument.
2. The word "Utility" should be removed from the 24'
fire lane and mutual access easement.
3. Ensure that the Property owners agreement
includes the maintenance of utilities.
4. Do not place vaults in the roadway.
1. Curve Data Table needs to include all curves.
2. Remove Fire Dept. Connection notes from
Preliminary Water plan.
No comments
1. Separate plats Village at Old Coppell and Coppell
Service Center into two documents.
2. Retitle Lot 8, Block 1 to Lot 1 R, Block 1, Coppell
Service Center and retitle Lot 1, Block 1, Coppell
Service Center to Lot 1 R, Block 1, Coppell Service
Center and remove lot line between the two. Ensure
title block reflects correct name of plat.
3. Include Service Center Lot lines and revisions
according to what is determined on the Senior Center
Plat. Coordinate with BW2 Engineers for exact
boundaries.
4. Abandon easements located on the Village at Old
Coppell portion of the plat by separate instrument as
these were dedicated by separate instrument.
5. Submit the final property owner's association
maintenance agreement.
KP A consulting inc
Pat Atkins, President
1801 Gateway Blvd., Suite 101, Richardson 75080
Tel: 972-644-2800, Fax: 972-644-2817
September 11, 2007
City of Coppell
255 Parkway Boulevard
Coppell, Texas 75019
-I
RE: THE VILLAGE AT OLD COPPELL
COPPELL, TEXAS
DRC REPORT
l~evlsed
P&7
Comments & ReSDOnSe
BUILDING INSPECTION
Greg Jones
Comment 1: No Comments
Response: N/A
ELECTRIC
Jeff Curry
Comment 1: Contact No Comments
Response: N/ A
ENGINEERING
Michael Garza
Comment 1: 15' utility easement and TXI easement should be abandoned by separate
instrument.
Response:
We will provide separate instruments.
Comment 2: The word "Utility" should be removed from the 24' fire lane and mutual access
easement.
Response:
Completed
Comment 3: Ensure that the Property owners agreement includes the maintenance of utilities.
Q:\Files\Pat\Comment_ Responses _ village@_old_coppell_DRC_report.doc
Response:
Completed
Comment 4: Do not place vaults in the roadway.
Response:
We have moved the vaults.
FIRE ADMINISTRATION
Tim Oates
Comment 1: Curve Data Table needs to include all curves.
Response: Completed
PARKS AND RECREATION
John Elias
Comment 1: No Comments
Response: N/A
PLANNING DEPARTMENT
Matt Steer
Comment 1: Separate plats Village at Old Coppell and Coppell Service Center into two
documents.
Response:
We have separated the documents.
Comment 2: Retitle Lot 8, Block 1 to Lot lR, Block 1, Coppell Service Center and retitle Lot 1,
Block 1 Coppell Service Center to Lot lR, Block 1 Coppell Service Center and
remove lot line between the two. Ensure title block reflects correct name of plat.
Response:
Completed
Comment 3: Include Service Center Lot lines and revisions according to what is determined on
the Senior Center Plat. Coordinate with BW2 Engineers for exact boundaries.
Response:
Completed
Comment 4: Abandon easements located on the Village at Old Coppell portion of the [plat by
separate instrument as these were dedicated by separate instrument.
Response:
Completed
Comment 5: Submit the final property owner's association maintenance agreement.
Response:
Included