Eng. memo-Chrono. order-plattngMEMORANDUM To: From: RE: Date: Alan D. Ratliff, City Manager Doug Stevens, Engineering Technician Chronological Order for the Platting of Coppell Switching Station 3/5/93 February 13, 1989 TU Electric submitted a Preliminary Plat Application and Special Use Permit for the building permit for a proposed substation to be constructed on the northwest comer of the intersection of Thweatt Road and Coppell Road. March 16, 1989 (2) PLANNING DEPARTMENT STAFF REPORTS. The first stated that..." Staff Has no objections to this (SUP) request." and the other that... "Staff has no objections to the preliminary plat provided the applicant commits to either dedicating the Brazos Electric Power Co-op, Inc frontage as Right-of-Way to the City, or produce documentation to the City evidencing this request to be an unreasonable request due to legal complication and leaving the dedications in the form of an easement to the City." March 16, 1989 MINUTES of March 16, 1989 March 28, 1989 EASEMENTS to City of Coppell for Widening of Coppell Road and Thweatt Road. Includes Draft of Escrow Agreement. March 30, 1989 LETTER to Mr. John T. McAlpin, Manager of Engineering Design, TU Electric from Billy W. Dyess, Manager-Project Construction and Engineering, Brazos Electric Power Cooperative, Inc. Re: time required to execute a Fee Simple Land Transaction April, 6, 1989 LETTER To Mr. Kevin Peiffer, City of Coppell Engineering Department from Mark Carpenter, Supervisor Substation Engineering, TU Electric. Re: submittal of Final Application and Special Use Permit (SUP) for the building permit for electric substation April 11, 1989 AGENDA REQUEST FORM for City Council Meeting 4/11/89, Item No. 8, Item Caption: Public Hearing to consider approval of a zoning change Case #S-1041, from (LI) Light Industrial, to (LI-SUP) Light Industrial Special Use Permit, for the construction of an electric switching station, on a 3.407 acre site located on the northwest comer of Thweatt Road and Coppell Road, at the request of TU Electric. APPROVED, with stipulations: 1. Applicant to work with staff to provide landscaping comparable to that at Hackberry substation City Manager' s Comments/Recommendation, Minutes of 3/16/89 and 4/11/89 Meeting attached. April 11, 1989 AGENDA REQUEST FORM for City Council Meeting 4/11/89, Item No. 9, Item Caption: To consider approval of a preliminary plat for the Coppell switching Station, on a 3.407 acre site located on the northwest corner of Thweatt Road and Coppell Road, at the request of TU Electric. APPROVED, with stipulations: 1. Approval of Variances: a. allow rock rather than concrete on the yard b. allow rock rather than concrete on driveway with the exception when the road is improved the driveway will become concrete. c. allow open ditch drainage until the road is widened at which time drainage will be enclosed. d. easement requirements to be worked out with staff prior to final plat. Minutes of 3/16/89 and 4/11/89, and additional copy of Agenda Request Form for 4/11/89 attached with separate comments. April 11, 1989 MINUTES of April 11, 1989 April 14, 1989 LETI'ER to Kevin E. Peiffer P.E., City of Coppell from Mark Carpenter, TU Electric. Re: removal of request for variance of landscaping requirement on the final plat package for Coppell Switching Station. April 18, 1989 LETTER to Mr. Mark Carpenter of TU Electric from Russell R. Doyle, P.E., City Engineer. Re: Coppell Switching Station Final Plat April 20, 1989 PLANNING & ENGINEERING DEPARTMENT STAFF REPORT - TU Electric requested Approval of Final Plat. Staff's requests were that the following items be agreed to prior to approval of the final plat: (1) Separate dedication instruments for future road easements be executed and filed with the City prior to Council Approval. (2) Items per the City Council on April 11, 1989 (Preliminary Plat) (3) Applicant agree to enter into escrow agreement with the City of Coppell for their pro-rata share of improvements to Thweatt and Coppell Roads. (Total Due: $140,204.00) (4) Add note to the plat that after adjacent roads are improved, within 30 days thereafter, applicant shall install landscape as required per the Streetscape Plan. The copy of the Staff Report found contains additional handwritten comments suggesting that Larry (Jackson) has item number (1). May 5, 1989 Letter to Mr. Mark Carpenter of TU Electric from Russell R. Doyle, P.E., City Engineer May 9, 1989 AGENDA REQUEST FORM, Item Caption: Consideration of a Final Plat for the Coppell Switching Station, on a 3.407 acre site located on the northwest comer of Thweatt Road and Sandy Lake Road, at the request of TU Electric. (DENIED 7-0) May 9, 1989 MINUTES of May 9, 1989 May 22, 1989 MEMORANDUM from Alan D. Ratliff, City Manager to Mayor and City Council. Subject: Meeting 5/17/89 ADR/Larry Jackson/Tom Parsons and Other TU Representatives. Ref: TU Final Plat June 5, 1989 LETTER sent to Mr. Tom Parsons from Alan D. Ratliff, City Manager confirming the placement of an item on Coppell's City council Agenda for June 13. "As discussed, I will recommend to the Council that TU be relieved of the cost of paving, contingent upon TU's dedication of right-of-way for both Coppell and Sandy Lake Roads, as well as your agreement to donate the right-of-way for the old Brazos Power and Light easement which parallels Sandy Lake Road. TU Electric will pay for relocation of this line at the time the City initiates the upgrade and improvement of "Sandy Lake Road .... We will also require that TU provide executed easements for the right-of-way for Coppell and Thweatt Roads." June 13 1989 AGENDA REQUEST FORM, Item Caption: Re-consideration of a Final Plat for the Coppell Switching Station, on a 3.407 acre site located on the northwest comer of Thweatt Road and Sandy Lake Road, at the request of TU Electric. June 13, 1989 MINUTES of June 13, 1989 August 14, 1990 AGENDA REQUEST FORM, Item Caption: To consider an ordinance for Case #S-1041, to change the zoning designation from (LI) Light Industrial to (LI-SUP) Light Industrial Special Use Permit, on a parcel of land located at the northwest corner of Coppell Road and Thweatt Road, for the operation of an electric substation, and authorizing the Mayor to sign. December 18, 1992 LETTER to Mr. Gary L. Sieb, Director of Planning & Community Services from Albin A. Petter, P.E., Brazos Electric Cooperative. interconnection between Brazos electric and TU at the Coppell substation. Re: December 23, 1992 ZONING APPLICATION, 2.726 acres NW comer of the Intersection of Thweatt and Coppell Road. (2) letters attached from Brazos Electric Cooperative. January 6, 1993 LETTER to Coppell City Council & Coppell Planning & Zoning Committee. Re: Zoning Application, Coppell Substation, Brazos Electric Power Cooperative, Inc. January 11, 1993 MEMORANDUM to Taryon Bowman, Planning & Zoning Coordinator from Kenneth M. Griffin, P.E., City Engineer. Re: Engineering Development Review Comments for the Meeting of December 30, 1992 and January 7, 1993 January 15, 1993 MEMORANDUM to Gary Sieb, Director Planning &' Community Services from Kenneth M. Griffin, P.E., City Engineer. Re: Coppell Switching Station SUP for Amendment to the Site Plan January 21, 1993 STAFF REPORT, Case # S-1041(A)-Electrical Substation for P & Z Hearing Date: 1/21/93 and C.C. Hearing Date: 2/9/93 January 22, 1993 LETTER to Mr. A1 Petter, Brazos Electric Cooperative from Gary L. Sieb, Director Planning & Community Services. Re: Case # S-1041(A) Electrical Substation. Request for approval of a zoning change request, Case # S-1041(A), for approval of a Special Use Permit, was recommended for approval by the Coppell Planning and Zoning Commission on Thursday January' 21, 1993, with conditions: 1) that TU Electric and Brazos Electric Cooperative would enter into an agreement with the City of Coppell that relieves both electric companies of paving Thweatt Road and Coppell Road, contingent upon the dedication of right -of-way for both roads to the City of Coppell, and also donation of right-of-way for the old power and light easement, which parallels Sandy Lake Road, 2) TU Electric and/or Brazos Electric Cooperative will pay for relocation of the line at the time the City indicates the upgrade and improvement of Sandy Lake Road, 3) more complete landscaping along Thweatt and Coppell Roads when the roads are finished, 4) and including the four variances requested February 8, 1993 FACSIMILE from Gary Sieb to Steve Goram of a draft copy of Relocation Agreement between Brazos Electric Power Cooperative,Inc., TU Electric, and the City of Coppell. Fax cover includes comments from Gary Sieb. February 9, 1993 FACSIMILE from Albin A. Petter, Brazos Electric Power Cooperative, Inc. to Taryon Bowman. Draft copy of an Agreement between Brazos Electric power Cooperative, Inc., TU Electric Company, and the City of Coppell, Texas. February 9, 1993 AGENDA REQUEST FORM, Item Caption: To consider approval of a zoning change request, Case #S-1041(A), for an amendment to an SUP site plan for an electrical substation, located at the northwest corner of Thweatt Road and Coppell Road, at the request of Brazos Electric Cooperative, Inc. (DENIED 7-0). Copy of Minutes attached. February 15, 1993 LETTER sent to Mr. A1 Petter of Brazos Electric Cooperative informing him that the request for approval of a zoning change request was denied. February 16, 1993 LETTER to Gary Sieb, A.I.C.P., Director of Planning & Community Services from Albin A. Petter, P.E., Brazos Electric Cooperative. Re: placement on the Agenda for the February 23, 1993 City Council meeting. February 18,1993 FACSIMILE from Nichols, Jackson, Kirk & Dillard to Mr. Alan D. Ratliff, City Manager. Re: TU Electric & Brazos Substation, Coppell Road & Thweatt Road. Included a LETTER to Mr. Russell Doyle, City Engineer from Lawrence W. Jackson dated 4/24/89. Re: TU Electric Escrow Agreement, and a LETTER to Mr. Frank Trando, Finance Director from Lawrence W. Jackson dated 4/24/89. Re: TIJ Electric Street Escrow Agreement, and an unsigned copy of a Street Escrow Agreement. February 25, 1993 FACSIMILE to Kenneth M. Griffin, P.E., City Engineer from Vicki McDaniels, Brazos Electric Cooperative. Includes EASEMENTS of Brazos line along Thweatt and Coppell Road. February 26, 1993 LETTER to Gary Sieb, A.I.C.P., Director of Planning & Community Services from Albino A. Petter, P.E., Brazos Electric Cooperative. Re: SUP Application, Case #S-1041(A) March 2, 1993 LETTER to Mr Gary Sieb, A.I.C.P., Director of Planning & Community Services from Kirk A. King, District Manager, TH Electric Company Re: Paving Assessment at Coppell Substation; Power Lines along Sandy Lake Road (Existing and Contemplated) March 9, 1993 AGENDA REQUEST FORM, Item Caption: Brazos Electric request to reconsider denial of zoning Case #S-1041(A), for an amendment to an SUP site plan for an electrical substation, located at the northwest comer of Thweatt Road, Sandy Lake Road and Coppell Road. 2/16/93 LETTER and 2/26/93 LETYER Attached.