Admin Approval 10-18-22 Approval Correspondence1
Matt Steer
To:Chris Delgado; Mahadin, Tariq; Jack Basil Foster
Cc:Steve Pendleton; STEPHEN SCHUBERT
Subject:RE: Pathgroup - Wintergreen - additional details
Sorry for all the back and forth!
This will suffice. I will print this email and save it with the approved Site Plan Amendment. @Jack Basil Foster please
note the following for the permit:
Both RTU-LAB-C Unit & Refrigeration units will be screened with the screening as depicted below. They will meet or
exceed the height of the objects which they are proposed to screen on the south side of the building.
Thanks,
Matt
Matthew Steer AICP, LEED® Green Associate
Development Services Administrator
City of Coppell, TX
972-304-3559 (office)
469-460-1807 (cell)
www.coppelltx.gov
From: Chris Delgado <Chris.Delgado@brandt.us>
Sent: Tuesday, October 18, 2022 1:54 PM
To: Matt Steer <MSteer@coppelltx.gov>; Mahadin, Tariq <Tariq.Mahadin@kimley-horn.com>
Cc: Steve Pendleton <Steve.Pendleton@brandt.us>; STEPHEN SCHUBERT <Stephen.Schubert@coppelltx.gov>
Subject: RE: Pathgroup - Wintergreen - additional details
Matt, per our phone call, and the site plan and permit set of drawings submitted, both RTU-LAB-C Unit & Refrigeration
units will be screened with the same material. See snip below from AS1.21 SCREEN WALL DETAIL (it shows the screen
wall detail).
The screen wall is a manufactured product, and is not “designed” by our architect or engineers. There are no additional
isometrics or renderings. The structural steel and concrete dimensions designed by the structural engineer are shown on
the drawings we have already submitted. See snip below from S.1.10 (it shows dimensions requested).
Does this suffice?
2
RTU PLATFORM/SCREEN WALL DIMENSIONS
3
REFRIGERATION UNIT/SCREEN WALL DIMENSIONS
4
Thank you,
CHRIS DELGADO, P.E. | SENIOR DESIGN BUILD PM
THE BRANDT COMPANIES, LLC
M 210.441.9185
Chris.Delgado@brandt.us | www.brandt.us
From: Matt Steer <MSteer@coppelltx.gov>
Sent: Tuesday, October 18, 2022 11:41 AM
To: Mahadin, Tariq <Tariq.Mahadin@kimley-horn.com>
5
Cc: Chris Delgado <Chris.Delgado@brandt.us>; Steve Pendleton <Steve.Pendleton@brandt.us>
Subject: RE: Pathgroup - Wintergreen - additional details
Tariq,
The isometric view shows this:
This too should be screened. We discussed it needing to be screened with the same material.
I am looking for a similar isometric view of the screening for the refrigeration units as well with dimensions.
Please upload those, so I can sign off on the Site Plan Amendment.
From: Mahadin, Tariq <Tariq.Mahadin@kimley-horn.com>
Sent: Tuesday, October 18, 2022 10:49 AM
To: Matt Steer <MSteer@coppelltx.gov>
Cc: Chris Delgado <Chris.Delgado@brandt.us>; Steve Pendleton <Steve.Pendleton@brandt.us>
Subject: Pathgroup - Wintergreen - additional details
Matt, we have uploaded on the city website additional details per your request. The two sheets we uploaded now are:
M-301. Pod A RTU ISOMETRIC (it show an isometric view of the equipment)
AS1.21 SCREEN WALL DETAIL (it shows the screen wall detail)
The full set of MEP and Arch plans have been submitted to the city (permitting department). Please let us know if you
need anything else.
Thank you
6
Tariq Mahadin, MLA, ASLA
Kimley-Horn | 2201 W Royal Ln #275, Irving, TX 75063
Direct: 469 965 4908 | Mobile: 214 918 8842
Connect with us: Twitter | LinkedIn | Facebook | Instagram | Kimley-Horn.com
Celebrating 15 years as one of FORTUNE’s 100 Best Companies to Work For
CAUTION: This email originated from outside of the organization. Do not click links, open attachments, or take any action in
response to this email unless you recognize the sender and know the content is safe.